Renewal, Recreation and Housing Policy Development and Scrutiny Committee noted this item on Thursday 17 January 2013. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Portfolio Holder be recommended to:- (1) endorse the latest 2012/13 budget projection for the Renewal and Recreation Portfolio; and (2) note the progress of the implementation of the Renewal and Recreation projects within the Member Priority Initiatives.
Word for word from the decision Bromley published for this meeting.Source: cds.bromley.gov.uk
2011/12 Division 2012/13 2012/13 2012/13 Variation Notes Variation Full Year Actuals Service Areas Original Latest Projection Last Effect Budget Approved Reported £'000 £'000 £'000 £'000 £'000 £'000 £'000
R&R PORTFOLIO
Housing Strategy & Development 73 Housing Strategy & Development (16) (16) (4) 12 1 12 0
16,938 TOTAL R&R PORTFOLIO 13,238 13,500 13,490 (10) 0 0
Reconciliation of latest approved budget £'000
Original budget 2012/13 (as per FCB) 13,245 Transfer of AEC to ECS Department (7) Revised original budget 2012/13 13,238 Allocation from contingency for Land Charges 112 Allocation from contingency for Building Control Charges 38 Allocation from Contingency Inbucon Pay Awards 8 Carry forward for Local Development Framework studies 60 Carry forward for libraries shared service one-off costs 40 Property Services Rental Income 4 Latest Approved Budget for 2012/13 13,500 Renewal & Recreation - Budget Monitoring Notes as at 30 November 2012
1) Housing Strategy & Development Dr £12k
As a result of deferral of part of the 2012-13 savings initiatives and following final settlement in September, there is an overspend of £12k.
Within income from affordable housing charges, there is a projected deficit of £60k. This is largely due to the on-going effects of the economic downturn, which have seen reduced planning & building initiatives and therefore a reduced requirement to provide affordable housing.
This deficit is being offset by a projected underspend within salaries of £60k, resulting from two vacant posts being held vacant.
2) Building Control £0k
Based on information to date, an income deficit is projected of £180k. This is being offset by savings of £180k from management action to reduce costs, including holding 3.7ftes vacant.
3) Planning Dr £20k
Income from non-major planning applications is £235k below budget for the first eight months of the year and a deficit of £300k is projected for the year. The actual income for the April to November 2012 is £60k higher than that received for the first eight months last year. Total income is therefore expected to be £72k higher than 2011/12, however, still some £300k below budget. The income projections have taken into account the statutory price increase in November. Full year effect of the price increase is expected to be around Cr £130k and will not therefore offset the current deficit forecast.
£159k has been received for major applications this year, compared to £137k for the same period last year. Planning officers within the major team have provided a schedule of potential future income that may be received before the year end of approximately £155k, and therefore a shortfall of income totalling £50k is projected from major planning applications.
There is a projected surplus within income from pre-application meetings of £50k, (which could be as high as £60k), due to higher than budgeted activity levels. Overall, this gives rise to a net projected deficit within income of £300k.
Continuing management action to hold 6.6fte posts vacant, has resulted in a projected underspend within salaries of £255k. There are further projected underspends across supplies and services budgets of £45k, which fully meet the income deficit.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Renewal, Recreation and Housing Policy Development and Scrutiny Committee at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.