Tree works contract

Decided Committee 4 papers

AI summaryBristol City Council's Public Health and Communities Committee unanimously approved procurement of a new tree works contract with a £7.8 million maximum budget, to run from April 2027 for at least five years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProcurement and award authorised unanimously
Money£7.8 million maximum budget envelopeOver 5 years plus optional 2 year extension
What happens nextProcure and award the contractBefore new contract start in April 2027
Who it affectsCouncil tree stock and highway usersOver 45,000 standard trees managed by Parks

What was decided

The committee authorised the Executive Director Growth and Regeneration, in consultation with the committee chair, to procure and award a Tree Works contract within the £7.8 million maximum budget envelope and procurement routes set out in the report. Report P20

The committee authorised the Executive Director to invoke any subsequent extensions or variations specifically defined in the contract, up to the maximum budget envelope. Report P21, P22

Why

The current contract with Gristwood and Toms expires in March 2027 and that supplier has said it cannot continue at current rates, so a replacement is needed to meet legal duties to maintain trees on council owned land and the adopted highway. Report P5, P7, P16

Pressures include a growing tree population, an expected 10,000 more trees entering inspection, ash dieback disease work, and higher market rates for contracted tree works. Report P8, P9

Officers preferred option 4: a tendered single principal supplier alongside the existing open framework contract, offering delivery security, value for money through rate testing, and reduced dependence on one contractor. Report P16, P17, P38

What happens next

Run a competitive procurement in line with the Procurement Act 2023 and the council's own procurement rules, with legal services advising on the process and contract. Report P41

Award the contract ahead of the new start date of April 2027, with the contract able to run alongside the £2.7 million framework contract approved on 9th May 2025. Report P9, P10, P37

An optional 2 year extension can be taken up to March 2034, taking total spend to £7.798 million. Report P10, P12

The money

  • £7.8 million Maximum budget envelope for the new principal contract over 5 years plus optional 2 year extension Report P10, P20
  • £5.616 million Projected tree works expenditure April 2027 to March 2032 over the initial 5 year term Report P12, P35
  • £7.798 million Total projected tree works expenditure April 2027 to March 2034 including the 2 year extension option Report P12
  • £6.817 million Revenue cost over 5 plus 2 years, from General Fund, HRA and Highways and Landscapes Tree Planting Programme Report P32
  • £0.981 million Capital cost over 5 plus 2 years, from S106, Trees for Climate Grants and other grant income Report P32
  • £345,000 Revenue budget uplift in financial year 2026/2027 to address market rate and volume pressures Report P9, P36
  • £350,000 Further revenue budget uplift in financial year 2028/2029 Report P9, P36
  • £2.7 million Framework contract approved on 9th May 2025, running April 2026 to March 2030, to add contractor capacity Report P9, P37

Options considered

  • Chosen: Option 4: tender for a single principal supplier plus tender for seasonal and project works on an open framework contract. Provides delivery security without reliance on a single contractor, enables market rate testing, and continues outsourcing of specialist tree work risks Report P16, P17, P38
  • Rejected: Option 5: tender for multiple suppliers and an open framework contract for project work only. Would require repetitive procurement processes and increased service resources, risking other work Report P16, P17
  • Rejected: Option 1: do nothing, extend the current Gristwood and Toms arrangement. Current contractor cannot deliver ash dieback works or continue at existing rates, and the contract ends March 2027 Report P16
  • Rejected: Option 2: tender for a single principal supplier only. Increases risk that health and safety work cannot proceed if the contractor has delivery difficulties Report P16
  • Rejected: Option 3: provide a tree works service in house. The council does not have service or corporate experience of managing the associated risks Report P16
  • Rejected: Option 6: tender for a shared service with a neighbouring authority. No options to progress this through negotiation with other authorities within the required timescale Report P16

Implications

  • Financial: Key financial risks are demand, volume and inflationary pressures exceeding budget as more trees enter the inspection regime and ash dieback works move to general revenue after 2028/29; mitigation is competitive procurement alongside the framework, clear specifications and ongoing budget monitoring. Report P39
  • Legal: The procurement must follow the Procurement Act 2023 and the council's own procurement rules, with legal services advising on the process and resulting contract. Report P41
  • Staffing: Officers have identified no HR implications from this report. Report P45, P46
  • Other: Officers have identified no IT implications from this report. Report P43, P44

Who and where

  • Bristol City Council Parks Service, which manages over 45,000 standard trees across parks, allotments, cemeteries, housing sites, car parks and civic spaces, and which carries out inspections using its own arboriculturists Report P3, P4
  • Residents, visitors and property owners, who benefit from reduced risk of harm and tree related subsidence through maintained safety works Report P27, P4
  • Highway users, through epicormic growth removal and winter pollarding on the adopted highway Report P4, P12
  • Housing tenants, through HRA funded tree safety works on housing land Report P12

Timeline

  • 9th May 2025: Public Health and Communities Committee approved a £2.7 million framework contract for additional contractor capacity Report P9, P37
  • February 2026: Full Council approved revenue budget uplifts of £345,000 for 2026/27 and £350,000 for 2028/29 Report P36
  • March 2027: Current Gristwood and Toms tree works contract expires Report P5, P7, P37
  • April 2027: New principal tree works contract expected to start Report P1, P7, P10, P12
  • March 2030: Framework contract (approved May 2025) ends and is due to be retendered Report P9, P37
  • March 2032: End of the initial 5 year term of the new principal contract Report P12, P35
  • March 2034: Latest possible end date if the optional 2 year extension is taken up Report P12

Plain English for the jargon

  • Arboriculturists: Specialists in the care and management of trees
  • Ash dieback: A disease affecting ash trees that creates safety risks and requires programmed removal or treatment
  • Epicormic growth: New shoots growing from dormant buds on tree trunks or branches, often managed to reduce nuisance and risk
  • Framework contract: An agreement setting up terms under which specific works can be called off, used here alongside the principal contract to add supplier capacity
  • HRA: Housing Revenue Account, the ringfenced landlord account for council housing
  • Pollarding: A pruning technique that removes upper branches to promote a dense head of foliage, used here on a cyclical basis
  • S106: Section 106 planning obligation contributions from developers, used here to fund tree planting
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

It was RESOLVED that the Committee for Public Health and Communities (Unanimously FOR): 1. Authorised the Executive Director Growth and Regeneration in consultation with the Chair of the Public Health and Communities Committee to procure and award a Tree Works contract in-line with the procurement routes and £7.8 million maximum budget envelopes outlined in this report. 2. Authorised the Executive Director Growth and Regeneration to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Public Health and Communities Policy Committee

Purpose of report

1. To approve the procurement of a new, principal tree works contract to help the council manage and maintain trees on its landholdings and on the adopted highway. The new contract will run alongside an existing framework contract, providing supplier options and securing the delivery of works for a minimum of five years from April 2027.

Evidence Base:

1. The Council has a significant and growing tree population on land it owns and on its adopted highways right across the city. Outside of trees found in its woodlands, the Parks Service manages over 45,000 standard trees in the city’s parks, allotments, cemeteries, Housing sites, car parks and civic spaces – with an average of 750 being added each year as a result of the council’s ambitious tree planting projects.

2. The Parks Service currently maintains the safety of these trees with its own Arboriculturalists carrying out routine inspections and instructing tree works (pruning, felling) to a specialist contractor as and when required. Contracted works also include cyclical pollarding work and annual epicormic growth removal of a section of trees in the adopted highway in order to prevent nuisance to the public and lower the risk of tree related subsidence to private properties. The Parks Service does not have the necessary expertise to carry out its own tree works beyond small- scale incidental work in parks.

3. The Council’s current tree works contract with Gristwood and Toms expires in March 2027 and approval to procure a new, replacement principal contract is now required to ensure we continue to meet our legal obligations to maintain trees on council-owned land and on the adopted highway

Template approved October 25

OFFICIAL from April 2027 onwards – avoiding any increased health and safety risks and maintaining routine cyclical works.

4. Not all trees in Council ownership are subject to a routine inspection. Highlighted as a corporate risk, a programme of identifying these tree locations and carrying out initial safety inspections is underway with a minimum of 10,000 more trees expected to be added to the inspection and tree works programme. The Council is also managing the increased safety risk from ash dieback disease on the city’s ash tree population – implementing a funded three-year programme of work to do so.

5. These elements are acting alongside an uplift in market rates for contracted tree works to generate pressure on allocated revenue budgets for both tree inspections and tree work. The Council has responded with a revenue budget uplift of £345,000 in financial year 2026/2027 and a further £350,000 for financial year 2028/2029. To support an increase in delivery, the Public Health and Communities Committee approved a £2.7 million framework contract at its meeting on 9th May 2025 to add contractor capacity during the final year of the Gristwood and Toms contract and beyond. This contract runs from April 2026 to March 2030 when it will be retendered.

6. Expenditure on tree works over the course of a new principal tree works contract has been estimated and given in Table 1. Works to this value would be commissioned and delivered through the new principal contract and the existing framework contract. The new principal contract value will reflect the whole programme cost with an optional 2-year extension, so £7.8 million. This will enable the council to use the contract more extensively if the secured rates are favourable and if so, lowering the need for repeated contract call-offs and associated resource impacts.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
7.2 Appendix B: Equality Impact Assessment: Tree and Woodland ServicesAppendix 407 KB Download
PDF
7.3 Appendix C: EnvIA Tree works contract procurementAppendix 451 KB Download
PDF
7.4 Appendix G: Options Appraisal: Tree and Woodland ContractAppendix 887 KB Download
PDF
Tree works contractReport 466 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 13 attended
SW
Councillor Stephen WilliamsChair, present
EC
Councillor Emily ClarkeVice-Chair, present
LD
Councillor Lisa DurstonCommittee Member, present
CJ
Councillor Carole JohnsonCommittee Member, present
EF
Councillor Ed FraserCommittee Member, present
FH
Councillor Fi HanceCommittee Member, present
CL
Councillor Cara LavanCommittee Member, present
AM
Councillor Abdul MalikCommittee Member, present
BU
Councillor Bador UddinCommittee Member, present
JS
John SmithOfficer, expected
PA
Pete AndersonOfficer, expected
CG
Christina GrayOfficer, expected

All 13 on the meeting page

On this subject at Bristol

Search all
  1. Tree works contractThis decision
  2. Streetworks Permit SchemeApproved

More from Bristol Public Health and Communities Policy Committee

All decisions
MeetingDecisionOutcome
11 Sep 2026 Canford Crematorium – Replacement of crematorsThe Committee RESOLVED (unanimously) to 1. Approve the allocation of £8.649m of capital funding for the replacement o... Approved Open
11 Sep 2026 Wessex Water Green Spaces Improvement BudgetFollowing an amendment proposed by the Chair, the Committee RESOLVED to Approve acceptance of £800,000 capital paymen... Approved Open
11 Sep 2026 Task and Finish Group - Improving safety in parks and green spacesThe Committee RESOLVED (unanimously) to: 1. Approve the proposed development programme and the establishment of a Mem... Approved Open
26 Jun 2026 Minutes of the Previous MeetingIt was agreed that this would be corrected and re published, to be confirmed at the following meeting. ACTION: The mi... Agreed Open
26 Jun 2026 Community Cohesion updateThe Committee for Public Health and Communities RESOLVED to note the Community Cohesion update. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies