RESOLVED that 1) subject to the Council agreeing the budget, approval be given for overall expenditure of £2,124,540 for building maintenance budgets in 2013/2014, broken down into the various budget heads as follows: Planned Maintenance £615,990 Reactive Maintenance £915,740 Cyclical Maintenance £334,110 Asbestos Management £105,141 Water Treatment Works £124,690 Disability Discrimination Act Works 0 External Decorations £26,500 Minor Improvements 0 TOTAL £2,124,540 2) the criteria used to assemble the planned maintenance programme (Gateway review 0 & 1) be approved: 3) the planned maintenance programme. Copies are available in the Members’ room. 4) the Director of Resources be delegated authority to vary the planned programme to accommodate any change in the approved budget or where such action is considered necessary to either protect the Council’s assets or make the most effective use of resources; 5) the preferred procurement option and method to be used. (Gateway review 2) be approved; 6) the Director of Resources be delegated authority to select the most economically advantageous tender for any individual item of expenditure under the approved programme referred to at (1) – (5) above; 7) the Director of Renewal and Recreation be authorised to submit planning applications where appropriate in respect of schemes set out in the report; and 8) the procurement method proposed for a rolling programme of condition surveys be approved.
Word for word from the decision Bromley published for this meeting.Source: cds.bromley.gov.uk
Report No. London Borough of Bromley DRR13/028 PART ONE - PUBLIC
Decision Maker: EXECUTIVE
Date: Wednesday 6 February 2013 Decision Type: Non-Urgent Executive Key
Title: GATEWAY REVIEW 0,1 & 2 APPROVAL OF 2013/2014 OPERATIONAL BUILDING MAINTENANCE BUDGETS, PLANNED MAINTENANCE PROGRAMMES AND PREFERRED PROCUREMENT OPTION
Contact Officer: Catherine Pimm, Head of Asset Management and Strategic Projects Tel: 020 8461 7834 E-mail: [email protected]
Andrew Brook, Planned Maintenance Team Manager Tel: 020 8461 7739 E-mail: [email protected]
Chief Officer: Director of Resources
Ward: (All Wards);
1. Reason for report
This report sets out the criteria used to assemble each programme based on the draft budget proposals.
The report also addresses the strategic assessment and business justification for the programmes and the preferred procurement option for completing them.
A copy of the proposed planned maintenance programme for operational properties is within the Members’ room.
(i) subject to the Council agreeing the budget, to approve an overall expenditure of £2,124,540 for building maintenance budgets in 2013/2014, broken down into the various budget heads as follows:
1 Planned Maintenance 615,990
Reactive Maintenance 915,740
Cyclical Maintenance 334,110
Asbestos Management 105,141
Water Treatment Works 124,690
Disability Discrimination Act Works 0
External Decorations 26,500
Minor Improvements 0
TOTAL £2,124,540
(ii) to approve the criteria used to assemble the planned maintenance programme. (Gateway review 0 & 1).
(iii) to approve the planned maintenance programme. Copies are available in the Members’ room.
(iv) to delegate authority to the Director of Resources to vary the planned programme to accommodate any change in the approved budget or where such action is considered necessary to either protect the Council’s assets or make the most effective use of resources.
(v) to approve the preferred procurement option and method to be used. (Gateway review 2).
(vi) to delegate authority to the Director of Resources to select the most economically advantageous tender for any individual item of expenditure under the approved programme referred to at (i) – (v) above.
(vii) to agree that the Director of Renewal and Recreation be authorised to submit planning applications where appropriate in respect of schemes set out in this report.
(viii) to agree the procurement method proposed for a rolling programme of condition surveys.
2 Corporate Policy 1. Policy Status: Existing Policy: 2. BBB Priority: Excellent Council: ________________________________________________________________________________ Financial 1. Cost of proposal: 0 2. Ongoing costs: Recurring Cost 3. Budget head/performance centre: Operational Property Services, Resources Directorate 4. Total current budget for this head: £2,124,540 5. Source of funding: Funded from Revenue Budgets ________________________________________________________________________________ Staff 1. Number of staff (current and additional): Not applicable 2. If from existing staff resources, number of staff hours: Not applicable ________________________________________________________________________________ Legal 1. Legal Requirement: Statutory Requirement: 2. Call-in: Applicable: ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): Borough wide ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? Not Applicable 2. Summary of Ward Councillors comments: Not applicable
3 3. COMMENTARY
3.1The Operational Property Division is responsible for a range of maintenance and improvements to the Council’s portfolio of operational buildings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.