Item290
Resolved
RESOLVED that (1) The estimated underspend of approximately £372K for the CRM capital project scheme be noted as outlined in the report; the actual figure will be confirmed within the capital scheme project closure report. (2) Additional expenditure be approved of £175K on the website redesign and upgrade project, to complement the CRM replacement project. (3) It is agreed that the website redesign and upgrade project be funded from the existing CRM capital programme provision and the capital programme be amended to reflect the revised total estimated costs to be funded of £625k.
Word for word from the decision Bromley published for this meeting.
Source: cds.bromley.gov.uk