RESOLVED that 1) the latest financial position be noted and that a projected net underspend of £3,580k is forecast based on information as at January 2013 consisting of £3,595k for early achievement of savings identified in the 2013/14 budget and £1,567k on services in year, additional council tax freeze grant income of £18k, prior year adjustments of £1,597k, and £1,164k underspend on the Central Contingency offset by the Commissioning Authority Programme earmarked reserve of £300k, a provision of £800k for facilitation payments and a contribution of £3,261k to the Economic Development Fund (as detailed in section 3.1 of the report); 2) a projected increase to the General Fund balance of £2,030k made up of £3,580k net underspend detailed above, offset by carry forwards of £1,550k funded from underspends in 2011/12 be noted (as in section 3.8 of the report); 3) the comments from the Director of Renewal and Recreation, the Director of Resources and the Director of Education and Care Services, as detailed in sections 3.2, 3.3 and 3.4 of the report be noted; 4) approval be give for the release of £14k ... view the full minutes text for item 157.
Word for word from the decision Bromley published for this meeting.Source: cds.bromley.gov.uk
1.1This report provides the fifth budget monitoring position for 2012/13 based on expenditure and activity levels up to January 2013. The report also highlights any significant variations which will impact on future years as well as any early warnings that could impact on the final year end position. __________________________________________________________________________
2. RECOMMENDATION(S) NOT UPDATED
2.1Executive are requested to: (a) consider the latest financial position;
(b) note that a projected net underspend of £3,580k is forecast based on information as at January 2013. This consists of £3,595k for early achievement of savings identified in the 2013/14 budget and £1,567k on services in year, additional council tax freeze grant income of £18k, prior year adjustments of £1,597k, and £1,164k underspend on the Central Contingency offset by the Commissioning Authority Programme earmarked reserve of £300k, a provision of £800k for facilitation payments and a contribution of £3,261k to the Economic Development Fund (see section 3.1);
(c) note a projected increase to the General Fund balance of £2,030k made up of £3,580k net underspend detailed in (b) above, offset by carry forwards of £1,550k funded from underspends in 2011/12 (see section 3.8);
(d) consider the comments from the Director of Renewal and Recreation, the Director of Resources and the Director of Education and Care Services, as detailed in sections 3.2, 3.3 and 3.4;
1 (e) agree to release £14k from the Central Contingency for Early Intervention KS2 writing moderation work as detailed section 3.5.6;
(f) agree to release £100k from the Central Contingency for Planning Appeals change in legislation as detailed section 3.5.7;
(g) agree to release £100k from the Central Contingency for Carbon Tax as detailed section 3.5.8;
(h) agree to release £64k from the 2013/14 Central Contingency for Local Reform & Community Voices grant as detailed in section 3.5.10;
(i) identify any issues that should be referred to individual Portfolio Holders for further action.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.