Resolved
That the Strategy and Resources Committee noted this report.
AI summaryStrategy and Resources Committee noted Bristol City Council's Q2 2026/27 Corporate Risk Report, which lists 14 strategic risks. Two are rated critical: failure of HRA stock to meet landlord obligations, and inability to maintain highways infrastructure.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
That the Strategy and Resources Committee noted this report.
1. The report provides an update on current significant strategic risks to achieving the Council’s objectives as set in the Corporate Strategy 2025-2030 and summarises progress in managing the risks and actions being taken as at Q2 2026/27. A summary of the Corporate Risk Register and the movement of risks over three consecutive periods are shown in Fig1 below.
Fig1 Q2 26/27 Corporate Risk register
Trav Assessment Risk ID Risk Risk Owner Rating Matrix el Date CRR10_A Delays, Gaps, or EDM_Adult and 14 13-Jul-2026 SC_01 Ineffective Practices in Communities Adult Safeguarding Processes Leading to Increased Risk of Harm or Serious Abuse to Adults With Care and 21 27-Feb-2026 Support Needs
CRR12_M Emergency Planning EDM_Growth & 15 28-Aug-2026 oP_02 Response Team ability Regeneration to prepare for and respond to emergencies / incidents could be overwhelmed 15 28-Jul-2026
CRR13_FI Possible Financial EDM_Resources 10 26-Aug-2026 N_04 Framework and Medium Term Financial Plan (MTFP) Failure
1 10 05-Jun-2026
CRR15_FI Possible In-Year EDM_Resources 15 05-Jun-2026 N_05 Financial Deficit
15 15-Oct-2025
CRR37_H Failure to successfully EDM_Growth & 10 25-Mar-2026 LS_07 implement the Tackling Regeneration Homelessness Programme and maintain key service priorities may lead to increased spend on 15 24-Mar-2026 temporary accommodation which will exceed our subsidy loss budget
CRR43_E Possible failure to EDM_Growth & 15 05-Nov-2025 oP_03 deliver City Regional Regeneration Sustainable Transport Settlement 1 by March 2027 will mean that a number of key sustainable transport 15 22-Aug-2025 improvements will not have been completed or delivered
CRR51_A ASC may be financially EDM_Adult and 21 27-May-2026 SC_02 unsustainable due to Communities national and local pressures, leading to a failure to deliver statutory duties 21 10-Nov-2025
CRR52_T Failure to manage and EDM_Housing 21 19-Aug-2026 BS_01 evidence compliance with the Building Safety Act 2022 obligations in HRA stock leading to
2 injury and or regulatory 21 19-May-2026 enforcement
CRR58_M Unable to adequately EDM_Growth & 28 21-Aug-2026 oP_01 maintain and replace Regeneration the Highway, Traffic, Parking and Docks infrastructure assets
28 08-Jun-2026
CRR60 Failure of HRA stock to EDM_Growth & 28 23-Mar-2026 meet landlord statutory Regeneration obligations, the decent homes standard and consumer standards may lead to regulatory enforcement action 28 18-Nov-2025
CRR61 Failure to manage the EDM_Resources 15 17-Sep-2026 W&C_08 requirements set out under the Construction Design Management framework may cause serious injury to the workforce and others 15 04-Jun-2026 and slow the delivery of the Capital Programme
CRR62_E Risk that prior to the EDM_Children 21 17-Sep-2026 &S_01 Government’s and Education commitment from March 2028 to meet the full costs associated with the Dedicated Schools Grant 21 13-Feb-2026
CRR7_LD Potential Cyber Security EDM_Resources 15 03-Sep-2026 S_05 Incident
3 15 03-Jun-2026
CRR9_SI Possible failure of EDM_Adult and 21 16-Jun-2026 C_02 Safeguarding Communities vulnerable children resulting in harm to a vulnerable child.
21 09-Dec-2025
FIN_03 The council's EDM_Resources 10 16-Dec-2025 arrangements for managing its insurance and risk arrangements may not be sufficient to protect it from experiencing both a 15 08-Dec-2025 service disruption and or financial loss
Fig 2 Risk Direction Key
Direction Description The risk rating has improved from the previous quarter, having reduced in its severity. The risk rating has deteriorated from the previous quarter, having increased in its severity.
The risk rating has not changed from the previous quarter.
Evidence Base / Context
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Q2 Corporate Risk Report 26/27Report | 8 pages | DownloadRead as text |
Follow Strategy and Resources Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2026 | Medium Term Financial Strategy and Capital Strategy 2027-28That the Committee for Strategy and Resources: 1. Noted the outlook and projections within the Medium Term Financial ... | Noted | Open |
| 12 Oct 2026 | Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ... | Noted | Open |
| 12 Oct 2026 | Private Water DistributionThat the Committee for Strategy and Resources: 1. Approved the approach taken to manage this area of emerging risk. 2... | Approved | Open |
| 12 Oct 2026 | Procurement of Display, Exhibition and Signage ServicesThat the Committee for Strategy and Resources: 1. Approved the procurement of a multi-supplier framework for Display,... | Approved | Open |
| 12 Oct 2026 | Arts Council England’s National Portfolio Organisation Funding Round 2028 – 2033That the Committee for Strategy and Resources: 1. Approved the proposal for Bristol Museums and Museum Development So... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.