Former St. George’s Primary Youth Justice and Bristol Autism Team Proposal
ApprovedCommittee3 papers
AI summaryBristol's Children and Young People Committee approved converting the former St. George's Primary School into service delivery space for the Youth Justice Service and Bristol Autism Team, with capital works costing £751k and occupation expected by April 2027.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSchool to be used by Youth Justice Service and Bristol Autism Team
Money£751k capital, £66k revenueFunded from corporate capital, H&S budgets and DfE grant
What happens nextTender in August 2026Works from November 2026, occupation by April 2027
Who it affectsYouth Justice Service, Bristol Autism TeamBoth currently in unsuitable or temporary accommodation
What was decided
The committee approved the continued educational use of the former St. George's Primary School as service delivery space for the Youth Justice Service and Bristol Autism Team. Report P13
The Executive Director for Growth and Regeneration was authorised, with the Executive Director for Children and Education and the committee chair, to procure goods, services and works contracts within the maximum budget envelope. Report P14
The Executive Director was also authorised to invoke any contract extensions or variations up to the same maximum budget envelope. Report P15
Why
The Youth Justice Service is a statutory provision, and HM Inspectorate of Prisons feedback found its current City Hall accommodation inadequate, with staff sometimes seeing children in cars or unsuitable locations. Report P3
Bristol Autism Team currently rents space at a Fishponds primary school where, in September 2025, it was moved to a less accessible area, and it needs larger space for training and storage. Report P6
A review of the corporate estate and external options concluded the former St. George's Primary School was the only suitable site, with significantly lower long-term revenue costs than third-party leased space. Report P4
What happens next
A construction tender is expected to start in August 2026, with works beginning in November 2026, subject to Full Business Case approval, and occupation expected by April 2027. Report P9
Statutory planning consultation is underway, alongside targeted engagement with the Youth Justice Service's young people's boardroom and surrounding residents. Report P22
Staff affected by the workplace move will need to be informed in line with relevant HR policy and procedures. Report P34, P35
The money
£751k Total capital cost including fees and contingency Report P8, P25
£288k Capital released as part of end of year budget review Report P8, P25
£275k DfE Schools Condition Allocation grant 2026/27 Report P8, P25
£191k Corporate H&S capital budget (including £91k DDA works), as stated in paragraph 8 Report P8
£188k Corporate H&S Capital Budgets, as stated in the background documents section Report P25
£66k Estimated revenue cost from existing Children and Families Directorate funding Report P25, P28
Options considered
Rejected: Do nothing. Risks around effective delivery of a statutory provision Report P10
Rejected: External third-party leased accommodation. Significantly greater long-term revenue costs than a corporately owned site Report P10
Rejected: Alternative BCC corporate accommodation. No suitable space available in the short term Report P10
Chosen: Refurbish former St. George's Primary School. Only suitable site identified, lowest long-term revenue cost Report P4, P10
Implications
Financial: Capital works are estimated at £751k with £66k revenue cost in 2026/27, funded from existing corporate capital, H&S budgets and DfE grant. Report P8, P25, P28, P29
Legal: Procurement must comply with the Procurement Act 2023 and the council's own procurement rules; legal services will advise on the process and contracts. Report P31
Equalities: The proposal supports autistic children and young people and justice-involved young people, groups identified as facing the greatest barriers; an Equality Impact Assessment is appended. Report P18, P20, P37
Risk: The building has access issues from steep gradients and narrow corridors, and some asbestos is present in the loft and plant room. Report P5
Staffing: Staff from the Youth Justice Service and Bristol Autism Team will move to the new site and must be informed in line with HR policy. Report P34
Who and where
Children and young people in contact with the Youth Justice Service Report P3, P20
Autistic children, young people and families using the Bristol Autism Team Report P6, P20
Youth Justice Service staff (currently based on the 4th floor of City Hall) Report P2
Bristol Autism Team staff (currently renting space at Avanti Gardens Primary School in Fishponds) Report P2, P6
Surrounding residents of the former St. George's Primary School site Report P22
Timeline
Early November (2025): Bristol City Council received vacant possession of St. George's Primary School from Cathedral Schools Trust Report P2
September 2025: Avanti Gardens Primary School reallocated Bristol Autism Team's space to a less accessible area Report P6
July 2026: Planning application submitted for refurbishment and compliance works Report P7
August 2026: Tender for construction works expected to commence Report P9
14th September (2026): Maintained Schools Condition paper considered at Strategy and Resources Committee, including the £275k SCA funding Report P8
November 2026: Works expected to begin, subject to committee and Full Business Case approval Report P9
April 2027: Expected occupation of the building Report P9
Plain English for the jargon
BAT: Bristol Autism Team, a council service providing training and support to education professionals and families of autistic children and young people.
YJS: Youth Justice Service, a statutory Bristol City Council service for children and young people in the justice system.
SCA: Schools Condition Allocation, a Department for Education grant for maintained school buildings.
OBC: Outline Business Case, the stage of project development at which options were assessed and the chosen option was confirmed.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
It was RESOLVED that the Committee for Children and Young People: 1. Approves the delivery of the proposal as set out for the on-going educational use of the former St. George’s Primary School to support the service needs of the Youth Justice Service and Bristol Autism Team (BAT). 2. Authorises the Executive Director, Growth and Regeneration, in consultation with Executive Director, Children and Education and the Chair of the Children and Young People Committee, to take all necessary steps to implement the various works as detailed in this report, including procuring all necessary goods, services and works contracts, and other agreements, in-line with the procurement routes and maximum budget envelope outlined in this report. 3. Authorises the Executive Director, Growth and Regeneration, to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Children and Young People Policy Committee
Purpose of report
To summarise proposals for the utilisation of St. George’s school for continued educational provision as service delivery space for the BCC Youth Justice Service and Bristol Autism Teams. To confirm the associated funding approach utilised to enable works to progress within the 26/27 financial year.
Evidence Base: 1. The BCC Youth Justice Service currently occupy part of the 4th floor of City Hall for accommodation and service delivery. The position is difficult for hosting service delivery due to the nature of security and management of City Hall. Historically, the team were housed in standalone accommodation in the city centre, which enabled an outward, public-facing position leading to more effective service delivery. BCC received vacant possession of St. George’s Primary School from the Cathedral School’s Trust in early November and the Corporate Landlord has supported feasibility and an outline business case to transform the building into a centre for the Youth Justice Service and Bristol Autism Team’s (BAT). As part of the development work, the team has identified the complimentary opportunity to support the service delivery needs of the Bristol Autism Team (BAT), who currently rent non-BCC educational accommodation at Avanti Garden’s Primary School in Fishponds.
2. The Youth Justice service is a statutory provision. As part of the HM Inspectorate of Prisons inspection feedback of the Youth Justice Service, several issues were raised that relate to the service’s ability to function effectively – which relate to inadequate accommodation to support service delivery. Notably these points include: a. “Organisational and strategic investment is required to promote stability, re-establish staff morale and service cohesion, and develop consistency in effective operational practice.” b. “The provision of safe and accessible places for staff to undertake meaningful and purposeful interventions with children needs to improve, as currently there are too many examples of staff seeing children in cars or other unsuitable locations.”
3. As part of the development of an Outline Business Case, Corporate Landlord undertook a review of potential accommodation opportunities within the corporate estate and other options including external third party leased accommodation. The team concluded that the only suitable accommodation available was the former St. George’s Primary School, and no other corporately owned spaces would be available in the short term. The on-going revenue costs for a third party owned space would be significantly greater than with a corporately owned site.
4. St. George’s Primary School is a locally-listed Victorian stone building comprising two-storeys and a basement located to the south of Brandon Hill and above Queens Parade. The building is in a relatively good condition, following some refurbishment works including a new heating system, undertaken by the previous tenant, Cathedral Schools Trust (CST), in 2023. The site and building have access issues, with steep gradients and narrow corridors, and some asbestos is present in the loft and plant room.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children and Young People Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.