Resolved
The Committee
Strategy and Resources Policy Committee decided this item on Monday 14 April 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee
Appendix A1 – IT for Corporate Landlord Project - Further Information Project Goal: To successfully deliver the IT solution(s) necessary to enable the Corporate Landlord operating model and associated savings.
Project Drivers: £2.6bn property assets are owned by Bristol City Council, currently managed across fragmented IT systems, spreadsheets, documents and email Significant lack of historic investment in property & FM IT over past 10 years – well out of line with other councils, and organisations with this scale of property portfolio Property-level cost data is only available for a limited number of operational buildings and is not complete. Information for property-related decisions must be collated manually across multiple sources. Information is gathered piecemeal on request, creating bottlenecks and restricting opportunities to plan. Compliance and condition cannot be easily understood across the property portfolio, increasing risk. Investment in IT is fundamental to enable the new operating model and savings by Corporate Landlord and critical disposal decisions;
Target Benefits: This project will enable a centralised corporate landlord function to operate efficiently, with reduced manual processing and improved access to property-related data. • There is an additional cost to the council to pay for the annual running costs of the IT, which is off-set by the efficiency savings delivered through the corporate landlord and new Hard FM contract; • Costs will be avoided to manually collate information for decision making, commissioning, planning and to fulfil information requests, as much of this will be automated through the new IT. • Staff will have access to the data they need to do their job; Managers have access to the insights they need to manage their functions; Decision makers have the property and financial information they need to make informed decisions • There will be a greater awareness of risks, enabling improved compliance and risk management.
Main Deliverables: The project was re-launched in March 2024 as part of the Property Programme, and has worked closely with the other Corporate Landlord changes being implemented.
Achieved to Date: Future delivery: Timescale Business case approved by CLB Sept 2024 Award contract with IT provider May 2025 Requirements gathered for a Property Asset Commence contract July 2025 Management Solution IT design (including integrations with other IT Finalise IT design with IT provider July 2025 systems) Launched tender Jan 2025 User testing complete Dec 2025 Planned implementation IT system go-live Feb 2026 Data cleansing commenced Project closure May 2026
Risks and Issues: The project is managing the following critical risks and issues
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
10.2 App A1: IT for Corporate Landlord Project Further InfoAppendix | 173 KB | DownloadRead as text |
PDF |
10.3 App B1 EQIA 100TSAppendix | 402 KB | Download |
PDF |
10.4 Appendix B2 EQIA TBYSAppendix | 421 KB | Download |
PDF |
10.5 App B3 EQIA Disposals and Estate RationalisationAppendix | 294 KB | Download |
PDF |
10.6 App B4 EQIA Print and MailAppendix | 387 KB | Download |
PDF |
Property Transformation Programme: Approval to spend against earmarked 25/26 budget, approval for IT Corporate Landlord contract award, and quarterly updateDecisions | 321 KB | Download |
Follow Strategy and Resources Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2026 | Medium Term Financial Strategy and Capital Strategy 2027-28That the Committee for Strategy and Resources: 1. Noted the outlook and projections within the Medium Term Financial ... | Noted | Open |
| 12 Oct 2026 | Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ... | Noted | Open |
| 12 Oct 2026 | Private Water DistributionThat the Committee for Strategy and Resources: 1. Approved the approach taken to manage this area of emerging risk. 2... | Approved | Open |
| 12 Oct 2026 | Procurement of Display, Exhibition and Signage ServicesThat the Committee for Strategy and Resources: 1. Approved the procurement of a multi-supplier framework for Display,... | Approved | Open |
| 12 Oct 2026 | Arts Council England’s National Portfolio Organisation Funding Round 2028 – 2033That the Committee for Strategy and Resources: 1. Approved the proposal for Bristol Museums and Museum Development So... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.