Resolved
RESOLVED that the Strategy and the four strategic principles set out within be adopted.
Policy and Performance Committee approved this item on Thursday 2 December 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Strategy and the four strategic principles set out within be adopted.
To seek approval for an Energy Procurement Strategy 2021 - 2025.
2. Background and detail
The Council (including LLeisure and Bramcote Crematorium) currently spends approximately £400,000 per annum on electricity and £225,000 per annum on gas. These figures are from 2019/20 as the 2020/21 figures were significantly skewed by COVID-19.
The updated Energy Procurement Strategy, included at the appendix, aims to establish the parameters for the Council’s energy (gas and electricity) procurement process for the next four years. This evaluation process is required to ensure the Council is achieving value for money in its procurement of gas and electricity supplies and also business continuity ensuring the continuation of the energy supply.
The Council is currently using an Eastern Shires Purchasing Organisation (ESPO) framework for both the supply of gas and electricity.
The Council’s gas supply contract is due to end on 31 March 2023. Procurement of the new contract needs to start imminently in order to have a new contract in place for 2023 onwards by March 2022 (gas is purchased up to one year in advance).
The electricity supply contract is due to end on 30 September 2023 and needs to have a new contract in place for 2023 onwards by September 2022 (electricity is also purchased up to one year in advance).
A full Equalities Impact Assessment has not been undertaken for this strategy as initial screening has indicated that the strategy relates to the means of purchase of energy for use within the Council’s own buildings, with no identifiable impact on the wider community or employees in terms of equalities.
There are no immediate financial implications arising from this report.
Recommendation Committee is asked to RESOLVE that the Strategy and the four strategic principles set out within be adopted.
Background papers Nil Policy and Performance Committee 2 December 2021 APPENDIX
BROXTOWE BOROUGH COUNCIL
ENERGY PROCUREMENT STRATEGY 2021 - 2025
December 2021 Policy and Performance Committee 2 December 2021 Contents
1.ENERGY PROCUREMENT RECOMMENDATIONS 2.INTRODUCTION AND BACKGROUND 2.1 Purpose of the Energy Procurement Strategy 2.2 Why is the Procurement of Energy Different? 2.3 What is an Energy Framework? 3.PROCUREMENT CONSIDERATIONS 3.1 Council Requirements 3.2 Security of Supply 3.3 Risk and Price Volatility (Purchasing Options) 3.4 Sustainability 3.5 Legislation 3.6 Selection and Evaluation of Frameworks Appendix Analysis of Purchasing Options
Glossary
Central Purchasing Body (CPB) An organisation set up to purchase goods, services and works on behalf of other contracting authorities.
Contracting Authority Means the State, regional or local authorities, bodies governed by public law, associations formed by one or several of such authorities or one or several of such bodies governed by public law.
Framework An agreement or other arrangement between one or more contracting authorities and one or more economic operators which establishes the terms (in particular the terms as to price and, where appropriate, quantity) under which the supplier will enter into one or more contracts with a contracting authority in the period during which the framework agreement applies.
Framework Provider A contracting authority that has tendered out for energy suppliers on behalf of other contracting authorities (can be a CPB or an individual public sector organisation). Policy and Performance Committee 2 December 2021 1. ENERGY PROCUREMENT RECOMMENDATIONS
The recommendations contained in this Strategy are:
a) The Council is to use a ‘compliant’ and existing CPB framework to ensure security of supply and the use of energy market experts.
b) Committee authorises the Deputy Chief Executive to purchase ‘green’ energy provided the premium is 5% or less than a non-‘green’ option. Relevant committee approval is required for a premium in excess of 5%.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ENERGY PROCUREMENT STRATEGY 2021: 2025Report | 305 KB | DownloadRead as text |
Follow Policy and Performance Committee at Broxtowe and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Mar 2022 | Appointment of chairRESOLVED that G Marshall be appointed Chair for the meeting. | Decided | Open |
| 24 Mar 2022 | Revision of the fire safety management policyRESOLVED that the revised Fire Safety Management Policy be approved. | Approved | Open |
| 24 Mar 2022 | Revisions of the control of legionella bacteria in water policyRESOLVED that the revised Control of Legionella Bacteria in Water Systems Policy be approved. | Approved | Open |
| 24 Mar 2022 | Ict strategy 2022 to 2027RESOLVED that, with effect from 24 March 2022, the new ICT Strategy be adopted. | Approved | Open |
| 24 Mar 2022 | Equality and diversity annual report 2021/2022RESOLVED that the proposed Equalities Objectives 2022/23 and action plan for 2022/24 contained in appendices 2 and 4 ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.