CRYSTAL PALACE SUBWAY CONTRACT AWARD REPORT AND UPDATE

Approved Scrutiny 1 paper

Renewal, Recreation and Housing Policy Development and Scrutiny Committee approved this item on Wednesday 26 January 2022. Below is the council's own wording, with the papers it was decided on.

Item63

Resolved

RESOLVED that the Executive be recommended to – (1) Delegate authority to the Director of Housing, Planning and Regeneration in consultation with the Portfolio Holder for Renewal, Recreation & Housing and the Director of Finance, to approve the acceptance of any additional grants required to deliver this scheme to completion, namely any further grants that come forward from the National Lottery Heritage fund and/or Historic England. (2) Delegate authority to the Director of Housing, Planning and Regeneration in consultation with the Portfolio Holder for Renewal, Recreation & Housing and the Director of Finance, to approve increasing the Capital Programme for the Subway Restoration Project up to a maximum of £3.597m, to enable the completion of the full restoration scheme, subject to securing additional grant funding, noting that if additional grant funding is not secured, the addition to the Capital Programme will not be required. (3) Delegate authority to the Director of Housing, Planning and Regeneration and the Director of Corporate Services, to agree the commercial heads of terms for a legal agreement proposed to be entered into between the Council and the London Borough of Southwark, outlining the Council’s future maintenance and management responsibilities for the Subway upon practical completion of the works . (4) Delegate authority to the Director of Corporate Services and Governance to execute all and any ancillary legal documentation relating to the proposed legal agreement referred to in paragraph (3) above. (5) Delegate authority to the Director of Housing, Planning and Regeneration and the Director of Corporate Services and Governance, to agree the commercial heads of terms for a works licence with the London Borough of Southwark, and the construction contractor, to enable the undertaking of the restoration works. (6) Delegate authority to the Director of Corporate Services and Governance to execute all and any ancillary legal documentation relating to the proposed works licence referred to in (5) above. (7) See the Part 2 Report for further recommendations in relation to the award of the works contract.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Renewal, Recreation and Housing Policy Development and Scrutiny Committee
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
RRH PDS 260122 CP Subway Part 1 ReportReport 343 KB Copy on its way

At this meeting

Whole meeting
50MINUTES OF THE RENEWAL, RECREATION AND HOUSING PDS COMMITTEE MEETING HELD ON 16 NOVEMBER 2021Decided 51MATTERS OUTSTANDING FROM PREVIOUS MINUTES AND WORK PROGRAMMENoted 53HPR PORTFOLIO PLAN 2021/22Noted 54CAPITAL PROGRAMME MONITORINGNoted 55CONFIRMATION OF ARTICLE 4 DIRECTIONS TO REMOVE PERMITTED DEVELOPMENT RIGHTS FOR UPWARDS EXTENSIONS IN SPECIFIED AREASDecided 56CONFIRMATION OF ARTICLE 4 DIRECTIONS TO REMOVE PERMITTED DEVELOPMENT RIGHTS FOR OFFICE TO RESIDENTIAL DEMOLITION IN BROMLEY’S DESIGNATED OFFICE AND INDUSTRIAL AREASDecided 57CONFIRMATION OF ARTICLE 4 DIRECTIONS TO REMOVE PERMITTED DEVELOPMENT RIGHTS FOR C3 RESIDENTIAL TO C4 HMO USEDecided 59YOUNG PEOPLES' ACCOMMODATION AND TENANCY SUSTAINMENT SERVICEApproved 60MEADOWSHIP HOMES – UPDATE AND CHANGE TO ACQUISITION CRITERIAApproved 61HOUSE BUILDING PROGRAMMEDecided 62AFFORDABLE HOUSING PROGRAMME (AHP) 21-26 GRANT AGREEMENTSApproved
63CRYSTAL PALACE SUBWAY CONTRACT AWARD REPORT AND UPDATEThis decision
64ORPINGTON TOWN CENTRE SUPPLEMENTARY PLANNING DOCUMENT (SPD) - CONSULTATION DRAFTApproved 65PLANNING OBLIGATIONS SUPPLEMENTARY PLANNING DOCUMENT (SPD) UPDATE - CONSULTATION DRAFTApproved 66AFFORDABLE HOUSING DEVELOPMENT PROJECT AT YORK RISE, ORPINGTONNoted 67RENEWAL, RECREATION AND HOUSING PORTFOLIO DRAFT BUDGET 2022/23Noted 68DIGITAL INFRASTRUCTURE WORK PLAN UPDATENoted 69THEMATIC SESSION: PLANNING POLICY, CIL AND ECONOMIC DEVELOPMENTOn the agenda 70RENEWAL, RECREATION AND HOUSING INFORMATION BRIEFINGOn the agenda 71LOCAL GOVERNMENT ACT 1972 AS AMENDED BY THE LOCAL GOVERNMENT (ACCESS TO INFORMATION) (VARIATION) ORDER 2006, AND THE FREEDOM OF INFORMATION ACT 2000Decided 36Appendix AOn the agenda

On this subject at Bromley

Search all
  1. CRYSTAL PALACE SUBWAY CONTRACT AWARD REPORT AND UPDATEThis decision
  2. (25/04937/res) - crystal palace park, thicket road, penge, london, se20 8dtDeferred
  3. (26/01021/RES) - Crystal Palace Park, Thicket Road, Penge, London, SE20 8DTApproved
  4. (26/00738/FPA and 26/00739/LBC) - CRYSTAL PALACE NATIONAL SPORTS CENTRE, LEDRINGTON ROAD, ANERLEY, LONDON, SE19 2GADecided
  5. Crystal palace park regeneration plan update and award of main works contractApproved
  6. (23/01759/FULL1) - Crystal Palace Football Club Academy, Copers Cope Road, Beckenham, BR3 1NZ.Refused

More from Bromley Renewal, Recreation and Housing Policy Development and Scrutiny Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 Minutes of the renewal, recreation and housing pds committee meeting held on 9 june 2026That the minutes of the meeting held on 9 June 2026 be agreed and signed as a correct record. Agreed Open
1 Sep 2026 Matters outstanding and forward work programmethat the report be noted. Noted Open
1 Sep 2026 Housing, planning and regeneration portfolio plan update 2026/27 q1 updateThat progress on the actions associated with the Housing, Planning and Regeneration Portfolio Plan for Quarter 1 of t... Noted Open
1 Sep 2026 Budget monitoring reportThat the recommendations in the report be supported. Decided Open
1 Sep 2026 Capital programme monitoring - quarter 1 2026/27That the recommendations in the report be supported. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies