PRIMARY BASIC NEED CAPITAL PROGRAMME: PROPOSED INITIAL ALLOCATIONS

Approved Scrutiny 1 paper

Children and Young People Policy Development and Scrutiny Committee approved this item on Tuesday 15 March 2011. Below is the council's own wording, with the papers it was decided on.

Item123h

Resolved

RESOLVED that the Portfolio Holder be recommended to: 1. Approve the individual schemes within the Primary Capital Programme as set out in paragraph 3.4 of the report; 2. Authorise the Director, in consultation with the Portfolio Holder, to approve further individual schemes in schools identified to accept additional pupils in September 2011, to ensure sufficient reception places. That the total budget for these additional schemes delegated to the Director for approval will be limited to £400K and the detail will be reported to a subsequent meeting; 3. Authorise the Director of Children and Young People Services to seek planning permission for schemes at the appropriate time when required.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Children and Young People Policy Development and Scrutiny Committee

Report No. London Borough of Bromley Agenda DCYP11041 Item No. PART 1 - PUBLIC

Decision Maker: Children and Young People Portfolio Holder Date: For Pre-Decision Scrutiny by the Children and Young People PDS Committee on 15 March 2011

Decision Type: Non-Urgent Executive Non-Key

TITLE: PRIMARY BASIC NEED CAPITAL PROGRAMME – PROPOSED INITIAL ALLOCATIONS Contact Officer: Mike Barnes, Head of Access Tel: 020 8313 4865 E-mail: [email protected] Robert Bollen, CYP Strategic Property Manager Tel: 020 8313 4697 E-mail: [email protected] Chief Officer: Gillian Pearson, Director of Children and Young People Services

Ward: Boroughwide

1. Reason for report

1.1This report seeks approval to allocate funding from the Basic Need Capital Grant to facilitate the urgent temporary expansion of places in identified primary schools.

________________________________________________________________________________

2. RECOMMENDATION(S)

2.1The Children and Young People Portfolio Holder is asked to:

(i) approve the individual schemes within the Primary Capital Programme as set out in paragraph 3.4 of this report;

(ii) authorise the Director of Children and Young People Services to seek planning permission for schemes at the appropriate time when required.

1 Corporate Policy

1. Policy Status: Existing policy: Children and Young People's Plan 2009-2011

2. BBB Priority: Children and Young People

________________________________________________________________________________

Financial

1. Cost of proposal: Estimated cost £829,500

2. Ongoing costs: N/A

3. Budget head/performance centre: Capital Programme

4. Total current budget for this head: £4,496,770

5. Source of funding: Government Grant

________________________________________________________________________________

Staff

1. Number of staff (current and additional) - N/A

2. If from existing staff resources, number of staff hours - N/A

________________________________________________________________________________

Legal

1. Legal Requirement: Non-statutory - Government guidance:

2. Call in: Call-in is applicable

________________________________________________________________________________

Customer Impact

1. Estimated number of users/beneficiaries (current and projected) The proposed works- provide 180 additional school places ________________________________________________________________________________

Ward Councillor Views

1. Have Ward Councillors been asked for comments? No

2. Summary of Ward Councillor's comments:

2 3. COMMENTARY

3.1On 19 January 2010 the Portfolio Holder, Children and Young People Services, approved a list of schemes to be progressed as part of the Local Authority‟s Primary Capital Programme (DCYP10011). The priorities for the Primary Capital Programme had been updated to accommodate the capital works required to facilitate the expansions of schools resulting from the 2009 review of the Primary School Development Plan. To support the Primary School Development Plan schemes were included to expand provision at Princes Plain Primary School, Bickley Primary School and Unicorn Primary School. These schemes have either been completed or are nearing completion, accommodating an additional 75 places in each year group.

3.2On 24 January 2011, the Portfolio Holder, Children and Young People Services, considered and approved the outcomes from a further review of the Primary School Development Plan completed in Autumn 2010 (DCYP11006). This review concluded that there was likely to be a need for an additional 7 forms of entry (210 places) across the Borough by 2013 and recommended the temporary expansion of places in a number of schools. This report seeks approval for the necessary urgent capital works to enable some of these temporary expansions to be in place in 2011. The schemes identified are those that are feasible to create additional places in the time required and in locations where there is sufficient demand for additional places.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PRIMARY BASIC NEED CAPITAL PROGRAMME: PROPOSED INITIAL ALLOCATIONSReport 118 KB DownloadRead as text

At this meeting

Whole meeting

More from Bromley Children and Young People Policy Development and Scrutiny Committee

All decisions
MeetingDecisionOutcome
20 Mar 2012 Youth offending team: core case inspection of youth offending work by her majesty's inspectorate of probationRESOLVED that the Portfolio Holder be recommended to: 1) Note the inspection outcomes; and 2) Approve the draft impro... Noted Open
20 Mar 2012 Minutes of the cyp pds committee meeting held on 21st february 2012 and matters arisingRESOLVED that the minutes of the meeting held on 21 st February 2012 be agreed. Agreed Open
20 Mar 2012 Standards of attainment in bromley schools 2011RESOLVED that the Portfolio Holder be recommended to: 1) Note the annual report on the standards of attainment and qu... Noted Open
20 Mar 2012 Annual report of the cyp pds committeeRESOLVED that the annual report of the Children and Young People Policy Development and Scrutiny Committee be conside... Decided Open
20 Mar 2012 The school funding settlement for 2012/13 - dedicated schools' grantRESOLVED that the Portfolio Holder be recommended to agree the proposals on the use of the Dedicated Schools Grant. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies