MINUTES OF THE MEETING HELD ON 10TH JANUARY 2012 AND MATTERS ARISING

Agreed Committee 1 paper

Bromley Economic Partnership (expired) agreed this item on Thursday 19 April 2012. Below is the council's own wording, with the papers it was decided on.

Item2

Resolved

RESOLVED that the minutes of the meeting held on 10 th January 2012 be agreed.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Bromley Economic Partnership (expired)

BROMLEY ECONOMIC PARTNERSHIP

Minutes of the meeting held at 4.00 pm on 10 January 2012

Present:

Councillor Peter Morgan (Chairman) Adrian Hollands, SE London Chamber of Commerce (Vice-Chairman) Robert Cundy, Federation of Small Businesses Robert Goddard, Thackray Williams Solicitors LLP Marc Hume, LBB Renewal & Recreation David Keogh, Jobcentre Plus Colin Maclean, Community Links Bromley Howard Oldstein, The Glades Martin Pinnell, LBB Renewal & Recreation Dene Stuart, NewsQuest

Also Present:

Louisa Allen, LBB Renewal and Recreation Carol Arnfield, Bromley Adult Education College Paul Le Blond, Biggin Hill Airport Mike Gibson, SoutheasternTrains Amanda Grice, Jobcentre Plus Phillip Lapper, Baxter Philips Mike Lewis, Michael Rogers Jenny Whyte, LBB Environmental Services

1 APOLOGIES FOR ABSENCE

Apologies for absence had been received from Chris Bannister (Rizon Jet), Bek Bekir (National Apprenticeships Service), Jeff East (Acorn Commercial), Mary Manuel (LBB Head of Planning Strategy and Projects), Sam Parrett (Bromley College), Liz McNaughton (Treval Engineering) and Councillor Sarah Phillips (Chairman, Renewal and Recreation PDS Committee).

2 MINUTES OF THE MEETING HELD ON 18 OCTOBER AND MATTERS ARISING

Martin Pinnell reported that the Council had been in contact with White Label (who had organised the Invest Bromley event in September 2011), and it should be possible to pull together an event to promote office/industrial property in Bromley. He would be pulling together a small team within the Council and involving partners.

RESOLVED that the minutes of the meeting held on 18th October 2011 be agreed.

1 Bromley Economic Partnership 10 January 2012

3 UPDATES ON MAIN PARTNERSHIP THEMES:

Members of the Partnership gave updates on progress across the main themes of the Partnership.

A) TOWN CENTRE DEVELOPMENT

Marc Hume reported on progress across the town centre development sites. He stated that although there was plenty of vision, what was needed, and what he thought Bromley had, was a sense of momentum and confidence to meet the challenge from Croydon and elsewhere.

Site A: Bromley North. Lord Justice Binning’s judgement on 20th December 2012 quashed Policy OSA and directed the Council to review the policy. This was an opportunity to develop a business case and lobby for a DLR extension in the run-up to the mayoral election in May. It was agreed by the Partnership that this should be a major economic development priority for the borough.

Site B: Tweedy Road. Work was being carried out to test the viability of using the site as a temporary car park – TfL would only support the proposal with sound traffic modelling data. The Chairman added that a variable message system for town centre parking was due to be installed later in the year.

Site C: Town Hall. The exclusivity agreement with the Land Group/Cathedral had been extended for up to six months.

Site E: The Pavilion. The £5m investment programme was on target, and work should be finished in the next few months.

Site F: Civic Centre. Refurbishment of the North Block should be completed by April, allowing the Joseph Lancaster and Anne Springman blocks to be emptied.

Site G: West of the High Street. Officers would be meeting with potential developers in the next 4-6 weeks to obtain their views, modify the scheme as necessary and then move on to securing a development partner. The scheme would still be retail-led, and a document would be circulated later in the month, including to members of the partnership. Work was also being carried out to investigate the possibilities for refurbishing the Churchill Theatre/Central Library in conjunction with this site.

Site J: Bromley South. Officers were discussing with Network Rail whether a more long-term redevelopment above the station would be possible following the withdrawal of the previous developers.

Site K: Westmoreland Car Park. The planning application was due to go to Development Control Committee on 3rd April 2012.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MINUTES OF THE MEETING HELD ON 10TH JANUARY 2012 AND MATTERS ARISINGMinutes 201 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. MINUTES OF THE MEETING HELD ON 10TH JANUARY 2012 AND MATTERS ARISINGThis decision
  2. Confirmation of the minutes of the meeting held on 23 july 2026Approved
  3. Minutes of the health and wellbeing board meeting held on 25th june 2026Agreed
  4. To confirm the minutes of the meeting held on 22 july 2026Agreed
  5. Confirmation of minutes of meeting held on 16th july 2026Decided
  6. Minutes of the children, education and families pds committee meeting held on 10 june 2026Agreed

More from Bromley Bromley Economic Partnership (expired)

All decisions
MeetingDecisionOutcome
12 Apr 2016 Town centres development programme update (verbal update)RESOLVED that the update on the town centres development programme be noted. Noted Open
12 Apr 2016 Local plan development update (verbal update)RESOLVED that the update on the Local Plan be noted. Noted Open
12 Apr 2016 Town centre management and business support update (verbal update)RESOLVED that: 1) Recent work around Town Centre Management and Business Support in the 4 th Quarter of 2015/16 be no... Noted Open
12 Apr 2016 Bromley youth employment project round 2 update (verbal update)RESOLVED that the update on the Bromley Youth Employment Project be noted. Noted Open
12 Apr 2016 Bromley economic partnership work programme 2016/17 (verbal update)RESOLVED that the update on the Work Programme be noted. Noted Open