Children, Education and Families Policy Development and Scrutiny Committee approved this item on Tuesday 27 January 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Portfolio Holder be recommended to: 1) Approve the updated list of schemes within the Basic Need Capital Programme; 2) Agree the procurement and award of contract of schemes within the Basic Need Programme through traditional procurement, the Lewisham Modular Buildings Framework or through devolution of the Basic Need Capital Grant to schools; 3) Authorise the Executive Director: Education, Care and Health Services to submit planning applications at the appropriate time in respect of the list of scheme.
Word for word from the decision Bromley published for this meeting.Source: cds.bromley.gov.uk
Report to Children, Education and Families Policy Development and Scrutiny Committee
APPENDIX 1 BASIC NEED PROGRAMME 2011-17
Project Funding sources cost Basic School Description of Works Type Year (s) Status (£000s) Need Other Notes Completed Projects
Balgowan Primary Conversion of existing space to form single School bulge class Temporary ‘Bulge’ 2014 Complete 10 10 Kitchen and servery works to complete Permanent Bickley Primary School expansion to full 2FE Expansion 2011 Complete 103 103
First phase of works to support re- Change of age Awaiting final Bromley Road organisation - asbestis strip out range 2014 invoices 113 113 Burnt Ash Primary Internal SEN unit modifications to address School OfSTED recommendations School rebuild 2012 Complete 50 50
Churchfields Primary Modifications to existing building to support Permanent School 4 years of expansion Expansion 2011-2014 Complete 357 357 Clare House Primary Internal modifications and 3 X temporary School accommodation Temporary ‘Bulge’ 2012-14 Complete 578 449 129 DSG New build class and facilities for additional Awaiting Final Access Crofton Primary School ‘Busy Bees’ class SEN 2014 invoices 475 450 25 Initiative AccessWorks - acoustic partitions and Darrick Wood School associated ICT/M&E works SEN 2012 Complete 45 45 Harris Primary Minor refurbishment and temporary toilet Academy Crystal unit to facilitate an extra form of entry in Permanent Palace 2011 & 2012. Expansion 2011-14 Complete 125 104 21 DSG Harris Primary Modular accommodation to provide an Academy Kent House additional form of entry in 2011. Temporary ‘Bulge’ 2011 Complete 263 263 Hawes Down Infants Conversion of existing space to for single School bulge class Temporary ‘Bulge’ 2012 Complete 115 115 Contribution from Basic Need to delivery of Hillside Primary School SEN facilities at school SEN 2011 Complete 100 57 43 James Dixon Primary Temporary reception block with potential for Awaiting Final School additional class in 2015 Temporary ‘Bulge’ 2014 invoices 193 117 76 DSG Conversion of existing space to for single Awaiting Final Leesons Primary School bulge class Temporary ‘Bulge’ 2014 invoices 20 20 Midfield Primary Refurbishment of existing accommodation School and new nursery block Temporary ‘Bulge’ 2012-14 Complete 503 503 Awaiting Final Mottingham Works to allow admission of 3rd KS2 class Temporary ‘Bulge’ 2014 invoices 50 50 Parish CE Primary Awaiting Final School 3 New recption classrooms Temporary ‘Bulge’ 2011-14 invoices 608 608 Poverest Primary Conversion of existing space to form single Awaiting Final School bulge class Temporary ‘Bulge’ 2014 invoices 80 80 Princes Plain Primary Refurbishment of classes in ED C School accommodation Temporary ‘Bulge’ 2012-14 Complete 467 327 140 Improvement of toilet facilities to support Red Hill Primary School increase in pupil numbers Temporary ‘Bulge’ 2012 Complete 57 57 S106 and Awaiting Final other Riverside School New school hall and ASD specific entrance SEN 2013-14 invoices 1,350 829 521 capital Scotts Park Primary Refurbishment of early years area temporary School accommodation block Temporary ‘Bulge’ 2012-14 Complete 498 463 35 S106 St George's CE Primary Conversion of existing space to form single Awaiting Final School bulge class Temporary ‘Bulge’ 2014 invoices 10 10 St Mark's CE Primary School Refurbishment of reception classrooms Temporary ‘Bulge’ 2013 Complete 135 135 St Mary's Cray Primary Minor works to support admission of School additional pupils Temporary ‘Bulge’ 2012 Complete 11 11 Conversion of existing space to form single Stewart Fleming bulge class, including creation of external Awaiting Final (Pioneer Academy) storage area Temporary ‘Bulge’ 2014 invoices 53 53
Temporary classroom block to decant breakfast and after school club, fencing and Awaiting Final Unicorn Primary School temporary 'grasscrete' parking Temporary ‘Bulge’ 2014 invoices 411 383 28
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children, Education and Families Policy Development and Scrutiny Committee at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.