Renewal, Recreation and Housing Policy Development and Scrutiny Committee noted this item on Tuesday 28 January 2014. Below is the council's own wording, with the papers it was decided on.
RESOLVED that:- (1) progress on the delivery of the Town Centres Development Programme be noted; (2) the Beckenham Town Centre Member Working Party be reconvened as a task and finish group to provide design oversight and strategic guidance during the initial scheme design stage of Beckenham Town Centre.
Word for word from the decision Bromley published for this meeting.Source: cds.bromley.gov.uk
Report to Renewal, Recreation and Housing Policy Development and Scrutiny Committee
Drr14/009 APPENDIX 1 Town Centres Individual Site Updates – January 2014
Site Lead Background Position Statement Officer
Bromley
Site A: Network The Council has received the judgement with Position Bromley Rail regards the Statutory Challenge to Policy North The OSA. An Order was issued that quashes A strategic option to re-examine land uses for the redevelopment of Council Policy OSA in its entirety. It requires the the Bromley North Station site was included in the papers approved Linden Council to prepare, publish, consult upon and for consultation purposes by the LDF Sub-committee. Work is Homes promote a new policy for the OSA site. progressing on the formulation of policy options including undertaking supporting massing and viability assessments. The Lead: KM It is proposed that this be dealt with in the results of which will inform the drafting of Local Plan draft policies. forthcoming Local Plan, as it is at an appropriate stage of development. TfL have completed an economic and design feasibility and viability assessments of a number of options. Officers are continuing to work with TfL to examine how these options can be further developed.
Site B: The The AAP states that the site could Position Tweedy Rd Council accommodate a scheme for around 70 residential units. The site is currently being used as a (temporary) compound for Lead: KM storing materials and plant relating to Bromley North Village for a two /HH year period.
1 Site C: Town The Site allocated for mixed use development Position Hall Council comprising Hotel and/or offices. Contracts have now been exchanged with the Cathedral Group based on their proposal to convert the Town Hall to a hotel, Lead: HH conference centre and associated restaurants.
Cathedral aim to submit their planning application within 6 months of entering into the conditional contract. They aim to open the hotel and conference centre in the Spring of 2016.
Site F: Civic The Following a review of the options, it has been Position Centre Council agreed that in the short term, up to 2015, the Council will concentrate on meeting its A report on options for the short term use of Ann Springman and Lead: HH accommodation needs through the more Joseph Lancaster blocks is being prepared. efficient use of the campus site, undertaking limited investment in maintenance.
Anne Springman and Joseph Lancaster blocks have been vacated.
Site G: West Various Major site in the AAP, allocated for mixed use Position of High street development incorporating residential, retail Lead: KM and community and health facilities. AAP Officers are continuing to work with Muse Developments on Inspector recommended that a Masterplan agreeing a viable scheme proposal and partnering arrangements should be prepared for the site and adopted that will deliver the Council’s objectives. Muse are amending their by the Council as supplementary planning original scheme design following the commencement of the Crest guidance. Nicolson residential scheme in Ringers Road. Officers are working with Muse to work up and evaluate this alternative proposal and this work should be completed by the end of March 2014.
2 Position Site J: Network Network Rail is improving the station, in Bromley Rail particular; access. Improvements will cover Timescale: South drop off facilities, disabled access, internal Lead: KM layout, repairs and refurbishment of the A permanent kiss and drop off point on the Waitrose access road building. has been completed as part of the Outer London Fund round 2 allocations.
The development potential of the station site is being reconsidered as part of the Local Plan review, which will include supporting massing and viability assessments. The results of which will form part of the Local Plan draft policy development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Renewal, Recreation and Housing Policy Development and Scrutiny Committee at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.