2026/27 Transformation Fund and Quarterly Change and Transformation Portfolio Update
ApprovedCommittee4 papers
AI summaryBristol City Council Strategy and Resources Committee approves £17.6m Transformation Fund for 2026/27, including £5.3m carried forward from 2025/26, to support change and transformation programmes.
What happens nextIndividual programmes report separatelyEach programme brings own decisions to relevant committee
Who it affectsCouncil transformation portfolioAll transformation programmes and projects
What was decided
The committee approved the Transformation Fund for the 2026/27 portfolio and the carry-forward of approved but unspent 2025/26 funding. Report P4
Members noted the definition of Transformation, the new funding model for internal programme and project management capacity, and that the S151 Officer may amend allocations in year. Report P4
Members noted the progress update on key priority transformation initiatives. Report P4
Why
Significant savings in the 2026/27 budget depend on the transformation programmes; delivering them is critical to the council's financial resilience. Report P18
The portfolio supports the council's ambition to be collaborative, inclusive and prevention-focused, with each programme linked to five strategic priorities and four cross-cutting principles. Report P6
The work aims to deliver a financially stable corporate position, good quality inclusive services, local housing capacity, community-level services and a One Council approach to property assets. Report P8
What happens next
Each programme will bring separate reports seeking decisions to its relevant committee, with individual consultation on key changes. Report P10, P12
Final funding alignment decisions are taken at year end by the Section 151 Officer, with capital receipts usage dependent on the disposals pipeline. Report P20, P23
Where projects require key decisions, the council's decision pathway and constitutional requirements apply; any procurement follows the Procurement Act 2023 and council rules. Report P27, P28
The money
£12.3m Revenue reserve funding for 2026/27 Transformation Portfolio Report P15
£5.3m Carry-forward of approved but unspent 2025/26 funding Report P15
£17.6m Total one-off revenue cost of the Transformation Fund Report P15
Options considered
Rejected: Alternative options considered. Report states N/A for alternative options Report P1
Implications
Financial: Funding is split between specific reserves, corporate transformation budget and capital receipts via the flexi-capital route; any shortfall in capital receipts would be met from reserves. Report P20, P22
Financial: Delays to transformation programmes will require immediate mitigation through budget management processes. Report P18
Legal: Individual key decisions must follow the council's decision pathway; procurement must comply with the Procurement Act 2023 and council rules. Report P27, P28
Staffing: Organisational changes affecting employees will follow the council's Managing Change Policy; use of day-rate agency or interim workers will be minimised by using directly employed resource. Report P34
Who and where
Bristol City Council transformation programmes and projects Report P4, P15
Council staff affected by organisational change within transformation programmes Report P34
Residents and communities receiving redesigned services Report P6, P8
Timeline
2026/27: Transformation Fund and portfolio delivery period Report P4, P15
Year end 2026/27: Final funding alignment decisions taken by the Section 151 Officer Report P23
2026-05-26: Strategy and Resources Policy Committee meeting approving the fund
Plain English for the jargon
S151 Officer: The council's statutory chief finance officer, here the Executive Director, Resources, responsible for financial administration.
Transformation Fund: Revenue funding allocated to a portfolio of change and transformation programmes and projects.
Flexi-capital / capital receipts flexibility: Use of proceeds from selling council assets to fund transformation or other revenue costs, subject to eligibility and receipt generation.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
The Committee for Strategy and Resources resolved to: 1. Approve the Transformation Fund for 2026/27 Transformation Portfolio and carry ? forward of approved but unspent funding from 2025/26. 2. Note the definition of "Transformation" for the 2026/27 portfolio and where requirement is needed to seek Transformation Board approval to secure transformation resource (funding and/or capacity). 3. Note where non-transformation funding is secured, approvals will follow the council’s scheme of delegations. 4. Note the new funding model for the internal provision of programme and project management transformation capacity to the portfolio. 5. Note the Executive Director, Resources (S151 Officer) can amend the approved programme of works and funding allocations in year as necessary. 6. Note the progress update of the key priority transformation initiatives.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
KEY DECISION OR FOR INFORMATION: Key decision over £500k spend/save & impacts more than 2 wards
COMMITTEE: Strategy and Resources Committee
DATE: 26 May 2026
TITLE: Transformation Funding 2026/27 and Portfolio Quarterly Update
Ward(s): City Wide
Officer presenting the report: Tara Dillon Job title: Head of Service – Portfolios, Programmes & Projects
Committee Chair: Cllr Dyer
Executive Director lead: Andy Rothery: Executive Director for Resources
Proposal origin: BCC Staff
Purpose of Report: 1. To seek Strategy and Resources Committee approval to the revenue reserve funding for the 2026/27 Transformation Portfolio of up to £12.3m and the carry-forward of approved but unspent 2025/26 funding of £5.3m, and to note the updated governance and funding arrangements set out in this report.
Evidence Base: 1. Background and Context 1.1. The Transformation Portfolio is the Council’s principal mechanism for overseeing large-scale, cross-council change programmes that aim to secure the long-term sustainability of the organisation. 1.2. The Transformation Board provides strategic oversight and governance of the portfolio, while the Portfolio Management Office supports its daily operational management. 1.3. Transformation is defined as activity that delivers fundamental, systemic change to how the Council operates or delivers outcomes for citizens, contributes materially to long term financial sustainability, and requires whole council level coordination to succeed. Initiatives that meet these criteria will be prioritised within the Transformation Portfolio and managed within the available funding, as well as centrally coordinated delivery capacity via our support service teams under the oversight and governance of the Transformation Board. 1.4. The Council will continue to recognise and support other key programmes and projects as part of its overall portfolio, offering centralised support services when needed and as capacity permits. However, these activities may be scheduled, postponed, or paused if necessary to ensure that priority transformation work is delivered within the available resources.
Template approved October 25
OFFICIAL 1.5. If such work secures alternative funding and does not affect the allocation of resources to prioritised transformation projects, approvals for these initiatives will follow the established scheme of delegations. Where this work is contained within the wider portfolio, funding allocations will be tracked so the total committed cost of council programme and project activity is clear. Additionally, basic reporting and visibility will be required through the council’s Portfolio Management system (PM3).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.