(DRR14/051) - Hard-standing, Skibbs Lane, Chelsfield.

Decided Committee 3 papers

Plans Sub-Committee No. 4 decided this item on Thursday 15 May 2014. Below is the council's own wording, with the papers it was decided on.

Item36.1

Resolved

ENFORCEMENT ACTION AUTHORISED
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Plans Sub-Committee No. 4

Report No. London Borough of Bromley DRR14/051 PART ONE - PUBLIC

Decision Maker: PLANS SUB-COMMITTEE NO. 4

Date: Thursday 15 May 2014 Decision Type: Urgent Non-Urgent Executive Non-Executive Key Non-Key

Title: HARD-STANDING, SKIBBS LANE, CHELSFIELD

Contact Officer: Mick Lane, Planning Enforcement Officer E-mail: [email protected]

Chief Officer: Chief Planner

Ward: Chelsfield and Pratts Bottom;

1. Reason for report

A small area of concrete hard standing has been constructed between Skibbs Lane and the Glebe Field which has been the subject of a complaint. The hard standing involves development requiring planning permission. In the absence of an application it is necessary to consider whether enforcement action against the development is expedient. ________________________________________________________________________________

2. RECOMMENDATION(S)

It is not considered to be expedient, in this instance given all the circumstances and information available to take any further action.

1 3. COMMENTARY

3.1This site was previously before Plans Sub-Committee 3 on 09.01.2014 when members resolved that the matter be deferred, without prejudice to any future consideration to, request a planning application, to seek the views of the Highways Drainage Engineer and to check the levels.

3.2The site is a sloping concrete access from Skibbs Lane to the Glebe Field, an area of predominantly pervious open meadow bounded on three sides by mature hedging and trees. This grassed meadow is approximately 1.5m above Skibbs Lane, and is owned by St Martins Church, situated within an open rural environment on the eastern side of Chelsfield Village.

3.3On 25.06.2012 a complaint was received alleging that surface water was running off the concrete hard- standing into Skibbs Lane and causing flooding to the complainant’s property, a bungalow situated approximately 40m from the entrance to the Glebe Field.

3.4On 25.06.2012 a site visit was undertaken when it was observed that the vehicle access to the Glebe Field adjacent to the rectory surfaced in concrete / paved hard standing in place approximately 4m wide between the highway and the field. The hard surface extends approximately 15m between Skibbs Lane and a gated access into the field. There was a gradient of approximately. 1.5m from the gate to the highway and no drainage appeared to have been installed to take away surface water.

3.5The lower section of the access has recently been concreted to provide a firmer surface for vehicles gaining access to the Glebe Field whilst the upper section appears to have been paved for many years and is therefore immune from any enforcement action.

3.6On 02.07.2012 the Church warden was contacted and initially agreed to install a slot drain in order to relieve any excess surface water that may run off the land. The engineering operations were considered to involve development which required planning permission and a retrospective application was requested for the hard standing that had been installed.

3.7A further site visit was subsequently undertaken during a torrential downpour when it was observed that very little surface water was running off down the slope into the road. The topography of surrounding area clearly shows that the complainants’ property is situated on land which is lower than where the hard - standing joins the highway

3.8Two further site visits were made during heavy torrential rain on Friday 11th October 2013 and again on Sunday 13th October 2013. On both occasions it had been raining for at least three hours and pooling of water would have been expected at the site. However it was observed that there were substantial amounts of surface water flowing down Skibbs Lane from the direction of Bucks Cross Road into the recently installed Highway drains which have been installed by the Council in Skibbs Lane.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(DRR14/051): Hard-standing, Skibbs Lane, Chelsfield.Report 117 KB DownloadRead as text
PDF
Enc. 1 for Hard-standing, Skibbs Lane, ChelsfieldReport 166 KB Download
PDF
Enc. 2 for Hard-standing, Skibbs Lane, ChelsfieldReport 432 KB Download

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. (DRR14/051) - Hard-standing, Skibbs Lane, Chelsfield.This decision
  2. (DRR13/150) - Hard-Standing, Skibbs Lane, Chelsfield.Deferred

More from Bromley Plans Sub-Committee No. 4

All decisions
MeetingDecisionOutcome
9 Nov 2023 Apologies for absence and notification of substitute membersNone Decided Open
9 Nov 2023 Declarations of interestVisiting Member Councillor Stammers declared she was a neighbour of the speaker in support of item 4.2. Decided Open
9 Nov 2023 Confirmation of minutes of meeting held on 14th september 2023Confirmed Decided Open
9 Nov 2023 (22/03824/FULL1) - 15 Madeline Road, Penge, London, SE20 8AYPERMISSION Decided Open
9 Nov 2023 (23/02527/FULL1) - Pavilion and Public Conveniences, Goddington Park, Goddington Lane, Orpington, BR6 9DHPERMISSION Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies