CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Bromley
Executive, Wednesday 30 November 2022 at 7.00pm

BROMLEY TOWN CENTRE HEALTH AND WELLBEING CENTRE DEVELOPMENT PROPOSAL ON BEHALF OF THE NHS BROMLEY ICB

Noted Executive 2 papers

Executive noted this item on Wednesday 30 November 2022. Below is the council's own wording, with the papers it was decided on.

Item100

Resolved

It be noted that the updated proposals for the HWBC on the site of the Adventure Kingdom and that previous proposals as approved by the Executive, Resources and Contracts at its meeting on 9 th February 2022 will not be proceeding. 2. Approval be given to agree the updated proposals with the ICB for delivery of the project on behalf of the ICB such as design, procurement, terms, management and funding, as set out in sections 3.2 to 3.18 of this report, as necessary to proceed and to approve the intention to continue to work in partnership with the ICB, noting that the ICB continues to provide a cost indemnity for the Council’s costs in respect of the project. 3. Authority be delegated to the Director of Housing, Planning, Property and Regeneration in consultation with the Director of Finance, the Director of Corporate Services and the Resources, Commissioning and Contract Management Portfolio Holder, to determine and finalise, as detailed in sections 3.2 to 3.18, all necessary commercial terms, financial arrangements and to deal with publicising, if appropriate, any Open Space Notices and considering representations received and reporting to Members as necessary, and prior to or in conjunction with the proposed report at 2.4 below. 4. Approval be given for proceeding to procurement, via a compliant joint procurement arrangement with the ICB as set out in paragraph 3.12 to 3.16, for the main works contractor for the refurbishment of the HWBC site at an estimated cost of £6,500,000 (with cost indemnity for the works provided by the ICB). Noting that a formal decision on contract award (and associated contract novations) as set out in paragraphs 3.12 to 3.16 will be presented to Executive in due course prior to the commencement of contract. 5. Authority be delegated to the Assistant Director of Legal Services to enter into all relevant legal agreements as detailed in paragraphs 3.12 to 3.16 of the report and any other necessary ancillary legal documentation relating thereto, including (but not limited to): · The project agreement; · The Section 2 agreement; · Agreement for lease and lease; and · Option agreement. 6. It be noted that the ICB programme envisages construction commencement in June 2023 for completion in March 2024 in order to secure funding. Should there be significant delays to the ICB programme then the Council will need to consider whether it should proceed at that time. 7. Officers provide regular updates to Executive, Resources and Contracts PDS Committee on the ICB’s progress with the project.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
BROMLEY TOWN CENTRE HEALTH AND WELLBEING CENTRE DEVELOPMENT PROPOSAL ON BEHALF OF THE NHS BROMLEY ICBReport 575 KB Copy on its way
PDF
Enc. 1 ICB Letter of Comfort for Bromley Town Centre Health and Well Being Centre Development Proposal on behalf of the NHS Bromley ICBReport 151 KB Copy on its way

At this meeting

Whole meeting
90APOLOGIES FOR ABSENCEDecided 91DECLARATIONS OF INTERESTDecided 92TO CONFIRM THE MINUTES OF THE MEETING HELD ON 19 OCTOBER 2022On the agenda 93QUESTIONSDecided 94BUDGET MONITORING 2022-2023Noted 95CAPITAL PROGRAMME MONITORING 2022-23Noted 96OPERATIONAL PROPERTY REVIEWNoted 97PROPERTY DISPOSALSNoted 98FUTURE COUNCIL HQ OPTIONSNoted 99BIGGIN HILL AIRPORT LTD: REQUEST TO VARY USER CLAUSERefused
100BROMLEY TOWN CENTRE HEALTH AND WELLBEING CENTRE DEVELOPMENT PROPOSAL ON BEHALF OF THE NHS BROMLEY ICBThis decision
101IT TRANSFORMATIONNoted 102UK SHARED PROSPERITY FUND - BOROUGH ALLOCATIONApproved 103NIGHT TIME ENTERPRISE ZONE FOR BROMLEY TOWN CENTREApproved 104LAWN TENNIS ASSOCIATION PARKS RENOVATION FUNDApproved 105DEPOT INFRASTRUCTURE WORKS STAGE 3 UPDATENoted 106GATEWAY REPORT - PROCEED TO PROCUREMENT: SUBSTANCE MISUSEApproved 107GATEWAY 1: ADULT MENTAL HEALTH RECOVERY AND REHABILITATION SUPPORT AT HOME SERVICEApproved 108GATEWAY 2: PERMISSION TO AWARD REPORT - ADVOCACY SERVICES (PART 1)Decided 109LEARNING DISABILITY - SHORT BREAKS - CONTRACT AWARD (PART 1)Decided 110LEARNING DISABILITY SUPPORTED LIVING SERVICES - BROMLEY ROAD, BROSSE WAY AND PADUA ROAD - CONTRACT AWARD (PART 1)Decided 111MAINTAINED NURSERIES TRANSFORMATIONAgreed 112HOLIDAY AND SATURDAY GROUP BASED SHORT BREAK SERVICE FOR DISABLED CHILDREN AND YOUNG PEOPLE - CONTRACT AWARDApproved 113CONSIDERATION OF ANY OTHER ISSUES REFERRED FROM THE EXECUTIVE, RESOURCES AND CONTRACTS POLICY DEVELOPMENT AND SCRUTINY COMMITTEEDecided 114LOCAL GOVERNMENT ACT 1972 AS AMENDED BY THE LOCAL GOVERNMENT (ACCESS TO INFORMATION) (VARIATION) ORDER 2006 AND THE FREEDOM OF INFORMATION ACT 2000Agreed 115CAPITAL PROGRAMME MONITORING 2022-23 (PART 2 APPENDIX)Private 116OPERATIONAL PROPERTY REVIEW (PART 2)Private 117PROPERTY DISPOSALS (PART 2)Private 118FUTURE COUNCIL HQ OPTIONS (PART 2)Private 119BIGGIN HILL AIRPORT LTD: REQUEST TO VARY USER CLAUSE (PART 2)Private 120GATEWAY 2: PERMISSION TO AWARD REPORT - ADVOCACY SERVICES (PART 2)Private 121LEARNING DISABILITY SUPPORTED LIVING SERVICES - BROMLEY ROAD, BROSSE WAY AND PADUA ROAD - CONTRACT AWARD (PART 2)Private 122LEARNING DISABILITY SHORT BREAKS - CONTRACT AWARD (PART 2)Private 123HOLIDAY AND SATURDAY GROUP BASED SHORT BREAK SERVICE FOR DISABLED CHILDREN AND YOUNG PEOPLE - CONTRACT AWARD (PART 2)Private 124DEPOT INFRASTRUCTURE WORKS STAGE 3 UPDATEPrivate 36Appendix AOn the agenda

On this subject at Bromley

Search all
  1. BROMLEY TOWN CENTRE HEALTH AND WELLBEING CENTRE DEVELOPMENT PROPOSAL ON BEHALF OF THE NHS BROMLEY ICBThis decision
  2. (23/02633/FULL1) - Waitrose, 45 Masons Hill, Bromley, BR2 9HD (Bromley Town Ward)Agreed
  3. Application to Register Land Described as Barnet Wood, Mazzards Wood, Brook Wood, Scrogginghall Wood as a New Town or Village Green (Bromley Common & Holwood and Hayes & Coney Hall Wards)Refused
  4. (21/05585/full1) - 2 - 4 ringers road and 5 ethelbert road, br1 1ht (bromley town ward)Refused
  5. Adoption of the bromley town centre supplementary planning documentApproved
  6. (23/01547/full1) - car park, station road, bromley (bromley town ward)Approved

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies