Environment and Sustainability Policy Committee, Thursday 30 July 2026 at 5.00pm

Albert Road Depot

Noted Committee 1 paper

AI summaryBristol's Environment and Sustainability Committee noted an update on relocating Albert Road Depot, the city's main waste and recycling hub, for Temple Quarter Phase 2. Officers plan a central depot and one in Avonmouth; £400,000 of capital funding is secured for mobilisation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedUpdate noted, no decision to make
Money£400,000Capital spend over two years for mobilisation works
What happens nextOptions appraisal underwayFuture report to return for approval
Who it affectsWaste and recycling servicesBristol Waste Company depot operations and staff

What was decided

The committee noted the report, which was for information only with no decisions to be made. Report P12

Why

The report updates the committee on the relocation of Albert Road Depot, as requested at the meeting on 4 February 2026. Report P1, P25

The 4.7-acre depot in St Philips Marsh must move because it sits within the Temple Quarter Regeneration area, Phase Two. Report P3, P5, P6

The depot is critical to the delivery of statutory household waste and recycling collection services. Report P16, P21

What happens next

Site assessment and operating model development are underway and will present options for viability. Report P9

A further report will return to the committee to seek approval once options are further explored and developed. Report P32

Any future proposal will need a robust business case, option appraisal, and alignment with the Temple Quarter programme and the Medium-Term Financial Plan. Report P29, P30

The money

  • £400,000 Capital cost over two years for mobilisation works, built into the Medium-Term Financial Plan Report P26, P28

Options considered

  • Chosen: Continue preparatory work to identify and assess future depot options. Officer recommendation to note the report while options and an operating model are developed Report P9, P10, P12

Implications

  • Financial: Finance cannot yet provide assurance on affordability, value for money, or whole-life costs; only £0.4 million of capital spend over two years has been secured for mobilisation. Report P28, P29, P30
  • Climate: Optimum locations are being chosen to reduce mileage and carbon emissions, and the new depot is being designed to power an electrified collection fleet. Report P19
  • Legal: No specific legal implications at this stage; Legal Services will advise as the process develops. Report P32
  • Staffing: No HR implications evident at this stage. Report P36
  • Risk: Planning of the new depot must mitigate impacts on sensitive receptors including residential housing and consider access to the strategic road network. Report P7

Who and where

  • Bristol Waste Company and its approximately 600 depot staff Report P3
  • Households receiving waste and recycling collection services in Bristol Report P21, P23
  • Residents near potential new depot sites Report P7

Timeline

  • January 2025: Public waste and recycling consultation identified effective service delivery as a key priority Report P23
  • 3 February 2026: Extraordinary Environment and Sustainability Committee decision (background document) Report P25
  • 4 February 2026: Committee meeting requested this update on the depot relocation Report P1
  • Winter 2026: Temple Quarter Phase Two business case approval expected Report P6
  • 21-22 July 2026: Finance, legal, IT and HR advice provided on the report Report P31, P33, P35, P37
  • 30 July 2026: Committee noted the update report

Plain English for the jargon

  • BWC: Bristol Waste Company, which runs the city's waste and recycling services
  • MTFP: Medium-Term Financial Plan, the council's budget planning document
  • ktpa: Thousand tonnes per annum, a measure of waste throughput
  • SLR Consulting: External consultancy working with the council's Waste Client Team on the relocation
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

The Committee for Environment and Sustainability noted this report.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Environment and Sustainability Policy Committee

Purpose of report

1. To provide an update on the Albert Road Depot re-location process following the Environment and Sustainability Committee request from the meeting on 4th February 2026.

Evidence Base:

1. Albert Road is the main depot for the waste and recycling services provided by Bristol Waste Company (BWC). The site is approx. 4.7 acres. Services on site include: o Recycling collection fleet – 45 plus vehicles o Refuse collection fleet – 20 plus vehicles o Recycling bulking facilities for circa 40-50ktpa (at capacity) o Workshop o Offices o Car Parking o Welfare facilities for circa 600 staff

BWC has provided a scope of requirements for a relocated site which takes account for greater recycling bulking capacity

2. Albert Road Depot is located within the Temple Quarter Regeneration area (St Philips Marsh), Phase Two. The re-location of services requires a systematic approach to finding a replacement.

OFFICIAL As result work has started ahead of the business case approval of Phase 2 which will be approved in Winter 2026. A replacement depot needs to be in the optimum location to provide the most efficient delivery of household waste and recycling collection services. A vehicle optimisation assessment has been undertaken to identify most optimal location/s. This assessment identified the need for a central depot and a depot in Avonmouth.

3. The planning and development of a new waste and recycling depot must test the positive and negative impacts of operational delivery and mitigate against sensitive receptors. Assessment of planning criteria will include access to the strategic road network and distance away from residential housing.

4. The council’s Waste Client Team are leading this preparatory work and are working closely with SLR Consulting.

Alternative options considered

1. Assessment of sites and the development of the operating model is currently underway. This will present options and assess viability.

Officer Recommendations:

That the Committee for Environment and Sustainability

1. Notes the report.

Corporate Strategy alignment:

1. Priority 4: Making it easier, greener and safer to travel into and around Bristol

• Maintain essential city infrastructure for safety, longevity and accessibility.

The replacement of Albert Road Depot is very important and critical to the provision and delivery of statutory waste services.

2. Priority 5: Accelerating climate action and nature recovery

• Reduce carbon emissions and drive progress towards Bristol becoming a carbon neutral city. • Improve the resilience of Bristol's people and places to the impacts of climate change.

The depot is considering the optimum locations for the delivery of collection services which will reduce mileage and associated carbon emissions. The new depot is incorporating the ability to power an electrified collection fleet which will reduce carbon emissions. Optimum locations for depots will also increase the operational resilience.

OFFICIAL City Benefits:

1. Supports key statutory collection services for refuse and recycling.

Consultation Details:

1. A public waste and recycling consultation was undertaken in January 2025. The effective and efficient delivery of household waste and recycling services was identified as a key priority.

Background Documents:

1. Decision of 3 February 2026 Extraordinary Environment and Sustainability committee

Revenue Cost Source of Revenue Funding Capital Cost £400,000 Source of Capital Funding Built into MTFP. One off cost ☒ Ongoing cost ☐ Saving Proposal ☐ If yes - existing or new saving? N/A OR Income generation proposal ☐

Professional comments section:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Albert Road DepotReport 136 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
AF
Councillor Abi FinchChair, present
KT
Councillor Kirsty TaitVice-Chair, present
JC
Councillor James CrawfordCommittee Member, present
KD
Councillor Kye DuddCommittee Member, present
MF
Councillor Martin FodorCommittee Member, present
TK
Councillor Tim KentCommittee Member, present
SK
Councillor Susan KollarCommittee Member, present
IR
Councillor Izzy RussellCommittee Member, present
MW
Councillor Mark WestonCommittee Member, present
JS
John SmithOfficer, in attendance
KL
Ken LawsonOfficer, in attendance
AM
Alex MinshullOfficer, in attendance

On this subject at Bristol

Search all
  1. Albert Road DepotThis decision
  2. 24/03892/X - Bristol Waste Recycling Facility, Albert Road, St Philips, Bristol BS2 0XSApproved

More from Bristol Environment and Sustainability Policy Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 Wetland City InitiativeThat the Committee for Environment and Sustainability: 1. Endorsed Bristol City Council’s participation in the Wetlan... Decided Open
24 Sep 2026 Clean Air Zone Overview – Air Quality, Traffic, and Fleet ComplianceThat the Committee for Environment and Sustainability: 1. Noted the update report. Noted Open
24 Sep 2026 Performance management report – Q1 2026/27That the Committee for Environment and Sustainability noted the Performance progress report. Noted Open
24 Sep 2026 2026/27 Quarterly Finance Report: P3/Q1That the Committee for Environment and Sustainability noted the contents of the report on the Q1 (P3) forecast. Noted Open
30 Jul 2026 Minutes of the Previous MeetingRESOLVED; To approve the minutes of the meeting on the 4 th June 2026. Approved Open