HERITAGE ASSETS

Deferred Planning 1 paper

Development Control Committee deferred this item on Thursday 13 January 2011. Below is the council's own wording, with the papers it was decided on.

Item69

Resolved

RESOLVED that the report be DEFERRED pending the submission of a fuller and more comprehensive list of the assets owned by the Council (including buildings that are statutorily listed, locally listed and within Conservation Areas), outlining their current condition and priority rating of work to be carried out. Consideration will also be given to including heritage The report to be submitted to a future meeting of the DCC .
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Development Control Committee

Report No. London Borough of Bromley DRR/10/00147 PART 1 - PUBLIC

Decision Maker: Development Control Committee

Date: 13 January 2011 Decision Type: Non-Urgent Non-Executive Non-Key

Title: HERITAGE ASSETS

Contact Officer: Cliff Jones, Contact Officer's Title Head of Construction Tel: 020 84617582 E-mail: [email protected]

Chief Officer: Marc Hume

Ward: All

1. Reason for report

A number of Heritage Assets are owned by the London Borough of Bromley. This report outlines those Statutory Listed Buildings owned by the Council and how they are being maintained and cared for.

________________________________________________________________________________

2. RECOMMENDATION(S)

Members comments are requested.

1 Corporate Policy 1. Policy Status: Existing policy. 2. BBB Priority: Quality Environment. ________________________________________________________________________________ Financial 1. Cost of proposal: N/A 2. Ongoing costs: N/A. 3. Budget head/performance centre: Property 4. Total current budget for this head: £288k 5. Source of funding: Existing revenue budgets ________________________________________________________________________________ Staff 1. Number of staff (current and additional): 2 2. If from existing staff resources, number of staff hours: N/A ________________________________________________________________________________ Legal 1. Legal Requirement: Statutory requirement. Planning (Listed Buildings and Conservation Areas) Act 1990 2. Call-in: Call-in is not applicable. ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): All residents of the Borough. ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? No. 2. Summary of Ward Councillors comments: N/A

2 3. COMMENTARY

The Property Division is responsible for carrying out planned, reactive and cyclical maintenance, redecoration, minor improvements and works to comply with disability discrimination requirements to the Council‟s portfolio of buildings. The estate includes both statutory and locally listed buildings.

The planned maintenance programme is established by identifying, costing and prioritising works needed to safeguard the long term life of the Council‟s built assets. The condition assessment module of Bromley‟s Asset Management Plan has been used as the basis to formulate the 5-year planned maintenance programme. The Division also recognises that the local knowledge of Headteachers and Departmental Client Units is invaluable in identifying building maintenance issues. As such, they have therefore continued to be involved in the development and management of the programme.

The condition assessment survey predicts when expenditure may be required in the future. Each element of a building is awarded a condition and priority classification by the inspecting surveyor or engineer. The Property Division uses the following grading criteria which accords with Government guidelines. Because of ongoing financial pressure only works identified as Condition C or D and priority 1, 2 or 3 can be considered for inclusion in the 5 year plan:

Condition

 Grade A – Good. Performing as intended and operating efficiently  Grade B – Satisfactory. Performing as intended but exhibiting minor deterioration  Grade C – Poor. Exhibiting major defects and/or mot operating as intended  Grade D – Bad. Life expired and/or serious risk of imminent failure

Priority

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HERITAGE ASSETSReport 97 KB DownloadRead as text

More from Bromley Development Control Committee

All decisions
MeetingDecisionOutcome
17 Sep 2026 Apologies for absence and notification of substitute membersThere were no apologies for absence. Decided Open
17 Sep 2026 Declarations of interestThere were no additional declarations of interest. Decided Open
17 Sep 2026 Questions by members of the public attending the meetingThere were three questions for oral reply and one question for written reply. Decided Open
17 Sep 2026 Confirmation of the minutes of the meeting held on 23 july 2026APPROVED. Approved Open
17 Sep 2026 (25/04937/res) - crystal palace park, thicket road, penge, london, se20 8dtDEFERRED. Deferred Open