London Borough of Bromley
Executive, Wednesday 26 May 2010 at 7.00pm

PROPOSALS FOR THE REDEVELOPMENT AND REFURBISHMENT OF THE PAVILION LEISURE CENTRE

Approved Executive 1 paper

Executive approved this item on Wednesday 26 May 2010. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

RESOLVED that 1) the proposals for the redevelopment of the Pavilion Leisure Centre as set out in the report, be approved; 2) a budget of £5.5m be approved for the refurbishment of the Pavilion Leisure Centre as detailed in the confidential part of the report; and 3) Council be recommended to approve the inclusion in the capital programme of £5.5m for the Pavilion development.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive

Report No. London Borough of Bromley Agenda DRR 10/00056 Item No. PART 1 - PUBLIC

<Please select>

Decision Maker: EXECUTIVE

Date: 26th May 2010 Decision Type: Non-Urgent Executive Key

Title: PROPOSALS FOR THE REDEVELOPMENT AND REFURBISHMENT OF THE PAVILION LEISURE CENTRE

Contact Officer: Paul Dale Director of Resoucres Tel: 020 8313 4338 E mail [email protected]

Marc Hume, Director of Renewal and Recreation Tel: 020 8461 7987 E-mail: [email protected] Chief Officer: Paul Dale Director of Resoucres Marc Hume, Director of Renewal and Recreation Ward: Bromley

1. Reason for report

1.1This report sets out a range of proposals for the redevelopment and refurbishment of the Pavilion Leisure Centre in Bromley town centre. These proposals have been developed by Bromley Mytime in conjunction with the Council and they encompass a general refurbishment of the Pavilion. Coupled with this, a number of internal alterations and a re-ordering of existing services with the introduction of new uses, specifically a bowling alley and soft play area to replace that contained on the existing Adventure Kingdom site are proposed.

1.2Furthermore, this report sets out a recommended funding package to support the proposals as set out in the report.

________________________________________________________________________________

2. RECOMMENDATION(S)

The Executive is requested to recommend to Council that:

2.1The proposals for the redevelopment of the Pavilion Leisure Centre as set out in this report are approved.

2.2A budget of £5.5 million be approved for the refurbishment of the Pavilion Leisure Centre as set out in detail in the Part 2 report.

1 Corporate Policy 1. Policy Status: Existing policy. 2. BBB Priority: Vibrant Thriving Town Centres. ________________________________________________________________________________ Financial 1. Cost of proposal: Estimated cost £5.5m 2. Ongoing costs: Non-recurring cost. 3. Budget head/performance centre: Proposed capital Programme 4. Total current budget for this head: £ 5. Source of funding: Capital/revenue contribution ________________________________________________________________________________ Staff 1. Number of staff (current and additional): N/A 2. If from existing staff resources, number of staff hours: N/A ________________________________________________________________________________ Legal 1. Legal Requirement: Non-statutory - Government guidance. Section 19 Local Government Miscellaneous Provisions Act 1976 2. Call-in: Call-in is not applicable. Funding decision to be made by Council. ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): 2007/08 = 410,377 and 2008/09 = 400,875 ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? Yes. 2. Summary of Ward Councillors comments: Comments received from Ward Members will verbally reported to the Executive on the night.

2 3. COMMENTARY

3.1The Pavilion Leisure Centre is now approaching 20 years old and in its heyday it was considered the flagship leisure centre for Bromley. However, with the advent of the Spa at Beckenham opening in 1999 and changes in leisure needs over the last decade, the Pavilion has become somewhat dated. This position is further heightened by a lack of investment in the facility leading to regular breakdowns and the occasional closure of facilities. Usage figures for the Pavilion for 2008/09 (last full years figures) indicate 400,875 visits. This is down on the previous year 2007/08 where there were 410,377 visits. Bromley Mytime are anticipating in their latest Service Delivery Plan for 2010/11 that this downward trend will continue.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PROPOSALS FOR THE REDEVELOPMENT AND REFURBISHMENT OF THE PAVILION LEISURE CENTREReport 168 KB DownloadRead as text

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open