RESOLVED that (1) The proposals for the Bandstand be approved at a cost of £236k including a contingency budget of £27k, and be added to the Capital Programme. (2) It is noted that a five year maintenance plan has identified a liability of £18k which includes redecoration works to uphold the restored condition of the bandstand; this will be funded as set out in paragraph 3.13 of the report. (3) Delegated authority be given to the Director of Environment and Public Protection to award contracts for the Bandstand Restoration following the tendering process. (4) Delegated authority be given to the Assistant Director of Carbon Management and Greenspace to approve spend on contingency fund. (5) The Executive records its thanks to the Friends of Croydon Road Recreation Ground and all the other groups involved in supporting this project through to fruition.