CRYSTAL PALACE PARK - REGENERATION PLAN

Noted Executive 1 paper

Executive noted this item on Wednesday 13 January 2016. Below is the council's own wording, with the papers it was decided on.

Item335

Resolved

RESOLVED that details of the tender process undertaken by officers be noted prior to a decision on contract award being considered under exempt proceedings of the meeting.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive

Report No. London Borough of Bromley DRR16/009 PART ONE - PUBLIC

Decision Maker: Executive

Date: 13th January 2016 Decision Type: Non-Urgent Executive Key

Title: CRYSTAL PALACE PARK - REGENERATION PLAN

Contact Officer: Colin Brand, Assistant Director Leisure and Culture Tel: 0208 313 4107 E-mail: [email protected]

Lydia Lee, Project Manager Change and Regeneration Tel: 0208 313 4456 E-mail: [email protected]

Chief Officer: Director of Regeneration & Transformation

Ward: Crystal Palace;

1. Reason for report

1.1To update Members on the outcome of a procurement process and seek approval for the award of contract.

1.2On 24th March 2015 the Executive agreed to contribute capital receipts to develop an alternative management option for the park and a second wave of capital improvements in line with the park Masterplan.

1.3Consequently officers have undertaken a procurement exercise to appoint a multi- disciplinary team to develop and deliver a Regeneration Plan for the park. This report outlines this process and seeks approval to appoint consultants.

________________________________________________________________________________

2. RECOMMENDATION(S)

2.1That the Executive considers the details of the tender process undertaken by officers, and agrees to the award of contract for the delivery of the Crystal Palace Park Regeneration Plan as set out in the accompanying Part 2 report.

1 Corporate Policy 1. Policy Status: Existing Policy 2. BBB Priority: Quality Environment ________________________________________________________________________________ Financial 1. Cost of proposal: See Part 2 report 2. Ongoing costs: Non-Recurring Cost 3. Budget head/performance centre: Crystal Palace Park capital scheme. 4. Total current budget for this head: £495k 5. Source of funding: Capital receipts. ________________________________________________________________________________ Staff 1. Number of staff (current and additional): N/A 2. If from existing staff resources, number of staff hours: ________________________________________________________________________________ Legal 1. Legal Requirement: None 2. Call-in: Applicable ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): In 2006 the park’s visitor numbers were estimated at 1.68 million.

________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? No 2. Summary of Ward Councillors comments:

2 3. COMMENTARY

3.1Following Executive Committee approval on the 24th March 2015 officers have undertaken a procurement process to appoint a multi-disciplinary team to both develop and deliver a second wave of capital improvements in line with the park Masterplan.

3.2This Regeneration Plan follows the £2.4m Crystal Palace Park Improvement Scheme currently being delivered in the park, and aims to release capital monies identified in the park Masterplan to deliver further capital improvement within the park. The Regeneration Plan is part of the works required to achieve a sustainable future for Crystal Palace Park under the management of a Trust or similar, and the continued capital improvement of the park in line with the Masterplan, as set out in the 24th March 2015 report to the Executive.

3.3To undertake the Regeneration Plan works a multi-disciplinary team is required. Officers identified the Homes and Communities Agency multi-disciplinary technical panel framework as a suitable framework for the procurement of this team.

3.4The framework required a two phase process to be undertaken. Initially a sifting brief was produced and all suppliers listed on the lot were invited to respond through ProContract/Due North. Seven responses were received in July 2015 and evaluated, and five suppliers taken forward to the second stage in line with the framework’s rules. The sifting brief did not require bidders to submit prices.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CRYSTAL PALACE PARK: REGENERATION PLANReport 148 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. CRYSTAL PALACE PARK - REGENERATION PLANThis decision
  2. (25/04937/res) - crystal palace park, thicket road, penge, london, se20 8dtDeferred
  3. (26/01021/RES) - Crystal Palace Park, Thicket Road, Penge, London, SE20 8DTApproved
  4. (26/00738/FPA and 26/00739/LBC) - CRYSTAL PALACE NATIONAL SPORTS CENTRE, LEDRINGTON ROAD, ANERLEY, LONDON, SE19 2GADecided
  5. Crystal palace park regeneration plan update and award of main works contractApproved
  6. (23/01759/FULL1) - Crystal Palace Football Club Academy, Copers Cope Road, Beckenham, BR3 1NZ.Refused

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies