OPERATIONAL PROPERTY REPAIR PROGRAMME UPDATE

Noted Executive 1 paper

Executive noted this item on Wednesday 29 November 2023. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

That 1) The contents of this report be noted and the following recommendations be agreed: a) To note that up to £ 1.046m of the OPR budget as planned will be used for the essential repair of surface car parks required to maintain statutory service. b) To proceed to procurement for the works contract for the essential repair of surface car parks at an estimated value of up to £ 1m as set out in paragraphs 3.13, with delegated authority to the Director of Housing, Planning, Property and Regeneration to approve the detailed procurement strategy and contract award. c) To approve the procurement of Construction Consultancy Services via a competitive tender process utilising the NHS SBS framework for consultants that can provide a Building Surveying led multidisciplinary team to design and deliver the Strategic Property OPR Workstreams, with delegated authority to the Director of Housing, Planning, Property and Regeneration to approve the detailed procurement strategy. d) To note that up to an additional £ 0.95M of the OPR budget as planned will be used for Building Surveying led multidisciplinary teams to design and deliver the Strategic Property Workstreams. The total budget value of the appointment(s) is estimated to be £ 2.4m . e) To agree to delegate authority to the Director of Corporate Services and Governance to enter and manage legal matters relating to these services and works to allow matters to progress. 2. Full Council be recommended to agree a supplementary capital estimate of £ 3.0m for surveys and potential remedial works associated with Reinforced Autoclaved Aerated Concrete (RAAC).
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
OPERATIONAL PROPERTY REPAIR PROGRAMME UPDATEReport 352 KB Copy on its way

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. OPERATIONAL PROPERTY REPAIR PROGRAMME UPDATEThis decision
  2. Extended operational property reviewAgreed
  3. Operational property refurbishment programme - procurement and award of construction consultancy servicesNoted
  4. Operational property reviewNoted

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies