AI summaryBristol City Council's Public Health and Communities Committee has approved funding for major lifecycle replacement of the Whitehall Athletics Track surface, with a forecast Council liability of £334,137 over 15 years, rising to £572,731 if operator surpluses are not realised.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFunding committed for track lifecycle replacement
Money£334,137 forecast, up to £572,731Council liability over 15 years for track surface works
What happens nextLegal agreements to be finalisedExecutive Director authorised to enter agreements
Who it affectsTrack users and operatorsSchools, athletics clubs, community groups in Bristol
What was decided
The Committee approved a long term Council commitment to fund major lifecycle replacement of the Whitehall Athletics Track surface, including a respray due in 2028 and full replacement within 15 years, as identified by specialist surveys. Report P33
The Committee authorised the Executive Director for Adults and Communities, in consultation with the Committee Chair, to finalise and enter legal agreements setting out roles, responsibilities and financial arrangements. Report P34
The Committee noted the financial forecast, including that operator contributions of £238,594 (42%) will offset lifecycle costs over 15 years, leaving a forecast Council net liability of £334,137 (58%), or approximately £22,276 per year, with a maximum exposure of £572,731 (about £38,182 per year) if operator surpluses are not generated. Report P35
Why
Whitehall Athletics Track is Bristol's only accredited 400m athletics track, constructed in 2010 with £1m of Council investment, and is used by schools, community groups, universities and athletics clubs. Report P3, P5
Specialist condition surveys by Labosport in 2025 identified essential lifecycle works needed to maintain safety standards and TrackMark accreditation, with a respray in 2028 estimated at £112,000 and full surface replacement by 2040 estimated at £300,000. Report P8, P9
Major lifecycle costs are beyond the financial capacity of the school or community operators and remain an unavoidable responsibility of the Council as landowner and original investor. Report P14
What happens next
The Executive Director for Adults and Communities will finalise and enter into legal agreements with the Cabot Learning Federation covering responsibilities and the proportion of lifecycle costs to be met by each party. Report P19, P34, P51
Funding will need to be considered and approved through the Council's capital programme and medium term financial planning, with confirmation of profiling and affordability at the points of commitment in 2028 and by 2040. Report P50
A tripartite steering group comprising the Council, City Academy Bristol and Bristol & West Athletics Club will provide oversight, monitor financial and participation performance, and escalate risks to the Council. Report P15, P29
The money
£238,594 (42%) Forecast operator contributions towards lifecycle costs over 15 years Report P12, P35
£334,137 (58%) Forecast Council net liability over 15 years, approximately £22,276 per year Report P12, P35
£572,731 Total inflation adjusted (3%) lifecycle cost over 15 years, maximum Council exposure if no operator surplus Report P9, P12, P35
£38,182 per year Maximum Council liability per year if 100% of lifecycle costs must be met Report P12, P35
£112,000 Estimated cost of track surface respray in 2028 Report P9
£300,000 Estimated cost of full surface replacement by 2040 Report P9
£1m Original Council investment in track construction in 2010 Report P3
Options considered
Chosen: Council commits to funding its share of lifecycle costs alongside a redesigned, sustainable operating model (preferred option). Only viable and sustainable means of safeguarding the asset, maintaining accreditation and protecting public investment while avoiding transfer of unaffordable risk to operators Report P26, P30
Rejected: Do nothing, with no commitment to funding lifecycle works. Track would fail TrackMark reaccreditation and deteriorate, leading to loss of Bristol's only accredited 400m athletics track Report P22
Rejected: Transfer full lifecycle liability to the operator (City Academy Bristol or Bristol & West Athletics Club). Not viable, as major capital liabilities including the £300,000 surface replacement are beyond operator financial capacity and would render the operating model unsustainable Report P23
Rejected: Close the facility. Would permanently remove Bristol's only accredited athletics track, undermine health objectives and contradict stakeholder and community support Report P24
Rejected: Continue with the current operating model. Facility currently operates at a deficit, remains underused, and provides no mechanism for generating contributions towards essential lifecycle costs Report P25
Implications
Financial: Forecast Council liability of £334,137 (about £22,276 per year) over 15 years, with maximum exposure of £572,731 (about £38,182 per year) if projected operator surpluses are not generated. Report P12, P35, P50
Financial: Funding will need approval through the Council's capital programme and medium term financial planning, with profiling and affordability confirmed at commitment points in 2028 and by 2040. Report P50
Legal: A legally binding agreement with the Cabot Learning Federation is required to set out responsibilities, ringfence operator surpluses in a lifecycle reserve, and provide monitoring and governance via the tripartite steering group. Procurement must follow the Procurement Act 2023 and the Council's own procurement rules. Report P19, P51, P54
Risk: Projected operating surpluses are subject to variability. If insufficient surpluses are realised and ringfenced, the Council may be required to fund up to 100% of lifecycle costs (£572,731). Report P17, P20
Risk: Failure to undertake required lifecycle works would lead to loss of TrackMark accreditation, increased safety and compliance risks, reduced availability and potential closure of Bristol's only accredited 400m athletics track. Report P20, P36
Equalities: Proposal aligns with the Council's Corporate Strategy by safeguarding citywide sports infrastructure that promotes health, reduces inequalities and supports active communities, with particular benefit identified in Easton and nearby neighbourhoods. Report P38, P40
Other: No significant HR implications anticipated at this stage, though workforce capacity should be monitored against future resourcing requirements. Report P58
Other: No implications on IT arising from this report. Report P56
Who and where
City Academy Bristol (CAB), which manages day to day operations of the track on land leased from the Council Report P3
Bristol & West Athletics Club (BWAC), the primary community user operating under a service agreement with the Cabot Learning Federation Report P4
Cabot Learning Federation (CLF), leaseholder of the land as part of off site playing fields Report P3
Schools, community groups, universities and athletics clubs using the track across Bristol Report P5
Residents of Easton and nearby neighbourhoods identified as benefiting from inclusive access to the facility Report P40
Timeline
2010: Whitehall Athletics Track constructed following £1m of Council investment Report P3
September 2025: Sporting Assets commissioned to help develop a sustainable business case and redesigned operating model Report P11
September to November 2025: Programme of consultation undertaken to inform the Whitehall Athletics Track Business Plan, including stakeholder interviews, community surveys, school engagement and club consultation Report P44
2025: Specialist condition surveys undertaken by Labosport, identifying essential lifecycle works Report P8
10 September to 3 November 2025: Sporting Assets conducted structured one to one consultations with 15 representatives across 10 organisations Report P44
22 April 2026: Legal advice provided by the Legal Team Manager Report P55
27 April 2026: Finance advice provided by the Finance Business Partner Report P53
2026-06-26: Committee decision to approve funding commitment and authorise legal agreements
by 2040: Full surface replacement required (estimated £300,000) Report P9
Plain English for the jargon
TrackMark: UK Athletics' new quality assurance scheme for outdoor Track and Field Athletics facilities, covering six units and open to any facility with track and/or field facilities
CLF: Cabot Learning Federation, leaseholder of the land on which the track is located
CAB: City Academy Bristol, which manages day to day operations of the track
BWAC: Bristol & West Athletics Club, the primary community user of the track
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item21
Resolved
The Committee for Public Health and Communities RESOLVED to: 1. Approve the proposal that Bristol City Council commits to fund the major lifecycle replacement costs associated with the Whitehall Athletics Track surface, including the respray required by 2028 and the full track replacement required within 15 years, as identified through specialist surveys. 2. Authorise the Executive Director for Adults and Communities, in consultation with the Chair of the Public Health and Communities Committee to take all steps required to finalise and enter into necessary legal agreements to reflect roles, responsibilities, and financial arrangements relating to the athletics track lifecycle and operational model. 3. Note the financial forecast, including that estimated operator contributions of £238,594 (42%) will offset the lifecycle costs over 15 years, and that the Council’s net liability is forecast to be £334,137 (58%), equating to approximately £22,276 per year but this could increase to full track surface lifecycle liability (£572,731 over 15 years, equivalent to approximately £38,182 per year) if sufficient surpluses are not generated. 4. Note that failure to undertake the required lifecycle works will lead to loss of TrackMark accreditation, reduced usage by schools and clubs, and deterioration of important citywide community sports infrastructure.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Public Health and Communities Policy Committee
Purpose of report
1. The purpose of this report is to seek approval for Bristol City Council’s long-term commitment to fund the major capital lifecycle replacement works required to maintain the Whitehall Athletics Track surface, including the respray due in 2028 and the full surface replacement expected within 15 years. This includes a forecast contribution of 58%, with potential exposure up to 100% subject to the delivery of projected operator surpluses, to safeguard accreditation, safety and continued community use of the facility.
Evidence Base:
1. Whitehall Athletics Track was constructed in 2010 following £1m of Council investment. The track is located on land leased to the Cabot Learning Federation (CLF) as part of the off-site playing fields for City Academy Bristol (CAB). While CAB manages day to day operations, Bristol City Council retains freehold ownership of the land and responsibility for major lifecycle liabilities associated with the track surface.
2. Bristol & West Athletics Club (BWAC) is the primary community user of the facility, operating under a service agreement with CLF that provides structured access during peak training periods.
3. Whitehall Athletics Track is Bristol’s only accredited 400m athletics track. It provides essential provision for schools, community groups, universities and athletics clubs, and plays a significant role in supporting physical activity, health improvement and inclusive participation across the city.
Template approved October 25
OFFICIAL 4. Loss or decline of this facility would significantly weaken Bristol’s strategic athletics infrastructure and undermine the Council’s wider objectives relating to health, prevention, equalities and community engagement
5. Specialist condition surveys undertaken by Labosport in 2025, informed by England Athletics guidance, have identified essential lifecycle works required to maintain safety standards and TrackMark accreditation. These include:
• Track surface respray in 2028 (estimated £112,000) • Full surface replacement by 2040 (estimated £300,000) • The total inflation (3%) adjusted lifecycle cost over 15 years is estimated at £572,731.
6. Maintaining TrackMark accreditation requires periodic respraying and eventual full resurfacing. Without these works the track would lose accreditation, resulting in reduced use by schools, clubs and events, and undermining the financial and operational viability of the facility.
7. Whitehall Athletics Track currently operates with limited resilience, including underutilisation and an unsustainable financial model. In response to these challenges, the Council commissioned Sporting Assets in September 2025 to help develop a sustainable business case and redesigned operating model.
8. The new operating model is forecast to generate £238,594 (42%) towards lifecycle costs through operating surpluses over 15 years. This leaves a forecast Council liability of £334,137 (58%), equating to approximately £22,276 per year. However, this is dependent on the delivery of projected surpluses, and in the event these are not realised, the council could be required to meet up to 100% of the lifecycle cost (£572,731) equating to a liability of £38,182 per year.
9. Under the operating model, the school will assume full responsibility for athletics equipment lifecycle costs (including hammer cage and jump pit covers), funded from operating surpluses. Following provision for these costs, any remaining surplus will be set aside and contributed towards the track surface lifecycle fund.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Public Health and Communities Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the Previous MeetingIt was agreed that this would be corrected and re published, to be confirmed at the following meeting. ACTION: The mi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.