Education Planned Maintenance Programme 2022/23

Noted Scrutiny 1 paper

Children, Education and Families Policy Development and Scrutiny Committee noted this item on Wednesday 15 June 2022. Below is the council's own wording, with the papers it was decided on.

Item12b

Resolved

That the Portfolio Holder be recommended to: · Note the School Condition Allocation of £383k from the Department for Education to support the capital maintenance of community and foundation schools within Bromley during 2022/23; · Note the allocation of £466k of Salix Public Sector Decarbonisation Scheme Phase 3 funding to the Local Authority for 2022/23; · Authorises the proposed expenditure of £982k capital funding allocation to the six remaining Community and Foundation schools as set out in Report CEF22034; · Agree that the maintenance works be procured either through open procurement or via the Council’s in-house Corporate Property Team. The Council may also on occasion delegate funds to schools to deliver capital works; and, · Delegate authority to the Director of Education to authorise the allocation of the £383k School Condition Allocation received for 2022/23.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Children, Education and Families Policy Development and Scrutiny Committee
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Education Planned Maintenance Programme 2022/23Report 321 KB Copy on its way

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. Education Planned Maintenance Programme 2022/23This decision
  2. Education planned maintenance programmeDecided
  3. Education planned maintenance programme 2024/25Decided
  4. Education planned maintenance programme 2023/24Noted
  5. Gateway review 1/2 approval of 2016/2017 education building maintenance budgets, education planned maintenance programme and preferred procurement optionsApproved
  6. Gateway review 0,1 & 2 approval of 2015/2016 education building maintenance budgets, education planned maintenance programme and preferred procurement optionsApproved

More from Bromley Children, Education and Families Policy Development and Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Appointment of coopted memberThat the following Co-opted Membership appointment be made to the Children, Education and Families PDS Committee for ... Decided Open
8 Sep 2026 Minutes of the children, education and families pds committee meeting held on 10 june 2026That the minutes of the meeting held on 10 June 2026 be agreed and signed as a correct record. Agreed Open
8 Sep 2026 Matters outstanding and forward work programmeThat progress on matters arising from previous meetings and the forward work programme be noted. Noted Open
8 Sep 2026 Portfolio holder updateThat the update be noted. Noted Open
8 Sep 2026 Children, education and families portfolio plan - 2026/27 q1 updateThat progress on actions associated with the Children, Education and Families Portfolio Plan be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies