Item287
Resolved
RESOLVED that (1) Council be recommended to approve an increase in the capital budget for the Waste 4 Fuel scheme by £1.880m, resulting in a total scheme cost of £4.589m in the capital programme, subject to additional funds being provided by DEFRA. (2) £47k be allocated from the 2017/18 Central Contingency to fund the increase in the scheme in addition to the further allocation from the Environment Agency. (3) The Contract Procedure Rules be waived to allow the contract to be awarded directly to Veolia. (4) It is noted that the total cost will be funded by contributions of £4.017m from the Environment Agency and £0.573m from the Council.
Word for word from the decision Bromley published for this meeting.
Source: cds.bromley.gov.uk