MUSHROOM FARM - ADDITIONAL INDUSTRIAL UNITS

Decided Finance 1 paper

Finance and Resources Committee decided this item on Thursday 9 July 2020. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

RESOLVED that the 2020/21 capital programme be amended such that the budget for additional industrial units at Mushroom Farm be increased from £219,000 to £270,000 with financing as set out in the report.
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Finance and Resources Committee

Purpose of report

To provide an update of progress on the capital scheme to provide additional industrial units at Mushroom Farm and seek approval to amend the budget for the scheme.

Background

The 2020/21 capital programme approved by the Committee on 13 February 2020 includes General Fund schemes that are on a “reserve list” and will only be brought forward for approval once a source of funding has been identified.

Included on the “reserve list” was a scheme for £246,400 to construct 3 industrial units at Mushroom Farm in Eastwood to add to the existing seven units at the site. Further information on this scheme is set out in a report to the Jobs and Economy Committee on 5 September 2019.

A bid for funding towards this scheme was submitted to the D2N2 Local Enterprise Partnership (LEP) who stated that they would provide £124,000 towards the cost. As reported to Jobs and Economy Committee on 5 September 2019, the cost of the scheme was estimated to be £219,000 as opposed to the figure of £246,400 initially reported. This would require a contribution from the Council of £95,000 which can be met from borrowing. Following the cancellation of the meeting of this committee scheduled for 2 April 2020, the Chief Executive used her urgency powers on that date to approve the removal of the scheme from the “reserve list” and allow it to proceed with a revised budget of £219,000.

Following the successful submission of an Expression of Interest (EOI) and Full Business Case (FBC) to the LEP and their approval of £124,000 towards the cost of the scheme, a procurement exercise was undertaken. This indicated a projected cost of £270,000 for the scheme. The events that led to this are summarised in appendix 1 with further financial details in appendix 2.

The LEP have indicated that, based on the projected cost of £270,000, they would be prepared to increase their contribution towards the scheme from £124,000 to £160,000 if the Council’s contribution were to increase by £15,000 from £95,000 to £110,000. As previously agreed, the cost of the Council’s contribution would be financed by borrowing.

Recommendation The Committee is asked to RESOLVE that the 2020/21 capital programme be amended such that the budget for additional industrial units at Mushroom Farm be increased from £219,000 to £270,000 with financing as set out in the report. Background papers Nil Finance and Resources Committee 9 July 2020

APPENDIX 1 Project Summary

The Mushroom Farm scheme will see the construction of three additional light industrial (B2 use) units at the site in Eastwood surplus parking and service areas. This is intended to provide additional employment in the north of the borough as well as increased income to the Council. The existing site consists of seven 80m2 units. These are all currently occupied and provide the Council with rental income in excess of £28,000 per annum with an average rent of £4,000 pa per unit.

Project Expression of Interest (EOI)

Approval to submit an EOI to the D2N2 LEP Local Growth Fund (LGF) programme for grant funding towards the project costs, was agreed by members of the Jobs and Economy committee held on the 5 September 2019.

Some pre-requisites of the EOI submission included confirmation of; site ownership, planning permission, an agreed capital co-funding contribution and ability to draw down grant funding by 31 March 2021.

Planning permission was later secured at committee on 8 October 2019 for the proposed scheme. Planning ref 19/00477/FUL.

Initial project costings were sought for the purposes of an EOI submission, at £219,000.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MUSHROOM FARM: ADDITIONAL INDUSTRIAL UNITSReport 289 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 16 attended
SJ
Councillor Stephen J CarrVice-Chair, present
EC
Councillor Edward CubleyCommittee Member, present
SE
Councillor Shane EasomCommittee Member, present
RI
Councillor Richard I Jacksonex-Officio, present
GM
Councillor Greg MarshallChair, present
PJ
Councillor Philip J OwenCommittee Member, present
PD
Councillor Paul D SimpsonCommittee Member, present
TR
Councillor Trish Roberts-ThomsonCommittee Member, present
MR
Councillor Milan Radulovic MBECommittee Member, present
PL
Councillor Patrick LallyCommittee Member, present
EK
Councillor Eric KerryCommittee Member, present
BC
Councillor Barbara C CarrCommittee Member, apologies, sent representative

All 16 on the meeting page

On this subject at Broxtowe

Search all
  1. MUSHROOM FARM - ADDITIONAL INDUSTRIAL UNITSThis decision
  2. Mushroom Farm Industrial Units - New BuildApproved

More from Broxtowe Finance and Resources Committee

All decisions
MeetingDecisionOutcome
10 Feb 2022 Business plans and financial estimates 2022/23 - 2024/25RESOLVED that the Business Plans relating to the support service areas be approved. 2. RECOMMENDED to Council that th... Approved Open
10 Feb 2022 Budget proposals and associated strategiesRESOLVED to approve: 1. The business plans for the Council’s corporate priorities and support functions, subject to a... Approved Open
10 Feb 2022 Capital programme amendments 2021/22RESOLVED that the capital budget variations for 2021/22 as set out in the appendix be approved. Approved Open
10 Feb 2022 Grants to voluntary and community organisations, charitable bodies and individuals involved in sports, the arts and disability matters 2021/22RESOLVED that the Grant applications be dealt with as follows: New Stapleford Community Association £4,000 Stapleford... Decided Open
10 Feb 2022 Civic event-freeman/alderman of the boroughRESOLVED that the finances be provisionally approved subject to Council’s approval of the establishment of a special ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies