INTERNAL AUDIT PROGRESS REPORT

Agreed Finance 7 papers

Audit and Risk Management Committee agreed this item on Wednesday 12 March 2014. Below is the council's own wording, with the papers it was decided on.

Item67

Resolved

It was agreed that verification be sought that the Care Services PDS Committee scrutinise placement waivers and if this was the case, to be reported back to Audit Sub Committee to allow members to decide if care services placements need to be included on the waiver list presented to this committee. It was confirmed by Cllr Wells that Education placements are reported to Education PDS but these were just a few. Cllr Harmer raised an issue on value for money and Cllr Grainger raised the report commissioned from CIPFA in 2008 that members found very useful. This was discussed at the previous meeting when it was agreed that the Director of Finance would explore this option. The update on financial impact on high risks was noted. RESOLVED that (1) The contents of the report be noted (2) The waivers approved from October 2013 to February 2014 be noted; the Committee is content with the revised format for reporting waivers, but felt that another column may need to be added to indicate details of PDS scrutiny. (3) The Committee notes the list of Internal Audit Reports on the web, and approves the reports where exemptions are sought. In future members wanted more detail for exemptions sought for reports not to be published within Part 2 of the agenda to include exemption reasons for reports already indicated within the Progress report. This will be reviewed every six months. (4) The Sub Committee notes the continuing achievements of the counter fraud benefit partnership with the Royal Borough of Greenwich. (5) The Committee agrees that placement waivers should in the future be scrutinised by PDS Committees and this should be reported to the Audit Sub Committee. (6) That the Director of Finance pursues the Value for Money study offered by CIPFA.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Audit and Risk Management Committee

Audit Sub Cttee-Priority One list March 2014 - Appendix A Report Title Opinion No. of Details of original Recommendation Implemented Responsible Officer Comments Risk of Number/Date Priority fraud or One’s loss ACS/068/01/2011 Emergency Limited 1 Service Teams, including LATCH, Leaving Care Services, In progress Exchequer The last update indicated that rent arrears High Accommodation & Rent Assurance Core and Cluster [now Supported Living], Traveller and Manager/Liberata Sundry at September 2013 were £2,017,242 an Accounts Orchard and Shipman are not recovering rent arrears or Debtors Section increase of 60% from September 2012 Part monitoring the debts of their clients, which on 10/2/12 gave Manager/Group Manager of the increase in arrears is due to increase an accumulative total of £533,753.50 in these groups. Leaving Care Team/Group in TA numbers and the effects of the Teams did not have access to the accounting files on Anite. Manager Residential wefare reforms. The rent arrears figure as In addition, these teams do not hold detailed procedures to Services/Group Manager at 31st December 2013 stands at outline the process for the recovery of debts Housing Needs £2,103,193. Adjustments of £183K that is The previous audit also highlighted problems with rent pending will bring down this figure and will arrears in emergency accommodation. be further reduced bt £280k for write offs Total rent arrears for current and former clients stands at awaiting action. This area will be audied as £1,266,528 compared to £1,268,466 in January 2012. part of the 2014/15 internal audit plan. See report progress report. CYP/024/01/2012 Behaviour Services N/A 1 o/s Part 2- six of the 7 priority one recommendations have been In progress Assistant Director ECS Expanded in Part 2 High implemented. RD/018/01/2013 Insurance N/A 11 Part 2 In progress Director Of Finance See update in Part 2 High ACS/023/01/2012 Learning Disabilities Nil 12 Part 2 In progress Executive Director ECH Additional work commissioned by Director High Assurance of Finance. Audit currently following up recommendations ECS/004/01/2012 ACS Care ManagerAsst N/A 3 o/s Part 2 - 5 priority one recommendations made.Care In progress Asstistant Director-Adult See update in Part 2. Audit are satisfied High Services Management have confirmed that the procedures Social Care that two of the recommendations have for cash handling, supervision, transfer of cases and been implemented. The 3 outstanding CareFIrst recording have been implemented. The cash recommendations will be reviewed on handling procedure note has bee updated and is now a link completion of the Quality Review check in the Cares Services Guide available on One Bromley. The currently in progress by ECH. Quality Assuarance Team are currently undertaking an audit of supervision and case recording that has been issued to all care teams. No service users contacted regarding contact with PR, responded. All recommendations will be reviewed and tested during the planned follow up audit in 2014-15.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for INTERNAL AUDIT PROGRESS REPORTReport 51 KB DownloadRead as text
PDF
Enc. 2 for INTERNAL AUDIT PROGRESS REPORTReport 60 KB Download
PDF
Enc. 3 for INTERNAL AUDIT PROGRESS REPORTReport 47 KB Download
PDF
Enc. 4 for INTERNAL AUDIT PROGRESS REPORTReport 47 KB Download
PDF
Enc. 5 for INTERNAL AUDIT PROGRESS REPORTReport 73 KB Download
PDF
Enc. 6 for INTERNAL AUDIT PROGRESS REPORTReport 71 KB Download
PDF
INTERNAL AUDIT PROGRESS REPORTReport 264 KB Download

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. INTERNAL AUDIT PROGRESS REPORTThis decision
  2. Annual internal audit report 2025/26Noted
  3. Internal Audit Plan, Strategy and CharterApproved
  4. Internal audit and fraud progress reportNoted
  5. Internal audit plan november 2024-march 2025Approved
  6. Internal audit annual report 2023/24Agreed

More from Bromley Audit and Risk Management Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 MATTERS OUTSTANDING FROM THE MEETING ON 25th FEBRUARY 2026RESOLVED that the Matters Arising Report be noted. Post Meeting Note : The omission of a work programme was not an er... Noted Open
25 Jun 2026 External audit plans 2025/26RESOLVED that: 1) The Audit and Risk Management Committee note the 2025/26 Council and Pension Fund Audit Plans from ... Noted Open
25 Jun 2026 Annual internal audit report 2025/26RESOLVED that: The Annual Internal Audit Report be noted, including the Head of Audit and Assurance’s conclusion for ... Noted Open
25 Jun 2026 Counter fraud report: 2025/26RESOLVED that 1) The Counter Fraud Report be noted. 2) The committee approve the amendments to the Whistleblowing Pol... Noted Open
25 Jun 2026 Annual governance statementRESOLVED that: The Audit and Risk Management Committee approve the Annual Governance Statement, with the following re... Approved Open