NEXT STEPS FOR THE CRYSTAL PALACE PARK REGENERATION PROJECT (PART 1)

Agreed Executive 5 papers

Executive agreed this item on Wednesday 29 June 2022. Below is the council's own wording, with the papers it was decided on.

Item23

Resolved

(1) Authority be delegated to the Director of Housing, Planning, Property and Regeneration to settle, agree and negotiate the commercial terms in respect of the proposed disposal of the housing sites subject to Executive approval and disposal by way of a grant of lease to the CPPT for the Park. (2) The terms of the shadow section 106 agreement attached to the agenda (Ref. Appendix F Part 2 Report) be noted, and the following confirmed – (i) in respect of any section of CPP to be retained by the Council and developed under a planning permission granted under reference 20/00325/OUT, that it shall comply with the terms of the shadow section 106 agreement: or (ii) in respect of any section of CPP to be sold or leased, that no development shall be progressed on the relevant land until such time as the purchaser or lessee has entered into a section 106 agreement with the Council, incorporating the obligations from the shadow section 106 agreement that are relevant to the part of the site. It is acknowledged that certain obligations in relation to (non-residential) development of CPP covered in the s.106 agreement may be discharged by the Council under commercial agreements made between the purchaser/lessee and the Council. (3) An initial addition of £4.5m to the capital programme in 2023/24 be approved to forward fund the capital regeneration works in CPP, which will need to commence prior to any of the housing land capital receipt being received; it is noted that subsequent CPP works will then be funded from the capital receipt from disposal of the housing land. (4) The commencement of the forwarded funded heritage restoration capital works, limited to £4.5m (expected housing receipt £17.5m) be approved, noting that the capital programme will be regularly updated to reflect the impact of this on total scheme expenditure. (5) Officers be authorised to action the disposal of the Sydenham and Rockhill housing sites ("Housing Sites") in line with the approved Outline Planning Application. (6) The placing of advertisements of the intention to dispose of the Housing Sites and the proposed disposal by way of a grant of a long lease of CPP to CPPT to section 123(2A) of the Local Government Act 1972 and the preparation of a further report in respect of any representations received be approved. (7) Approve the following course of action in respect of the capital requirements for the regeneration of the Park: ( i ) That any capital receipt generated by the disposal of the Housing Sites will be ringfenced solely for heritage works in CPP, as required by the enabling development Planning Permission, as set out in paragraph 3.10 of the report. (ii) That any capital receipt generated by the Housing Sites will be spent on the Park’s Regeneration Plan capital scheme (including returning funds spent to date to the Council and the endowment) within ten years of the capital receipt entering the Council’s bank account. If the funds are not spent within this ...
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Exec 290622 Crystal Palace Park App AAppendix 152 KB Copy on its way
PDF
Exec 290622 Crystal Palace Park App BAppendix 112 KB Copy on its way
PDF
Exec 290622 Crystal Palace Park App CAppendix 7 MB Copy on its way
PDF
Exec 290622 Crystal Palace Park App DAppendix 5 MB Copy on its way
PDF
NEXT STEPS FOR THE CRYSTAL PALACE PARK REGENERATION PROJECT (PART 1)Report 408 KB Copy on its way

At this meeting

Whole meeting
10APOLOGIES FOR ABSENCEDecided 11DECLARATIONS OF INTERESTDecided 12QUESTIONSDecided 13TO CONFIRM THE MINUTES OF THE MEETING HELD ON 25 MAY 2022Decided 14PROVISIONAL FINAL ACCOUNTS 2021/22Noted 15CAPITAL PROGRAMME OUTTURN 2021/22Noted 16AUTHORISATION TO PROCEED TO CONTRACT: ENERGY CONTRACTSApproved 17HOMES FOR UKRAINENoted 18TRANSFORMING SEN TRANSPORT - SUPPORTING CHILDREN AND FAMILIES IN INNOVATIVE AND COST-EFFECTIVE WAYSAgreed 19ADULTS SUBSTANCE MISUSE CONTRACT VARIATIONApproved 20PROCEED TO PROCUREMENT REPORT - THE ADVOCACY SERVICES CONTRACTApproved 21ADOPTION OF THE PLANNING OBLIGATIONS SUPPLEMENTARY PLANNING DOCUMENTApproved 22LOCAL GOVERNMENT AND SOCIAL CARE OMBUDSMAN REPORTNoted
23NEXT STEPS FOR THE CRYSTAL PALACE PARK REGENERATION PROJECT (PART 1)This decision
24CONTRACT AWARD: ACCOMMODATION AND TENANCY SUSTAINMENT FOR YOUNG PEOPLE (PART 1)Approved 25PROVISION OF HOLIDAY AND SATURDAY GROUP BASED SHORT BREAKS - PERMISSION TO TENDER FOR NEW CONTRACT - GATEWAY 1 (PART 1)Approved 26FUTURE USE OF THE PHOENIX CENTRE (PART 1)Approved 27PROCEEDING TO PROCUREMENT (GATEWAY 0): HOUSING SUPPORT - MENTAL HEALTH SERVICES (PART 1)Approved 28GATEWAY 1: SUPPORTED LIVING - AT PADUA ROAD, BROMLEY ROAD AND BROSSE WAY (PART 1)Agreed 29LEARNING DISABILITY SHORT BREAKS - GATEWAY REPORT (PART 1)Noted 30CONSIDERATION OF ANY OTHER ISSUES REFERRED FROM THE EXECUTIVE, RESOURCES AND CONTRACTS POLICY DEVELOPMENT AND SCRUTINY COMMITTEEDecided 31LOCAL GOVERNMENT ACT 1972 AS AMENDED BY THE LOCAL GOVERNMENT (ACCESS TO INFORMATION) (VARIATION) ORDER 2006 AND THE FREEDOM OF INFORMATION ACT 2000Agreed 32NEXT STEPS FOR THE CRYSTAL PALACE PARK REGENERATION PROJECT (PART 2)Private 33CONTRACT AWARD: ACCOMMODATION AND TENANCY SUSTAINMENT FOR YOUNG PEOPLE (PART 2)Private 35FUTURE USE OF THE PHOENIX CENTRE (PART 2)Private 36GATEWAY 1: SUPPORTED LIVING - AT PADUA ROAD, BROMLEY ROAD AND BROSSE WAY (PART 2)Private 37LEARNING DISABILITY SHORT BREAKS - GATEWAY REPORT (PART 2)Private 29Appendix A - Questions and RepliesOn the agenda

On this subject at Bromley

Search all
  1. NEXT STEPS FOR THE CRYSTAL PALACE PARK REGENERATION PROJECT (PART 1)This decision
  2. Bromley central library relocation next stepsApproved
  3. Bromley central library relocation next steps part 1 (public) reportDecided
  4. Chislehurst library redevelopment update & next stepsAgreed
  5. Next steps for the crystal palace park regeneration planNoted
  6. Next Steps for the Crystal Palace Park Regeneration PlanApproved

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies