Resolved
RESOLVED that:- 1 the report be noted and the Committee’s comments be provided to Members of the Executive. 2 The Executive be recommended to:- 2.1 agree that the Director of Housing, Planning, Property and Regeneration has authority to approve the design work at RIBA stages 2 and RIBA stages 4 in consultation with the Portfolio Holder for Renewal, Recreation and Housing instead of the scheme returning to Committee at these points in the programme to enable speed of delivery. All Members (particularly Ward Members) should be kept informed of progress on a regular basis; 2.2 delegate the decision to proceed to procurement for the works contract at an estimated value of £1.055m to the Director of Housing, Planning, Property and Regeneration in consultation with the Portfolio Holder; and 2.3 delegate the decision to award the contract for the works contract referenced in 2.3 to the Director of Housing, Planning, Property and Regeneration in consultation with the Portfolio Holder.