Children and Young People Policy Committee, Thursday 30 April 2026 at 5.00pm

Children and Education Transformation Update

Approved Committee 4 papers

AI summaryChildren and Young People Policy Committee approved the Families First programme, authorising £2.6m of transformation spending for 2026/27. The programme will continue as a new Stable Homes programme targeting £15.3m in savings.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFamilies First programme continuation approved
Money£2.6mTransformation funding requested for 2026/27
What happens nextAugust 2026Update report on transformation portfolio
Who it affectsChildren and familiesChildren in care and SEND services in Bristol

What was decided

The Committee approved the Families First programme, to continue through a newly formed Stable Homes programme in 2026/27. Report P51, P61

The Executive Director for Children and Education was authorised, in consultation with committee chairs and the Director of Finance, to implement the programme within the £2.6m budget envelope, subject to Strategy and Resources Committee approval. Report P62

The Committee acknowledged the full scope of the Children and Education transformation portfolio for 2026/27 and noted a further update report will come to committee in August 2026. Report P63, P64

Why

The programme is expected to deliver £15.3m of savings in 2026/27, mainly by reducing reliance on high-cost external placements and increasing use of in-house and family-based provision. Report P55, P56

Officers judged it critical to continue the programme to maintain the financial and operational improvements set out in the Families First business case. Report P58

Outcomes reported so far include 37 children supported to leave external residential homes since February 2025, and 78% of families staying together after involvement with Connecting Families. Report P34, P40

What happens next

Formal allocation of the £2.6m transformation fund for 2026/27 will be requested at the Strategy and Resources Committee on 26 May 2026. Report P52

Programme focus will move to an embed and sustain phase, with sustainability planning monitored through performance governance. Report P50

An update report on progress of the transformation portfolio will be brought back to committee in August 2026. Report P64

The money

  • £2.6m Transformation funding requested for 2026/27 Report P1, P52
  • £15.3m Total savings target for Stable Homes Programme in 2026/27 Report P55, P56
  • £1.47 million Final two payments to Newton (transformation partner) Report P79
  • £0.9m Planned spend on additional staff to oversee transformation in 2026/27 Report P52, P79
  • £0.2m Held back as contingency Report P52, P79
  • £6.6m Savings delivered by Families First in 2025/26 Report P75
  • £65m Cumulative financial benefit over the life of the Medium-Term Financial Plan Report P31
  • £53.1m Education capital programme to deliver 569 new specialist provision places Report P12
  • £7.55 million Planned council contribution to High Needs deficit in 2026/27 under Safety Valve Report P16

Options considered

  • Chosen: Continue Families First through a new Stable Homes programme in 2026/27 with £2.6m of transformation funding. Needed to deliver the financial and operational improvements set out in the Families First business case and £15.3m of 2026/27 savings Report P51, P55, P57, P58
  • Rejected: Formally close the programme on 31 March with no ongoing Families First transformation, relying on operational teams. Would not offer sufficient resource or strategic impetus to deliver the required financial and operational improvements Report P57, P58

Implications

  • Financial: £2.6m of transformation funding requested for 2026/27, subject to approval at Strategy and Resources Committee on 26 May 2026; transformation funding is budgeted to reduce to £0.5m in 2027/28. Report P52, P80
  • Financial: Stable Homes Programme brings interdependent savings proposals totalling £15.3m in 2026/27, including £2.5m of undelivered 2025/26 over-delivery and £10m of additional Families First savings. Report P55, P56, P76, P77
  • Staffing: An in-house programme lead and two further service change leadership posts will be funded, plus an HR post and insight and improvement officers. Report P52, P53, P54
  • Legal: Legal advice confirms no specific legal implications from the update; any new or continued commissioned services must comply with procurement laws, regulations and contractual arrangements. Report P82, P83
  • Risk: Numbers of children in care and out-of-authority residential placements remain above targets, requiring further embedding of Coming Home and Stability work. Report P47, P49
  • Equalities: An Equality Impact Assessment (Appendix B) and Environmental Impact Assessment (Appendix C) accompany the report. Report P90, P91

Who and where

  • Children and young people in care in Bristol Report P27, P51
  • Children with SEND and their families Report P7, P8
  • Foster carers and prospective foster carers Report P37
  • Unaccompanied Asylum-Seeking Children and Section 17 families Report P27
  • Children and Education directorate workforce Report P31, P45
  • Bristol City Council taxpayers, through placement budget savings Report P55, P68

Timeline

  • 23 January 2025: Final full business case approved by this Committee Report P28
  • 8 May 2025: Addendum to the Full Business Case approved following programme mobilisation Report P29
  • 19 May 2025: Programme agreed as part of the Council's transformation programme by Strategy and Resources Committee Report P28, P29
  • 9 February 2026: Government announced end of the Safety Valve programme and replacement with a High Needs Stability Grant in Autumn 2026 Report P15
  • 23 February 2026: Government's Every Child Achieving and Thriving White Paper and SEND reforms announced Report P17
  • 26 May 2026: Strategy and Resources Committee to consider formal allocation of the £2.6m transformation fund Report P52
  • August 2026: Update report on progress of transformation portfolio to come back to this Committee Report P64

Plain English for the jargon

  • DCS: Director of Children's Services, the Executive Director for Children and Education
  • SEND: Special Educational Needs and Disabilities
  • EHCP: Education, Health and Care Plan
  • DSG: Dedicated Schools Grant
  • Safety Valve: Government programme supporting 38 local authorities, including Bristol, to reduce High Needs deficits; ending and being replaced by the High Needs Stability Grant
  • FGDM: Family Group Decision Making, part of the National Families First Partnership Programme
  • UASC: Unaccompanied Asylum-Seeking Children
  • ILS: Inclusive Learning Service
  • ITS: Invest to Save funding scheme
  • Bristol WORKS: Bristol programme providing work experience to young people
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item52

Resolved

At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Kollar The Committee RESOLVED UNANIMOUSLY : That the Committee for Children and Young People: To approve the Families First programme. To authorise the Executive Director, Children & Education (DCS), in consultation with Chairs of the Children and Young People Committee and the Strategy and Resources Committee, as well as the Director of Finance, to take all steps required to implement the Families First programme in line with the maximum budget envelopes allocated for 2026/27 and as outlined in this report (subject to approval of the transformation budget by the Strategy and Resources Committee) To acknowledges the full scope of programmes and projects that constitutes the C&E transformation portfolio in 2026/27 4. Notes that an update report on progress of the transformation portfolio will be brought back to committee in August 2026.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Children and Young People Policy Committee

Purpose of report

1. To update Children and Young People Committee on the Families First Transformation Programme and to request permission to spend the approved/delegated programme funding of £2,600k for 26/27, recognising budget envelope approval will be sought at Strategy and Resources committee.

2. To provide an overview of the wider set of programmes and projects that together will constitute the directorate’s Transformation Portfolio in 2026/27

Evidence Base:

Children and Education Transformation Portfolio 26/27 1. The Children and Education Transformation Portfolio is structured into four programmes delivering change across the full spectrum from universal prevention to specialist response services, with the ambition of improving outcomes for children and families. Each programme has clear strategic alignment, and interdependent projects are grouped together where they deliver overarching objectives and financial and operational benefits. These are overseen by the Children and Education Portfolio Board, strengthening governance and accountability.

Template approved October 25

OFFICIAL Education: SEND and Alternative Provision Programme

2. The programme aims for financial sustainability of the High Needs Block and improved experiences for children with SEND in mainstream schools by strengthening relationships among schools, families, and children. This is in line with the recently published Schools White Paper and will include Bristol’s proposals under the SEND reforms currently being consulted on. The programme supports delivery of the Council’s SEND and Inclusion Strategy 2024-2028 ensuring fair and consistent processes backed by strong monitoring and accountability.

• We continue to transform Bristol’s SEND system through the co‑produced SEND and Inclusion Strategy (2024–2028), developed with families, schools, health partners and the Parent Carer Forum. Governance arrangements have strengthened, with the SEND Executive and Delivery Boards now well‑established and recognised by the DfE for strong partnership working. • In January 2026, as part of our regular engagement with the DfE, DfE advisers highlighted that “the Local Authority has an ambitious clear SEND and Inclusion strategy with wide stakeholder support. The coherence of the strategy as it has developed and the way agencies and stakeholders work in collaboration is impressive.”

• Delivery momentum has increased over the last year, with 59% of actions now complete and most others on track. Key improvements include a strengthened permanent leadership team, the launch of the WAVE practice framework, and major investment in SEND services—such as £1m additional Educational Psychology capacity and the fully established Inclusive Learning Service (ILS), which is delivering early intervention and strong school engagement citywide.

• Demand pressures remain, but statutory performance is improving. EHCP assessment requests are down 7% compared to last year, final plans issued in 2025 increased by 37%, and Educational Psychology output improved by 53%. While timeliness is still below national levels, backlogs have begun to stabilise and quality assurance has strengthened through the SEND QA Framework.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Equality Impact Assessment Quarterly Children & Education Transformation UpdateAppendix B 115 KB Download
PDF
Environmental Impact Assessment Quarterly Children & Education Transformation UpdateAppendix C 118 KB Download
PDF
Children and Education Transformation UpdateReport 3.9 MB DownloadRead as text
PDF
Slides for CYP CommitteeReport 3.7 MB Download

At this meeting

Whole meeting

Who was there

8 of 15 attended
CT
Councillor Christine TownsendChair, present
KH
Councillor Katja HornchenVice-Chair, apologies, sent representative
KB
Councillor Kerry BailesCommittee Member, present
EF
Councillor Ellie FreemanCommittee Member, present
JG
Councillor John GoulandrisCommittee Member, apologies
SJ
Councillor Shona JemphreyCommittee Member, present
SK
Councillor Susan KollarCommittee Member, present
YM
Councillor Yassin MohamudCommittee Member, present
AV
Councillor Andrew VarneyCommittee Member, present
HW
Hannah WoodhouseOfficer, expected
FT
Fiona TudgeOfficer, expected
HC
Helen CoxOfficer, expected

All 15 on the meeting page

On this subject at Bristol

Search all
  1. Children and Education Transformation UpdateThis decision
  2. Children and Education Transformation UpdateNoted
  3. Children and Education Transformation UpdateApproved
  4. Children & Education Transformation Programme UpdateNoted
  5. Our Families Programme (Children & Education Transformation)Approved
  6. Children’s Social Care and Special Education Spot Purchase Placements UpdateNoted

More from Bristol Children and Young People Policy Committee

All decisions
MeetingDecisionOutcome
15 Oct 2026 Children and Young People Policy Committee Update ReportThe Committee for Children & Young People noted the report. Noted Open
15 Oct 2026 School Attendance Task and Finish Group - closure reportThe Children and Young People Policy Committee: 1. Noted the findings of the School Attendance Task and Finish Group,... Noted Open
15 Oct 2026 Bristol Sanctuary Services update and grant fundingThe Committee for Children and Young People: 1. Noted Sanctuary Services updates, including progress on the Sanctuary... Noted Open
15 Oct 2026 Adoption West ContractThe Committee for Children and Young People: 1. Approved a Variation to the Contract with Adoption West for the ongoi... Approved Open
15 Oct 2026 Q1/P3 Finance update reportThe Committee for Children and Young People noted the contents of the report on the Q1 (P3) forecast. Noted Open