Q2 Corporate Risk Report 26/27

Noted Committee 1 paper

AI summaryStrategy and Resources Committee noted Bristol City Council's Q2 2026/27 Corporate Risk Report, which lists 14 strategic risks. Two are rated critical: failure of HRA stock to meet landlord obligations, and inability to maintain highways infrastructure.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the Q2 risk report
MoneyNot stated
What happens nextRevised CRR in Q3Updated register due for Q3 reporting
Who it affectsCouncil risk management14 strategic risks to corporate priorities

What was decided

The committee noted the Q2 2026/27 Corporate Risk Report, which sets out 14 strategic risks to the council's objectives. Report P34, P67

Why

Two risks are rated critical at 28: CRR60 on HRA stock failing landlord obligations and CRR58 on maintaining highways, traffic, parking and docks infrastructure. Report P38

One risk improved, adult safeguarding, falling from 21 to 14 as new controls came in. No risks deteriorated during the quarter. Report P40, P42

One risk, CRR37 on the tackling homelessness programme, is being moved down to be managed at Executive Director level. Report P46

What happens next

A revised corporate risk register with more detailed reporting is planned for Q3, following a workshop with the Corporate Leadership Board. Report P60

During Q3, officers will challenge risk owners on 12 risks whose scores have stayed the same for three or more periods. Report P51

Improving risk data completeness, including potential financial impact, is a focus for the next quarter. Report P64

Options considered

  • Chosen: Note the Q2 2026/27 Corporate Risk Report. Officer recommendation in the report Report P67

Implications

  • Risk: Two critical risks remain: HRA stock failing landlord duties, and the council's ability to maintain highways, traffic, parking and docks infrastructure. Report P38
  • Governance: The council's Risk and Assurance Policy requires the Corporate Leadership Board and policy committees to carry out quarterly reviews of corporate risks. Report P28
  • Other: A new online risk management training course launched in April 2026 for officers and managers across the council. Report P59

Who and where

  • Tenants in council housing, given the critical risk on HRA stock and landlord obligations Report P38, P16
  • Highways, traffic, parking and docks users, given the critical risk on infrastructure maintenance and replacement Report P38, P14
  • Adults with care and support needs, covered by the improved safeguarding risk Report P40
  • People placed in temporary accommodation, covered by the de-escalated homelessness programme risk Report P46

Timeline

  • Q2 2026/27: Reporting period for this risk review Report P1, P28
  • May 2026: Executive Directorate members reviewed risks to form the current register Report P53
  • June 2026: Date of the last Corporate Leadership Board risk review Report P28
  • 04 September 2026: Date of the Q2 2026/27 Corporate Risk Report Report P34
  • Q3 reporting: Revised corporate risk register and reports planned Report P60

Plain English for the jargon

  • CRR: Corporate Risk Report
  • CLB: Corporate Leadership Board
  • EDM: Executive Director Member
  • HRA: Housing Revenue Account
  • MTFP: Medium Term Financial Plan
  • SRR: Service Risk Register
  • DRR: Directorate Risk Report
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

That the Strategy and Resources Committee noted this report.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Strategy and Resources Policy Committee, 8 pages

Purpose of report

1. The report provides an update on current significant strategic risks to achieving the Council’s objectives as set in the Corporate Strategy 2025-2030 and summarises progress in managing the risks and actions being taken as at Q2 2026/27. A summary of the Corporate Risk Register and the movement of risks over three consecutive periods are shown in Fig1 below.

Fig1 Q2 26/27 Corporate Risk register

Trav Assessment Risk ID Risk Risk Owner Rating Matrix el Date CRR10_A Delays, Gaps, or EDM_Adult and 14 13-Jul-2026 SC_01 Ineffective Practices in Communities Adult Safeguarding Processes Leading to Increased Risk of Harm or Serious Abuse to Adults With Care and 21 27-Feb-2026 Support Needs

CRR12_M Emergency Planning EDM_Growth & 15 28-Aug-2026 oP_02 Response Team ability Regeneration to prepare for and respond to emergencies / incidents could be overwhelmed 15 28-Jul-2026

CRR13_FI Possible Financial EDM_Resources 10 26-Aug-2026 N_04 Framework and Medium Term Financial Plan (MTFP) Failure

1 10 05-Jun-2026

CRR15_FI Possible In-Year EDM_Resources 15 05-Jun-2026 N_05 Financial Deficit

15 15-Oct-2025

CRR37_H Failure to successfully EDM_Growth & 10 25-Mar-2026 LS_07 implement the Tackling Regeneration Homelessness Programme and maintain key service priorities may lead to increased spend on 15 24-Mar-2026 temporary accommodation which will exceed our subsidy loss budget

CRR43_E Possible failure to EDM_Growth & 15 05-Nov-2025 oP_03 deliver City Regional Regeneration Sustainable Transport Settlement 1 by March 2027 will mean that a number of key sustainable transport 15 22-Aug-2025 improvements will not have been completed or delivered

CRR51_A ASC may be financially EDM_Adult and 21 27-May-2026 SC_02 unsustainable due to Communities national and local pressures, leading to a failure to deliver statutory duties 21 10-Nov-2025

CRR52_T Failure to manage and EDM_Housing 21 19-Aug-2026 BS_01 evidence compliance with the Building Safety Act 2022 obligations in HRA stock leading to

2 injury and or regulatory 21 19-May-2026 enforcement

CRR58_M Unable to adequately EDM_Growth & 28 21-Aug-2026 oP_01 maintain and replace Regeneration the Highway, Traffic, Parking and Docks infrastructure assets

28 08-Jun-2026

CRR60 Failure of HRA stock to EDM_Growth & 28 23-Mar-2026 meet landlord statutory Regeneration obligations, the decent homes standard and consumer standards may lead to regulatory enforcement action 28 18-Nov-2025

CRR61 Failure to manage the EDM_Resources 15 17-Sep-2026 W&C_08 requirements set out under the Construction Design Management framework may cause serious injury to the workforce and others 15 04-Jun-2026 and slow the delivery of the Capital Programme

CRR62_E Risk that prior to the EDM_Children 21 17-Sep-2026 &S_01 Government’s and Education commitment from March 2028 to meet the full costs associated with the Dedicated Schools Grant 21 13-Feb-2026

CRR7_LD Potential Cyber Security EDM_Resources 15 03-Sep-2026 S_05 Incident

3 15 03-Jun-2026

CRR9_SI Possible failure of EDM_Adult and 21 16-Jun-2026 C_02 Safeguarding Communities vulnerable children resulting in harm to a vulnerable child.

21 09-Dec-2025

FIN_03 The council's EDM_Resources 10 16-Dec-2025 arrangements for managing its insurance and risk arrangements may not be sufficient to protect it from experiencing both a 15 08-Dec-2025 service disruption and or financial loss

Fig 2 Risk Direction Key

Direction Description The risk rating has improved from the previous quarter, having reduced in its severity. The risk rating has deteriorated from the previous quarter, having increased in its severity.

The risk rating has not changed from the previous quarter.

Evidence Base / Context

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q2 Corporate Risk Report 26/27Report 8 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 15 attended
TD
Councillor Tony DyerChair, expected
SC
Councillor Sarah ClassickVice-Chair, expected
TB
Councillor Tom BlenkinsopCommittee Member, expected
EK
Councillor Ellie KingCommittee Member, expected
JG
Councillor John GoulandrisCommittee Member, expected
HM
Councillor Heather MackCommittee Member, expected
PM
Councillor Patrick McAllisterCommittee Member, expected
AT
Councillor Ani TownsendCommittee Member, expected
PO
Councillor Paula O'RourkeCommittee Member, expected
NH
Nick HibberdOfficer, expected
PA
Pete AndersonOfficer, expected
AH
Alex HearnOfficer, expected

All 15 on the meeting page

On this subject at Bristol

Search all
  1. Q2 Corporate Risk Report 26/27This decision
  2. Q2 Corporate Risk Report 26/27Noted
  3. Q1 Corporate Risk Report 2026/27Noted
  4. Corporate Risk Report Q1 26/27Noted
  5. Q1 Corporate Risk Report 26/27Noted
  6. Q1 2026-27 Corporate Risk ReportDecided

More from Bristol Strategy and Resources Policy Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Medium Term Financial Strategy and Capital Strategy 2027-28That the Committee for Strategy and Resources: 1. Noted the outlook and projections within the Medium Term Financial ... Noted Open
12 Oct 2026 Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ... Noted Open
12 Oct 2026 Private Water DistributionThat the Committee for Strategy and Resources: 1. Approved the approach taken to manage this area of emerging risk. 2... Approved Open
12 Oct 2026 Procurement of Display, Exhibition and Signage ServicesThat the Committee for Strategy and Resources: 1. Approved the procurement of a multi-supplier framework for Display,... Approved Open
12 Oct 2026 Arts Council England’s National Portfolio Organisation Funding Round 2028 – 2033That the Committee for Strategy and Resources: 1. Approved the proposal for Bristol Museums and Museum Development So... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies