LEISURE CENTRE MAJOR WORKS PROGRAMME - APPROVAL TO PROCEED

Approved Executive 2 papers

Executive approved this item on Thursday 18 April 2024. Below is the council's own wording, with the papers it was decided on.

Item161

Resolved

That 1. Authority be delegated to the Director for Housing, Planning, Property and Regeneration, in consultation with the Renewal, Recreation and Housing Portfolio Holder, to enter into a Full Repair and Insurance Lease, up to a period terminating no later than March 31st 2059, with the tenant operator named in the Part 2 report, after works are completed for both West Wickham and the Walnuts Leisure Centres, as set out in paragraphs 3.2 to 3.6 of the Part 2 report. 2. The acceptance of £ 296k grant funding from Sport England to fund solar panels and pool covers at West Wickham Leisure Centre be approved. 3. Subject to plans remaining within budget at the end of RIBA 4 , authority be delegated to the Director of Housing, Planning and Regeneration, in consultation with the Director of Corporate Services and Governance, to enter into a Development Agreement with Alliance Leisure Services to deliver the works and services (project management and quantity surveying) contained within this report for both the West Wickham and Walnuts Leisure Centres. 4. The release of £640,750 from the Section 106 Carbon Offset Fund scheme, as accrued through developer contribution, be approved for air handling units and building energy management systems to support additional carbon reduction and improved energy efficiency of both the Walnuts and West Wickham leisure centres. 5. Authority be delegated to the Director of Environment & Public Protection, in consultation with the Portfolio Holder for Environment and the Director of Housing, Planning and Regeneration, to approve the allocation of additional Section 106 Carbon Offset Funding, up to 20%, should there be an overspend on the installation of air handling units and building energy management systems. 6. Authority be delegated to the Director of Environment & Public Protection, in consultation with the Portfolio Holder for Environment and the Director of Housing, Planning and Regeneration, to approve the allocation of additional Section 106 Carbon Offset Funding, up to £ 150k , for further identified carbon reduction projects during the leisure centre major works programme. 7. The acceptance of a £ 1m contribution from the tenant operator towards the major works be approved. 8. £ 10.949m from the OPR’s budget for leisure centres to fund the proposed works and services at the Walnuts Leisure Centre be approved. 9. An additional budget of £232,310 above the OPR allowance, funded from OPR Contingency (see 6.4), required to deliver the major works be approved. 10. The plans for the Walnuts Leisure Centre as set out on pages 30-32 of the Part 1 Appendices and laid out in paragraphs 3.38-3.55 of this report be approved. 11. It be noted that any Planning Applications required will be submitted. 12. £402,390 from the OPR’s budget for leisure centres to fund the proposed enabling works package at West Wickham Leisure Centre be approved. 13. £ 15.374m from the OPR’s budget for leisure centres to fund the proposed works and services at West Wickham Leisure Centre be approved. 14. An additional budget of £550,000, above the OPR allowance, ...
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
App.: Leisure Centre Major Works Part 1 (Public), 17/04/2024 Renewal, Recreation and Housing Policy Development and Scrutiny CommitteeReport 10 MB Copy on its way
PDF
LEISURE CENTRE MAJOR WORKS PROGRAMME: APPROVAL TO PROCEEDReport 808 KB Copy on its way

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. LEISURE CENTRE MAJOR WORKS PROGRAMME - APPROVAL TO PROCEEDThis decision
  2. (26/01512/FPA) - Walnuts Leisure Centre, Lych Gate Road, Orpington, BR6 0TJApproved
  3. West wickham leisure centre update reportDecided
  4. (24/03198/FULL1) - Walnuts Leisure Centre, Lych Gate Road, Orpington, BR6 0TJApproved
  5. (24/02648/FULL1) - West Wickham Leisure Centre, Station Road, West Wickham, BR4 0PYApproved
  6. West wickham leisure centre enabling works variationDecided

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies