Broxtowe Borough Council
Cabinet, Tuesday 25 July 2023 at 6.00pm

HRA BUDGETS 2023/24

Approved Executive 1 paper

Cabinet approved this item on Tuesday 25 July 2023. Below is the council's own wording, with the papers it was decided on.

Item33.1

Resolved

RESOLVED that the proposed variations to the Capital Programme 2023/24, as presented, be approved. The additional capital cost of £1,205,900 to be being funded by prudential borrowing and the associated costs being factored into future years HRA budgets. Reason The Council, as a landlord, has many legal obligations it must satisfy to ensure the health, safety and welfare of its tenants and leaseholders. It must also adhere to the regulatory standards as set out by the Regulator, particularly the Home Standard.
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Cabinet

Purpose of report

To consider proposals for variations to the approved Capital Programme 2023/24 relating to the Housing Revenue Account (HRA) relating primarily to health and safety and compliance issues.

Recommendations

Cabinet is asked to RESOLVE that the proposed variations to the Capital Programme 2023/24, as presented, be approved. The additional capital cost of £1,205,900 to be being funded by prudential borrowing and the associated costs being factored into future years HRA budgets.

3. Detail

Each year the Council sets a three-year rolling Capital Programme for the General Fund and Housing Revenue Account (HRA). A review of progress made in quarter 1 of the 2023/24 HRA capital budgets has identified a number of important health and safety and compliance works that are not currently covered within the approved budgets as presented in appendix 1. The current HRA capital budgets are insufficient to meet the expenditure required to comply with health and safety compliance and standards. It is important to note that, in relation to electrical compliance, the Council is making faster progress than legislation, as the Council’s Electrical Compliance standards exceed statutory obligations as properties have electrical inspections every five years rather than the legislative requirement of 10 years.

The additional proposed compliance work includes essential fire door replacements (both HRA tenants and leaseholders), work arising from fire risk assessment, electrical works, asbestos remedial works and concrete surveys.

It is therefore proposed that an additional net capital budget of £1,205,900 be approved made to complete these essential works. In order to partly mitigate the increase in the capital budget, it is proposed that budget allocations from two existing schemes that are underspent is used. The net budget increase will be funded from increased prudential borrowing.

Financial implications

The comments of the Head of Finance Services were as follows:

The Capital Programme for 2023/24 was approved as part of the budget setting process which culminated in a recommendation from Cabinet on 7 February 2023 that was duly approved at full Council on 2 March 2023. Cabinet 25 July 2023

The net capital cost of the HRA element of the Capital Programme following the above review and re-profiling exercise is £1,205,900. This additional budget requirement would have to be funded by prudential borrowing. The additional borrowing costs of around £65,000 per annum would have to be factored into future years HRA budgets. The 30-Year HRA Business Plan outlining the HRA financial sustainability will be presented to Cabinet in September.

The comments from the Head of Legal Services were as follows:

The Council, as a landlord, has many legal obligations it must satisfy to ensure the health, safety and welfare of its tenants and leaseholders. It must also adhere to the regulatory standards as set out by the Regulator, particularly the Home Standard.

6. Human Resources Implications

There were no comments from the Human Resources Manager.

7. Union Comments

There were no Unison comments in relation to this report.

8. Climate Change Implications

The comments relating to climate change implications:

8. Data Protection Compliance Implications

This report does not contain any OFFICIAL Sensitive information and there are no Data Protection issues in relation to this report.

9. Equality Impact Assessment

As there is no change to policy an equality impact assessment is not required.

Background papers

Nil Cabinet 25 July 2023

APPENDIX CAPITAL PROGRAMME 2023/24 – HRA CAPITAL REPAIRS, IMPROVEMENTS AND COMPLIANCE BUDGETS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HRA BUDGETS 2023/24Report 221 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
MR
Councillor Milan Radulovic MBEChair, present
GM
Councillor Greg MarshallVice-Chair, present
SA
Councillor Susan A BagshawCommittee Member, apologies
RE
Councillor Ross Edward BofingerCommittee Member, present
CC
Councillor Chris CarrCommittee Member, present
HJ
Councillor Helen J FaccioCommittee Member, present
JW
Councillor John W McGrathCommittee Member, apologies
HE
Councillor Helen E SkinnerCommittee Member, present
PA
Councillor Pauline A SmithCommittee Member, present
VC
Councillor Vanessa C SmithCommittee Member, present

More from Broxtowe Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Reference - Overview and Scrutiny CommitteeRESOLVED that: 1. The introduction of an end date for the informal service trial currently underway with Lime as 31 D... Approved Open
3 Nov 2026 Communications And Engagement Strategy 2026-28RESOLVED that the Communications and Engagement Strategy be approved. Reason The strategy will support the Council’s ... Approved Open
3 Nov 2026 General Fund - Medium Term Financial Strategy 2026/27 to 2030/31 and Business Strategy 2027/28RESOLVED that the updated Medium Term Financial Strategy and the Business Strategy 2027/28 be approved. Reason To be ... Approved Open
3 Nov 2026 Grant Aid Requests from Parish/Town CouncilsRESOLVED that the grant aid requests from Eastwood Town Council for up to £2,458 for its Remembrance Sunday Event 202... Decided Open
3 Nov 2026 Grants to Voluntary and Community Organisations, Charitable Bodies and Individuals Involved in Sports, the Arts and Disability Matters 2026/27RESOLVED that: The Grant Aid requests be granted as follows: Broxtowe Women’s Project £13,000 Eastwood People’s Initi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies