CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Bromley
Plans Sub-Committee No. 4, Thursday 18 February 2016 at 7.00pm

(15/05258/FULL1) - Bournewood Sand and Gravel, Swanley Bypass, Swanley BR8 7FL

Decided Committee 2 papers

Plans Sub-Committee No. 4 decided this item on Thursday 18 February 2016. Below is the council's own wording, with the papers it was decided on.

Item25.9

Resolved

PERMISSION
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Plans Sub-Committee No. 4

Section ‘3’ - Applications recommended for PERMISSION, APPROVAL or CONSENT

Application No : 15/05258/FULL1 Ward: Cray Valley East

Address : Bournewood Sand And Gravel Swanley Bypass Swanley BR8 7FL

OS Grid Ref: E: 550231 N: 168274

Applicant : Bournewood Ltd Objections : NO

Description of Development:

Temporary relocation of site workshop and hardstanding for the washing of vehicles until 14th January 2018

Key designations:

Biggin Hill Safeguarding Area Green Belt London City Airport Safeguarding Sites of Interest for Nat. Conservation Smoke Control SCA 20

Proposal

Permission was originally granted on appeal in 1997 for the extraction of Thanet sand and the restoration and re-contouring of this land by the disposal of inert waste, and a later appeal (ref.10/00657) allowed the use to continue (and the associated buildings to remain) until 14th January 2018. Condition 10 required the provision of a hardstanding for the washing of vehicles (which was subsequently provided), whilst condition 1 required the extraction works to cease by 31st March 2017, and the associated infilling to cease by 14th January 2018.

Permission was granted in 2009 (ref.08/03444) for inter alia a site workshop to the north of the site entrance.

The current application is for the temporary relocation of the existing site workshop and associated hardstanding for the washing of vehicles to the south-eastern corner of the site close to the railway line. It is currently located approximately 190m further to the north adjacent to the A20. The need for the relocation of these facilities is explained by the applicant as follows:

The existing workshop building and associated hardstanding for washing vehicles is located towards the northern side of the site within the area that is below the general final level for the restored site which is causing difficulties in accessing the void on the western side of the site for infilling, particularly as there is material that has been stockpiled for infilling close to the workshop building and hardstanding.

There is also a problem with surface water run-off collecting within the lower area, rendering the washing of vehicles useless as they have to drive away from the wash-down area through the muddy area at lower level. It is therefore considered necessary to re-locate the workshop and hardstanding to an area close to the finished ground area, and the most appropriate area would be the existing hardstanding at the front of the site towards the south- eastern end of the frontage.

This area is adjacent to land where infilling has been completed, and it will enable these facilities to be located out of the way of the general operations needed to complete the excavation and infilling in the central and western parts of the site.

The applicant states that using this area has the advantage that all of the facilities serving the site would be then be located together on an existing hard surfaced roadway which is directly accessible from the main site entrance.

Location

This site comprises an active quarry and infill site which lies within the Green Belt. It borders Sevenoaks District Council to the south and east, and is separated from the nearest residential properties by the A20 Swanley By-Pass.

Consultations

No local objections have been received to the proposals.

Comments from Consultees

The Council's Highway Engineer considers that the proposals are unlikely to have any impact on highways within the London Borough of Bromley.

No drainage objections are raised to the proposals, and Thames Water has no concerns.

Sevenoaks District Council has no objections to a temporary permission, subject to a condition requiring the removal of the development and the restoration of the land on or before 14th January 2018.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(15/05258/FULL1): Bournewood Sand and Gravel, Swanley Bypass, Swanley BR8 7FLReport 64 KB DownloadRead as text
PDF
15-05258-FULL1Report 2.1 MB Download

At this meeting

Whole meeting

More from Bromley Plans Sub-Committee No. 4

All decisions
MeetingDecisionOutcome
9 Nov 2023 Apologies for absence and notification of substitute membersNone Decided Open
9 Nov 2023 Declarations of interestVisiting Member Councillor Stammers declared she was a neighbour of the speaker in support of item 4.2. Decided Open
9 Nov 2023 Confirmation of minutes of meeting held on 14th september 2023Confirmed Decided Open
9 Nov 2023 (22/03824/FULL1) - 15 Madeline Road, Penge, London, SE20 8AYPERMISSION Decided Open
9 Nov 2023 (23/02527/FULL1) - Pavilion and Public Conveniences, Goddington Park, Goddington Lane, Orpington, BR6 9DHPERMISSION Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies