That the Committee for Economy and Skills: 1. Noted the update of the BTQ LLP outlined in the report. 2. Noted the Executive Director Growth and Regeneration has taken all necessary steps to terminate the Agreement for Lease and recover possession of Redcliffe Wharf site and return the £516,000 Brownfield Land Release Fund. 3. Authorised the Executive Director Growth and Regeneration in consultation with the Director of Finance to agree the terms for, and thereafter conclude, option agreements (and associated documentation) with the BTQ LLP for Redcliffe Wharf (as identified at Appendix A3 subject to satisfaction of the best consideration test being met under section 123(1) Local Government Act 1972;
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
1. This report updates members of the Economy and Skills Committee on the work of the BTQ LLP during 2024/25. The report provides background to the project, details of some of the progress and highlights achieved in the first year of BTQ LLP. 2. The report provides information on the master-planning process for the St Philip’s Marsh area of Bristol Temple Quarter, and the emerging engagement plan for this work. 3. To note an alternative delivery strategy for Redcliffe Wharf is required. 4. To delegate authority to the Executive Director Growth and Regeneration to establish if terms can be agreed with BTQ LLP to incorporate the site within BTQ. If an agreement can be reached, approval is sought to put an option agreement on Redcliffe Wharf in favour of the BTQ LLP.
Evidence Base / Options to consider:
Bristol Temple Quarter Context Bristol Temple Quarter (BTQ) is one of Europe’s most ambitious regeneration projects. It aims to deliver at least 10,000 new homes, space for 22,000 jobs, and new and improved sustainable infrastructure and public spaces. BTQ comprises approximately 135 hectares in the heart of Bristol, close to a number of key city centre destinations, including Bristol Temple Meads mainline railway station, Bristol’s prime commercial area, the rejuvenated harbourside and the historic Redcliffe district. This location also provides important connections to several established residential areas, including Brislington, Barton Hill and Totterdown.
The project is split into two principal delivery phases, Temple Meads West, comprising of the land to the west of Bristol Temple Meads station, and St Philip’s Marsh. Maps of the project area, as well as other 1 Version January 2024 photographs, are included at Appendix A1. Temple Meads West presents the opportunity for comprehensive and coordinated delivery of sites in public ownership.
Regeneration of Temple Meads West will serve as a catalyst to support the longer-term opportunity at St Philip’s Marsh to deliver significant housing and employment outputs for Bristol and the region. Already, there is considerable private development of sites within St Philip’s Marsh, either proposed, in planning, or being constructed. There is also a strong employment base in the area with approximately 180 businesses currently located in the area. The area also requires significant investment in infrastructure, flood resilience, and public transport, alongside investment in the other infrastructure required to support good lives.
In this context and noting the scale of the opportunity at St Philip’s Marsh, it is essential Members are meaningfully engaged in the masterplanning process, to ensure the transformation of the area, matches the city’s ambition and regeneration approach. Further detail on St Philip’s Marsh and the approach to public engagement is set out below.
Bristol Temple Quarter Limited Liability Partnership In November 2023 BCC’s Cabinet authorised entering into arrangements for a Joint Delivery Vehicle to deliver the regeneration of BTQ and enter into the Shareholders’ Agreement with all other BTQ Partners. Cabinet also authorised putting option agreements in place with the delivery vehicle for parcels of land within council ownership within Temple Meads West.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingRESOLVED; To approve the minutes of the meeting on the 30th March 2026. On the motion of the Chair, seconded by Counc...
BNET Business Plan Outline ProposalThe Committee for Economy and Skills RESOLVED to: Note the BNET business plan framework and the continued development...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.