Resolved
RESOLVED that: 1. That further information is gained regarding “early win” projects and the need for the EM Devco Ltd to provide tangible projects. 2. Encourage further engagement with Neighbourhood forums.
Advisory Shareholder Sub Committee decided this item on Monday 17 October 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that: 1. That further information is gained regarding “early win” projects and the need for the EM Devco Ltd to provide tangible projects. 2. Encourage further engagement with Neighbourhood forums.
E The Cabinet is asked to: 1. REVIEW the year 1 update and confirm if any further information is required. 2. To APPROVE the year 2 contribution of £167,000.
C 3. To COMMENT on the year 2 plans.
3. Detail
EN In 2020, Leicestershire County Council, Nottinghamshire County Council, Broxtowe Borough Council, North-West Leicestershire District Council, and Rushcliffe Borough Council agreed to establish an Interim Vehicle, EM DevCo Ltd, to focus on plans for the co-ordinated delivery of development and infrastructure at Toton and Chetwynd; Ratcliffe Power Station and East Midlands Airport Area. The Interim Vehicle has been established to drive forward the proposition whilst the parliamentary processes required to establish the proposed new model of Locally Led Urban Development Corporation (LLUDC) take place. ER A full update on the Oversight Authority for 2022/23 is included in the appendix.
Broxtowe Borough Council approved a contribution of £0.5m over three years in 2021, with £167,000 allocations for 2022/23 and 2023/24 subject to annual reviews by the relevant Committee at the end of year 1 and 2 against progress and relevant milestones in the Company’s Business Plan. EF
The comments from the Head of Finance Services were as follows: Provision for the £167,000 contribution to EMDevco was approved as part of this year’s budget process.
5. Legal Implications R
The Grant Agreement covering the Council’s financial contributions to EMDevco was completed on 10 September 2021 setting out the terms for payment. At the time the agreement was completed subsidy control (formerly state aid) advice had been sought which confirmed the proposed basis for the financial contributions complied with the subsidy control scheme.
Nil Cabinet 24 May 2022
APPENDIX
EM DevCo Ltd – Oversight Authority Update Report 2022/23
The Council is represented by the Leader of the Council of the Council in an Oversight Authority and the Chief Executive represents the Council as a Director on the skills- based Board. The Oversight Authority first met in April 2021 to agree the annual business plan and budget and the company was formally incorporated in May 2021. EM DevCo Ltd was formally established as a company limited by guarantee in April
E 2021. This follows the submission of a Business Case in March 2021 for a LLUDC to be enshrined in statute and established in the East Midlands.
It was agreed that Nottinghamshire County Council would host the company on behalf
C of the member authorities to provide support services. Independent legal and financial support have been procured to avoid conflicts of interest.
Progress on Corporate Deliverables
EN Since the incorporation of EM DevCo, a small team has been established including a Managing Director, Richard Carr. The following progress has been made during 2021/22:
Governance EM DevCo Ltd has been set up to mirror the structure of the Locally-Led Urban Development Corporation (LLUDC) model with an Oversight Authority (comprising ER elected members from the five local authorities), Board of Directors (comprising senior officer representatives from each of the five local authorities, five independent non- executive directors, and an independent chair) and an Executive Team. This structure was also developed with consideration of Public Interest Reports into local authority- owned companies in order to avoid facing the same issues seen in other recent high- profile cases.
The first formal meeting of the Oversight Authority took place in April 2021 where the EF
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EMDEVCO FIRST YEAR REPORT AND FUNDING REQUESTReport | 980 KB | DownloadRead as text |
PDF |
EMDEVCO LTD UPDATEReport | 225 KB | Download |
Follow Advisory Shareholder Sub Committee at Broxtowe and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | Work ProgrammeRESOLVED that the , with the addition of items regarding Open Spaces, Recreation and Leisure Connectivity Strategy, b... | Approved | Open |
| 15 Jun 2026 | Work ProgrammeRESOLVED that the be approved. | Approved | Open |
| 16 Mar 2026 | Work ProgrammeRESOLVED that the Work Programme be approved. | Approved | Open |
| 26 Jan 2026 | Work ProgrammeRESOLVED that the be approved. | Approved | Open |
| 8 Sep 2025 | Liberty leisure end of year accounts 2023/24RESOLVED to note the report. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.