Resolved
RESOLVED that £200,000 be allocated in the 2019/20 Programme for new build housing feasibility costs to be funded from HRA capital receipts.
Finance and Resources Committee decided this item on Thursday 10 October 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that £200,000 be allocated in the 2019/20 Programme for new build housing feasibility costs to be funded from HRA capital receipts.
To seek approval to undertake feasibility work on sites being considered for new build housing funded by the Housing Revenue Account.
2. Background and detail
The Housing Delivery Plan was approved by Housing Committee on 5 June 2019. Providing new build housing on Council owned sites is a key component of the delivery plan to help ensure a minimum of 230 new social rented homes are provided over the next 10 years.
The new build housing programme requires external construction consultants to be appointed in order to progress the relevant feasibility work. A list of likely consultancy work required is provided in the appendix.
Due to a lack of internal resources and the specialist nature of these tasks, the Council will need to commission the work externally.
Work is already underway with the Interim Procurement and Contracts Officer to undertake the necessary procurement procedures for these contracts including the potential use of existing OJEU compliant Construction Frameworks. All appointments will be compliant with the Council’s constitution and standing orders.
It is proposed that an initial sum of £200,000 be allocated in the 2019/20 capital programme for feasibility costs to initiate new build housing schemes as set out in the Housing Delivery Plan. Once suitable schemes have been identified and the required preparatory work as set out in the appendix has been completed, these schemes will be presented to the Finance and Resources Committee for consideration of their formal incorporation within the capital programme.
The initial sum of £200,000 can be met from available receipts from the sale of Council houses which amounted to over £4,097,800 at 31 August 2019.
Recommendation The Committee is asked to RESOLVE that £200,000 be allocated in the 2019/20 Programme for new build housing feasibility costs to be funded from HRA capital receipts.
Background papers Nil Finance and Resources Committee 10 October 2019
APPENDIX Feasibility consultancy work required
1) Architect/Principal Designer 2) Planning consultant 3) Employer's Agent/Project Manager 4) Quantity Surveyor/Cost Consultant 5) External Legal advice – due diligence 6) Legal Search fees 7) Utility Reports 8) Structural/Civil Engineering advice 9) Environmental consultants: Ground condition/site investigation work 10) Site Surveys – not all will be required on every site; Asbestos survey, Tree survey, Ecology survey, Topographical survey, Utility CAT scans, f) Archaeological survey,
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HOUSING DELIVERY PLAN: NEW BUILD HOUSING FEASIBILITY COSTSReport | 217 KB | DownloadRead as text |
Follow Finance and Resources Committee at Broxtowe and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Feb 2022 | Business plans and financial estimates 2022/23 - 2024/25RESOLVED that the Business Plans relating to the support service areas be approved. 2. RECOMMENDED to Council that th... | Approved | Open |
| 10 Feb 2022 | Budget proposals and associated strategiesRESOLVED to approve: 1. The business plans for the Council’s corporate priorities and support functions, subject to a... | Approved | Open |
| 10 Feb 2022 | Capital programme amendments 2021/22RESOLVED that the capital budget variations for 2021/22 as set out in the appendix be approved. | Approved | Open |
| 10 Feb 2022 | Grants to voluntary and community organisations, charitable bodies and individuals involved in sports, the arts and disability matters 2021/22RESOLVED that the Grant applications be dealt with as follows: New Stapleford Community Association £4,000 Stapleford... | Decided | Open |
| 10 Feb 2022 | Civic event-freeman/alderman of the boroughRESOLVED that the finances be provisionally approved subject to Council’s approval of the establishment of a special ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.