Executive, Wednesday 31 March 2010 at 7.00pm

THE RIVERSIDE SCHOOL - PHASED CAPITAL INVESTMENT

Approved Executive 1 paper

Executive approved this item on Wednesday 31 March 2010. Below is the council's own wording, with the papers it was decided on.

Item193

Resolved

RESOLVED that approval be given to add £567,000 to the Capital Programme to fund the new hydro-pool at the Riverside School.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive

Report No. London Borough of Bromley Agenda DCYP10041 PART 1 - PUBLIC Item No. 11

Decision Maker: Children and Young People Portfolio Holder Date: For Pre-Decision Scrutiny by the Children and Young People PDS Committee on 25 March 2010

Decision Maker: Executive Date: 31 March 2010

Decision Type: Non-Urgent Executive Key

TITLE: THE RIVERSIDE SCHOOL – PHASED CAPITAL INVESTMENT Contact Officer: Rob Carling, Head of Children and Young People Finance Tel: 020 8313 4807 E-mail: [email protected] Chief Officer: Gillian Pearson, Director of Children and Young People Services

Ward: Cray Valley East

1. Reason for report

1.1This report provides updated information on the capital building scheme which has supported the development and expansion of Riverside School and recommends that additional hydro facilities are created to supplement the current provision to meet the needs of pupils.

________________________________________________________________________________

2. RECOMMENDATION(S)

2.1That the Children and Young People Portfolio Holder recommends to the Executive to add £567,000 to the Capital Programme to fund the new hydro-pool at the Riverside School.

1 Corporate Policy

1. Policy Status: Existing policy: Children and Young People's Plan 2009-2011 2. BBB Priority: Children and Young People ________________________________________________________________________________

Financial 1. Cost of proposal: Estimated cost £567,000 2. Ongoing costs: N/A 3. Budget head/performance centre: Capital Programme 4. Total current budget for this head: £5.274m plus £0.567 if approved 5. Source of funding: DSG, Primary Capital Programme, Secondary Capital Programme ________________________________________________________________________________

Staff 1. Number of staff (current and additional) - 2. If from existing staff resources, number of staff hours - ________________________________________________________________________________

Legal 1. Legal Requirement: Statutory requirement: Education Act 1996 (As Amended) Special Educational Needs and Disability Act 2001, Education and Inspections Act 2006, The School Organisation (Prescribed Alterations to Maintained Schools) (England) Regulations 2007 No. 1289. 2. Call in: Call-in is applicable ________________________________________________________________________________

Customer Impact 1. Estimated number of users/beneficiaries (current and projected) - All children and young people at the Riverside School ________________________________________________________________________________

Ward Councillor Views 1. Have Ward Councillors been asked for comments? N/A 2. Summary of Ward Councillors comments:

2 3. COMMENTARY

3.1On 10 October 2005, Members of the Council’s Executive approved the amalgamation of the former Rectory Paddock and Woodbrook Special Schools. These proposals enabled the establishment of a new 160 place special school, for pupils with profound and multiple learning difficulties and severe social and communication disorders including autistic spectrum disorders. A capital scheme was approved in principle to expand the buildings on the former Rectory Paddock site.

3.2At the subsequent meeting of the Executive on the 12 December 2005, Members were informed of the outcome of feasibility work on the design of the new special school on the site of Rectory Paddock School. The Consultant's initial findings were that it was possible to provide the accommodation and site requirements for the new school. Through consultation with the Head Teacher and Governors a number of issues were identified for further consideration within the capital scheme.

These included:

 size of the hall and whether it would be adequate for the enlarged school;  adequacy of the existing hydrotherapy pool for the enlarged school;  adequacy of the proposed 6th form provision in terms of number of general classrooms;  adequacy of the staff accommodation given the increased staffing numbers.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
THE RIVERSIDE SCHOOL: PHASED CAPITAL INVESTMENTReport 144 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. THE RIVERSIDE SCHOOL - PHASED CAPITAL INVESTMENTThis decision
  2. Outcomes from Statutory Consultation Process Regarding Expansion of Riverside Special School and Churchfields Primary SchoolAgreed
  3. (10/02293/FULL1) - Riverside School, Main Road, St Pauls Cray.Decided
  4. The riverside school - phased capital investmentDecided

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies