Resolved
RESOLVED that the Portfolio Holder for Sustainability, Green Services and Open Spaces be recommended to: 1) Note the potential options explored within the existing market to reduce costs. 2) Approve proceeding with the option to replace Bridge B with a new timber footbridge structure and authorise officers to proceed to procurement for a design and build contract to this purpose. 3) Approve an addition of £567k to the Capital Programme for the replacement of Footbridge B, with £412k to be funded from the Investment Infrastructure Fund and £155k to be funded from the Healthy Bromley Earmarked Reserve. 4) Agree to delegate authority to the Director of Environment and Public Protection in consultation with the Portfolio Holder for Sustainability, Green Services and Open Spaces to award contracts for the delivery of the footbridge replacement