Resolved
NO FURTHER ACTION SUBJECT TO ADDITIONAL LANDSCAPING ALONG THE SIDE AND REAR BOUNDARIES OF THE SITE
Plans Sub-Committee No. 4 decided this item on Thursday 18 February 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
NO FURTHER ACTION SUBJECT TO ADDITIONAL LANDSCAPING ALONG THE SIDE AND REAR BOUNDARIES OF THE SITE
Report No. London Borough of Bromley Agenda DRR/10/00020 PART 1 - PUBLIC Item No. 5A
Decision Maker: PLANS SUB COMMITTEE No. 4
Date: 18 February 2010 Decision Type: Non-Urgent Non-Executive Non-Key
Title: 13 WOODLANDS ROAD, BROMLEY BR1 2AD - ALLEGED DEPOSIT OF MATERIAL AND RAISING OF GROUND LEVELS IN REAR GARDEN
Contact Officer: Tim Bloomfield, Development Control Manager Tel: 020 8313 4687 Tel No E-mail: [email protected]
Chief Officer: Chief Planner
Ward: Farnborough and Crofton
1. Reason for report
Complaints have been received that material has been deposited in the rear garden of this large detached dwelling and the land has been extensively re-contoured. It is alleged that the work has involved substantial engineering operations which has raised ground levels in particular around the site boundaries.
________________________________________________________________________________
2. RECOMMENDATION(S)
No further action subject to additional landscaping along the side and rear boundaries of the site.
1 3. COMMENTARY
3.1Under planning reference 03/01700 permission was granted on 2 July 2003 for single storey side and rear extensions and rear dormer to existing building (13 and 15 Woodland Road). This permission included the construction of an indoor swimming pool at the rear the property.
3.2The property is a listed building within Bickley Park Conservation Area.
3.3Following a complaint in June 2009 concerning the alleged deposit of waste material in the rear garden a site inspection was made. It is alleged that material including demolition rubble and earth had been excavated to the rear of the house and deposited in the rear garden which had been comprehensively landscaped and re-contoured, in places raising ground levels around the edge of the site above the level of the adjoining gardens. The landscaping includes gravel footpaths, steps, internal brick retaining walls and earth banking around the site boundaries.
3.4The scale of the landscaping works was considered to involve engineering operations which required planning permission and the owner was requested to submit a retrospective planning application.
3.5The owner maintains that the material/spoil from the demolition of a former rear extension and construction of the recent extensions was disposed of rather than being retained and deposited in the rear garden. The owner also maintains that before any works were carried out the rear garden had a significant upward gradient which it is claimed has not been modified to any material extent.
3.6The owner has submitted photographs of the rear garden taken during construction work following the demolition of the former rear extension. The photographs show that former ground levels in the rear garden were generally similar to the present levels, although extensive re-contouring, landscaping and construction work has since taken place. The banking of material around the site boundaries is a matter of particular concern and the owner has agreed to additional tree and shrub planning in order to mitigate any problems of overlooking and loss of privacy.
3.7The Ward Member has stated he had dealings at the site 5-8 years ago when he met the previous owner on the site. He recalls that the garden at that time was in a very unkempt state and was completely overgrown. He also recalls that the garden had a steep incline towards the rear boundary and he was able to look down on the adjoining gardens from the top of the slope. He concludes that the garden levels today are no higher than they were when he visited the site around 2004.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
(DRR/10/00020) 13 Woodlands Road, BromleyReport | 15 KB | DownloadRead as text |
Follow Plans Sub-Committee No. 4 at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Apologies for absence and notification of substitute membersNone | Decided | Open |
| 9 Nov 2023 | Declarations of interestVisiting Member Councillor Stammers declared she was a neighbour of the speaker in support of item 4.2. | Decided | Open |
| 9 Nov 2023 | Confirmation of minutes of meeting held on 14th september 2023Confirmed | Decided | Open |
| 9 Nov 2023 | (22/03824/FULL1) - 15 Madeline Road, Penge, London, SE20 8AYPERMISSION | Decided | Open |
| 9 Nov 2023 | (23/02527/FULL1) - Pavilion and Public Conveniences, Goddington Park, Goddington Lane, Orpington, BR6 9DHPERMISSION | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.