Resolved
It was agreed that the Beeston Town Centre residential development should be added to the report.
Jobs and Economy Committee agreed this item on Thursday 10 June 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed that the Beeston Town Centre residential development should be added to the report.
Jobs and Economy Committee 10 June 2021
APPENDIX Regeneration Sites Update June 2021 Site Progress Notes Application Latest Expected projected start date (best estimate) Moults Yard, Updated planning application recently Development NA Stapleford submitted to amend house types. Started but Verbal update on night regarding now delayed. progress re the S106 agreement (associated with this application), which is nearing completion. Have spoken to developer who is keen to get on the site and build out.
The Manor There are containers to the back of the 2021 Unknown Garage Site, site, enforcement proceeding Toton undertaken on these.
Hot food uses on site, can be there for 56 days a year.
Application for car wash was recently refused, enforcement action under consideration but the car wash use has now ceased, thus removing the issue.
We have had further discussions with the owners about submitting a planning application, which they have suggested they want to do, but to date no progress.
Cossall Hybrid planning application and was Revised Unclear Industrial approved at a previous planning scheme for 64 Estate committee. Future progress unclear. dwellings approved. Beeston Ongoing discussions with Network Rail Application 2021 Cement about bringing this site forward. stage. Depot Planning application (20/00745/FUL) submitted for 42 dwellings earlier this year although currently resolving some issues on viability. Application went to planning committee in April and was deferred for further clarification and updates on certain matters. This application returned to Planning Committee on 2 June 2021. Jobs and Economy Committee 10 June 2021
Site Progress Notes Application Latest Expected projected start date (best estimate) Boots Work underway on access and S106 Meetings 2021 discussions at an advanced stage. continue to Several discussions taken place about take place to the proposed submission of the progress reserved matters application, though as matters. yet the outline permission has still not been signed.
Bartons Development has commenced on site Resolved to Development for the 29 house scheme. grant planning commenced. permission for No further REM applications for the 29 houses (full) remaining phases have been submitted and 221 but pre submission meetings have outline. taken place and these are expected imminently.
Cemex Outline planning application approved Approved. 2021 Concrete for 20 dwellings.
Delivery timescales likely to depend on the programme for decommissioning of the depot and submission of reserved matters. Discussions are ongoing between the planning department and the agents.
Eastwood Discussions are on-going with the land Pre application 2021 Road/ Maws owner and planning agent to try and discussions Lane bring forward both sites. are on-going and early draft Topographical surveys have now been plans expected carried out. but limited contact There are still some ownership issues recently. around the access to the northern site that are slowly being resolved. This issue was recently chased with the applicant/ land owner who has suggested that there are some ‘legal issues’ holding this site up. Unfortunately, nothing further. Jobs and Economy Committee 10 June 2021
Site Progress Notes Application Latest Expected projected start date (best estimate) Walker Transport assessment work being 2021 2021 Street carried out currently by the County Eastwood Council, with Broxtowe recently transferring its share of the relevant funding. Recent planning applications submitted on this site.
Stoney The underutilised site opposite Unknown Unknown Street Sainsbury’ and the ‘Bell’ in the Beeston pedestrianized area.
Discussions have taken place with the Agent marketing the site, but no real progress. It would appear that the price sought for the site is unrealistic in the current market. Nothing moved for a while.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
NOTE 2.1 Regeneration Sites UpdateReport | 40 KB | DownloadRead as text |
PDF |
UPDATE ON KEY SITESReport | 7 KB | Download |
Follow Jobs and Economy Committee at Broxtowe and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 31 Mar 2022 | Update in relation to the hmo supplementary planning document to support the upcoming article 4 directionRESOLVED that the percentage for the radius approach be set at 10% relative to the total number of known HMOs. RESOLV... | Decided | Open |
| 31 Mar 2022 | Borough wide job clubs initiativeRESOLVED that subject to there being proven demand and an absence of alternative support, a commitment of up to £4,00... | Approved | Open |
| 27 Jan 2022 | Business plans and financial estimates 2022/23 - 2024/25RESOLVED that the Business Growth Business Plan be approved. 2. RECOMMENDED that the Finance and Resources Committee ... | Approved | Open |
| 27 Jan 2022 | Revised statement of community involvementRESOLVED that the SCI be approved for consultation. | Approved | Open |
| 27 Jan 2022 | Levelling up bids for eastwood and kimberleyRESOLVED to endorse to the proposals for the respective emerging LUF bids for Kimberley and Eastwood bids and feed th... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.