BELLEGROVE HOUSING REDEVELOPMENT - PLANNING SUBMISSION AND PROCEED TO PROCUREMENT

Approved Executive 2 papers

Executive approved this item on Wednesday 27 November 2024. Below is the council's own wording, with the papers it was decided on.

Item111

Resolved

That 1) The addition of the Bellegrove Housing Development to the Capital Programme at a cost of £ 29m be approved, noting that this is the scheme cost, not the cost to the Council. This will allow the Housing Investment Fund to be ‘refunded’ ensuring funding is available for future feasibility exercises. 2) The submission of necessary Planning Applications for the Bellegrove Housing Development be approved. 3) The completion of pre-construction stages be approved, covering RIBA 3b – 4, costing c.£ 490k (inclusive within the overall budget figure), noting that the contract for the architect-led multi-disciplinary team has already been approved by Executive in HPR2024 /007 but authority currently only extends to the completion of RIBA 3a . 4) Subject to a successful determination of the Bellegrove Planning Application, expected in May 2025, authority be delegated to the Director of Housing, Planning, Property & Regeneration to approve separate Proceeding to Procurement Gateway Reports for the demolition of the site and the design and build works contract for the Bellegrove scheme at an estimated value of £ 25.5m , in agreement with the Portfolio Holder, the Assistant Director Governance & Contracts, the Director of Corporate Services and the Director of Finance, noting that award of contract and commencement of the scheme, if considered financially viable, will be subject to Executive decision in due course. 5) External borrowing in relation to the financing requirements of the Bellegrove scheme, as set out in Section 6 and Paragraph 3.28 of this report be approved. 6) Authority be delegated to the Director of Housing, Planning, Property & Regeneration, in consultation with the Portfolio Holder for Renewal, Recreation and Housing and the Portfolio Holder for Adult Care and Health, to convert the thirteen one-bed ground floor units into Supported Living accommodation for Adult Social Care should the viability assessment prove to be positive. 7) It be note that this scheme will be progressed subject to a Secretary of State Direction to either (a) hold the properties outside of the Housing Revenue Account ( HRA ) or (b) by Secretary of State’s Direction to allow the transfer of an appropriate sum from the General Fund to the HRA as set out in Paragraph 6.6 of the report.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
App. A: Scheme Images, 12/11/2024 Renewal, Recreation and Housing Policy Development and Scrutiny CommitteeReport 3 MB Copy on its way
PDF
BELLEGROVE HOUSING REDEVELOPMENT: PLANNING SUBMISSION AND PROCEED TO PROCUREMENTReport 721 KB Copy on its way

At this meeting

Whole meeting
97APOLOGIES FOR ABSENCEDecided 98DECLARATIONS OF INTERESTDecided 99QUESTIONSDecided 100TO CONFIRM THE MINUTES OF THE MEETING HELD ON 16 OCTOBER 2024Agreed 101BUDGET MONITORING 2024/25Noted 102CAPITAL PROGRAMME MONITORING - QUARTER 2 2024/25Noted 103MEMBER AND OFFICER INDEMNITYDeferred 104BECKENHAM PUBLIC HALLS, BROMLEY ROAD, BECKENHAM BR3 5JE - FREEHOLD DISPOSALDecided 105PURCHASE OF A NEW CHILDREN'S HOMEAgreed 106CONTRACT AWARD FOR THE BROMLEY SPECIALIST STOP SMOKING SERVICEAgreed 107ADULT SERVICES TRANSFORMATION PROGRAMME - ADULT SOCIAL CARE WORKFORCE STRATEGY 2024 TO 2028Noted 108VEOLIA ENVIRONMENTAL SERVICES CONTRACT EXTENSIONAgreed 109HOUSING ASSISTANCE POLICY (APPROVAL TO ADOPT NEW POLICY)Approved 110HOMELESSNESS AND ROUGH SLEEPING STRATEGY 2025-2030Approved
111BELLEGROVE HOUSING REDEVELOPMENT - PLANNING SUBMISSION AND PROCEED TO PROCUREMENTThis decision
112CONSIDERATION OF ANY OTHER ISSUES REFERRED FROM THE EXECUTIVE, RESOURCES AND CONTRACTS POLICY DEVELOPMENT AND SCRUTINY COMMITTEEDecided 113LOCAL GOVERNMENT ACT 1972 AS AMENDED BY THE LOCAL GOVERNMENT (ACCESS TO INFORMATION) (VARIATION) ORDER 2006 AND THE FREEDOM OF INFORMATION ACT 2000Agreed 114EXEMPT MINUTES OF THE MEETING HELD ON 16 OCTOBER 2024Agreed 115PART 2: CAPITAL PROGRAMME MONITORING - QUARTER 2 2024/25Private 116PART 2: BECKENHAM PUBLIC HALLS, BROMLEY ROAD, BECKENHAM BR3 5JE - FREEHOLD DISPOSALPrivate 117PART 2: PURCHASE OF A NEW CHILDREN'S HOMEPrivate 118PART 2: CONTRACT AWARD FOR THE BROMLEY SPECIALIST STOP SMOKING SERVICEPrivate 119PART 2: VEOLIA ENVIRONMENTAL SERVICES CONTRACT EXTENSIONPrivate 120ACADEMY INFORMATION SYSTEMDecided 25Appendix 1On the agenda

On this subject at Bromley

Search all
  1. BELLEGROVE HOUSING REDEVELOPMENT - PLANNING SUBMISSION AND PROCEED TO PROCUREMENTThis decision
  2. Bellegrove housing redevelopment - planning submission and proceed to procurementDecided

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies