RESOLVED that : 1. The Stapleford Town Deal’s Executive and Delivery Boards’ decisions to appoint VIA EM to design the whole town highway improvement scheme; provide detailed designs and construct the replacement car park on Derby Road be endorsed. 2. An exemption to the Council’s Contract Procedure Rules be approved to allow for The contract to be awarded without a full tender process being carried out. Reason The provision of the new car park is vital to facilitate the creation of the next stage of the Victoria Street Enterprise Hub and the commission of VIA EM would enable the construction of the car park once the design had attained planning permission. (Councillors T Hallam, R D MacRae and J W McGrath, having declared other registerable interests in the item left the room prior to discussion or voting thereon.)
Word for word from the decision Broxtowe published for this meeting.Source: democracy.broxtowe.gov.uk
Report Presented to Stapleford Town Deal Executive Board Meeting 23 September 2022
Proposed Procurement Route Background
The Executive Board is asked to consider and decide on the proposal to commission VIA EM to undertake all highways related works throughout the town centre, in order to submit the sixth and final business case (due early December).
VIA EM is the Highways Authority preferred partner and wholly owned arm’s length subsidiary of Nottinghamshire County Council (NCC), and provides engineering services across the East Midlands region. It is VIA who delivers highways services for NCC who have, in the past, proposed the need to use VIA for highways works, to ensure there is a coherence between highways all strands of highways policy and design. Faithful and Gould have recommended their use to the Executive Board in the Stapleford TIP following previous design iterations for the town in the TIP development and business case process undertaken thus far.
As the delivery agent for highways services for NCC, there is little value in tendering for this area of work when the winning tenderer would need to bring in the services of VIA EM and potentially increase costs to the Executive Board because of additional management and oversight that would be needed and charged not only by a contractor but also by VIA as expert contractor for NCC.
Teckal Rules would apply (see Appendix 1) allowing Contracting Authorities to look outside the application of procurement rules when co-operating between public sector bodies or using the “in-house exemption”.
Considering the above there is little value in tendering for this area of work when the winning tenderer would need to bring in the services of VIA EM and potentially increase costs to the Executive Board because of additional management and oversight that would be needed and charged not only by a contractor but also by VIA as expert partner/ contractor for NCC.
An alternative option is to use the Single Tender Waiver Justification (see Appendix 2), recently agreed as part of the updated Local Assurance Framework.
The Executive Board has recently approved an updated Local Assurance Framework within which is the Single Tender Waiver Justification.
1 Cabinet 20 December 2022
This Justification allows Board to waive formal tendering procedures in exceptional circumstances when those procedures would not be practicable or the estimated expenditure or income would not warrant formal tendering procedures, or where specialist expertise is required and is available from only one source, and must be approved by the Accountable Body’s Chief Executive or s.151 Officer.
The Town Deal was awarded a 5% advance of the total award to fund business case and project development activity. Not all of this funding has been defrayed and there is sufficient resource to commission VIA to use take the existing proposals for the town to manage traffic and secure the best possible harmonization between through route users, traffic visiting the shops and services, cyclists and pedestrians. The work will continue to develop proposals for street scene and pedestrian realm improvements. It will also develop a whole town approach and create some high level schemes capable of being delivered by the Towns Fund budget as well as give the Town opportunities and options to bid for other highways improvement funds when opportunities arise.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.