APOLOGIES
To receive apologies and to be notified of the attendance of substitutes.
What the committee will consider, in order, with every paper attached to its item. TO FINALISE BROXTOWE'S YEAR 3 UK SHARED PROSPERITY FUND (UKSPF) FUNDING BETWEEN THEMES AND PRIORITIES FOR THE 2024-25 FINANCIAL YEAR is the main business; one item may be taken in private.
To receive apologies and to be notified of the attendance of substitutes.
Members are requested to declare the existence and nature of any disclosable pecuniary interest and/or other interest in any item on the agenda.
Cabinet is asked to confirm as a correct record the minutes of the meeting held on 9 January 2024.
The purpose of this report is to make Members aware of matters proposed for and undergoing scrutiny.
To recommend to Council the capital and revenue budget proposals together with the Capital Strategy, Prudential Indicators, Treasury Management Strategy, Investment Strategy and General Fund Medium Term Financial Strategy and to approve the Business Plans.
Decision: RESOLVED that the business plans for the Council’s corporate priorities and support service functions, subject to amendment as a result of any budget decisions still to be taken by Council recommended by Cabinet, be approved. RECOMMENDED to Council that: 1. The Housing Revenue Account budget as submitted be approved (appendix 2). 2. The General Fund revenue budgets as submitted be approved (appendix 3). 3. The capital submissions and priorities within them be approved and that the Deputy Chief... Decision page
To consider requests for grant aid in accordance with the provisions of the Council’s Grant Aid Policy.
Decision: RESOLVED that the grant aid requests be approved accordingly : Eastwood People’s Initiative £2,500 5 th Stapleford Scout Group £4,500 2 nd Beeston Sea Scouts £2,150 Age Concern Eastwood £9,000 2 nd Kimberley Scout Group £7,000 Stapleford Community Association £3,000 Broxtowe Women’s Project £8,000 Phoenix Community Association £7,500 D H Lawrence Music Festival £2,500 Young Individual Boxing Competitor £1,000 (Having declared an other-registerable interest in the item, Councillor M Radulovic... Decision page
To enable Cabinet to see a copy of the Pay Policy for 2024/25 before it goes to full Council for approval in March 2024.
To outline potential options for producing the Council’s residents’ newsletter in the future.
Decision: RESOLVED that Option 2, as included in the report, be approved. Reason Option 2 utilises the financial and Officer resource of producing a newsletter into a wider range of targeted engagement activities. Options considered and rejected: Option 1: Continue with existing arrangement to produce a resident’s newsletter which is promoted online. Reduce distribute of printed copies to 2,000 based on take up during 2023/24. Decision page
The purpose of this report is to allocate the Year 3 programme that has been the subject of consultation at the Members Advisory Panel last November which has been guided by the Borough’s Investment Plan and signed off by Department for Levelling Up, Housing and Communities (DHLUC) in December 2022. The report provides Cabinet with information to enable alignment of the work with corporate priorities and...
Decision: RESOLVED that the funding profile for the Year 3 UKSPF allocations as described in section 3 and detailed in appendix 2 of the report, be approved. Reason The parameters for decision and change were based on the Borough’s approved Investment Plan and the limited flexibilities granted to the Council in managing the programme . Decision page
The purpose of this report is to obtain approval for the Chetwynd : The Toton and Chilwell Neighbourhood Plan to be modified as recommended by the Independent Examiner and to proceed to referendum based upon the current Neighbourhood Plan Area. It is also to confirm that the Council is of the view that, once modified as per the Independent Examiner’s recommendations, the Chetwynd : The Toton and Chilwell...
Decision: RESOLVED that: 1. The Chetwynd : The Toton and Chilwell Neighbourhood Plan should be modified as proposed by the Independent Examiner. 2. Once modified as proposed by the Independent Examiner, it is considered the Neighbourhood Plan will meet the Basic Conditions and other legislative requirements. 3. The Chetwynd : The Toton and Chilwell Neighbourhood Plan should proceed to a referendum, with the extent of the area eligible to vote to be based upon the Chetwynd : The Toton and Chilwell... Decision page
To seek Cabinet approval for the procurement and subsequent appointment of a specialist civil engineering firm to undertake rock face stabilisation works to the area located at Leamington Road, Chillwell, also known as Chillwell quarry following a landslide due to adverse weather conditions.
Decision: RESOLVED that that the procurement and subsequent appointment of a civil engineering firm and employer’s agents to complete the scheme of works to undertake rock face stabilisation works at Chilwell Quarry be approved. The scheme at a cost of up to £1,000,000 will be added to the Capital Programme in 2023/24 and funded by prudential borrowing. Reason To avoid any legal claims, it is imperative this work is carried out to avoid any legal claims made against the Council as land owner, the... Decision page
To seek approval to construct five new homes on land adjacent to 51 Ilkeston Road, Bramcote NG9 3JP, as specified by Planning consent 21/00038/REG3, and to refurbish Farm Cottage at the site to bring it back into use for Social Rent as one home.
Decision: RESOLVED that the production of six dwellings at the Farm Cottage site, as detailed in the report, be approved. Reason This was an opportunity to provide homes which would accommodate different people on the Council’s waiting list. Decision page
Cabinet is asked to approve its Work Programme, including potential key decisions that will help to achieve the Council’s key priorities and associated objectives.
Decision: RESOLVED that the Work Programme be approved. Decision page
Cabinet is asked to RESOLVE that, under Section 100A of the Local Government Act, 1972, the public and press be excluded from the meeting for the following items of business on the grounds that they involve the likely disclosure of exempt information as defined in paragraphs 1, 2, 3 and 4 of Schedule 12A of the Act.
Decision: RESOLVED that: 1. The identified supplier is commissioned to develop a detailed design for the new Bramcote Leisure Centre (RIBA 4) and, on behalf of the Council, submits planning application for the development of the new Leisure Centre. 2. A capital budget of £800,000 to fund the RIBA 4 design, planning fees, associated survey costs and project management be approved and added to the Capital Programme 2023/24 to funded from General Fund capital receipts. 3. A Bramcote Leisure Centre Board is...
Decision: RESOLVED that the Council meets the estimated Employee Matters costs as detailed within the report, with the total cost being funded directly from General Fund Reserve balances. Reason This will allow for legislative and policy requirements to be met. (Having declared anon-registerable interest in the item, Councillor J W McGrath left the meeting before voting thereon.)
Decision: RESOLVED that: 1. The revised structure for the Economic Development and Regeneration Team as illustrated in the organogram, appendix 1 of the report, be approved. 2. The creation of the Town Centres & Contracts Manager post be approved. 3. The change of title of the Section Manager from Economic Development and Regeneration Manager to Economic Development, Regeneration and UKSPF Programme Manager be approved. Reason This will assist with all of the Council’s policies.
Item 122.1 is where most of this meeting's papers sit: 4 papers, about 1.8 MB.
The purpose of this report is to allocate the Year 3 programme that has been the subject of consultation at the Members Advisory Panel last November which has been guided by the Borough’s Investment Plan and signed off by Department for Levelling Up, Housing and Communities (DHLUC) in December 2022. The report provides Cabinet with information to enable alignment of the work with corporate priorities and...
This committee has dealt with the subject before.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 26 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 9 January 2024. 3 of its items lead into this meeting; 9 items are new. Point at any item to follow a thread. Procedural items are left out.
BUDGET CONSULTATION 2024/25, TREASURY MANAGEMENT AND PRUDENTIAL INDICATORS 2023/24 MID-YEAR REPORT, CHANGE DELIVERY MANAGER TO SUPPORT THE IMPLEMENTATION OF THE SERVICE IMPROVEMENT PLAN FOR ASSET MANAGEMENT REPAIRS AND COMPLIANCE, HOUSING DELIVERY TRAINEE POST TO SUPPORT THE HOUSING DELIVERY FUNCTION and 5 more do not return this time.
See the 9 January meetingEvery Cabinet meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Broxtowe, Cabinet
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Cabinet, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.