Broxtowe Borough Council
Cabinet, Tuesday 16 July 2024 at 6.00pm

Brinsley Headstocks

Approved Executive 2 papers

Cabinet approved this item on Tuesday 16 July 2024. Below is the council's own wording, with the papers it was decided on.

Item18.2

Resolved

RESOLVED unanimously that option 1, a direct replacement with an oak framed structure, funded from sources including section 106 contingencies, be approved. Reason The memorial would provide a fitting tribute to those who worked and gave their lives at the site. Options considered and rejected 2. Direct replacement with a steel structure. 3. Ground level interactive art piece.
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Cabinet

Recommendation

Cabinet is asked to CONSIDER the options provided in the Appendix and RESOLVE accordingly.

3. Detail

Brinsley Headstocks operated at Brinsley Colliery a former coal mine, between 1872 and 1934. The twin Headstocks and nearby disused mineral railway track, were all that remained of the once extensive coal mining works, acting as a visual link to the heritage of the site.

In January 2023, a condition report and safety inspection was undertaken on the Headstocks. It identified that the Headstocks were no longer considered capable of safely carrying the load from the winding wheels without intervention. In late November 2023, further deterioration of the wooden structure was identified and concerns were raised by suitably qualified employees, that the structure was at risk of imminent collapse. In the interest of public safety, the Headstocks were dismantled in December 2023.

A report was presented to Cabinet on 12 March 2024, requesting approval for a public consultation to be undertaken regarding potential replacement options for the Headstocks. The proposed questions were approved, and the consultation was undertaken from the 7 to the 31 May 2024. The consultation was conducted using an online platform and paper questionnaires. The latter was distributed across various locations in the Borough.

The options presented for replacement were as follows:

1. Direct replacement with an oak framed structure. 2. Direct replacement with a steel structure. 3. Ground level interactive art piece. 4. Other (detail to be provided).

Findings from the public consultation and feedback captured from the Friends of Brinsley Headstocks focus group are presented in the Appendix. Cabinet 16 July 2024

4. Key Decision

This report will be a key decision as defined under Regulation 8 of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012. As one of the options for approval could result in the Council incurring capital or revenue expenditure of £250,000 or more.

5. Updates from Scrutiny

Not applicable.

Financial implications

The comments from the Head of Finance Services were as follows:

Members should note that there is currently no budgetary provision for the refurbishment of Brinsley Headstocks. The capital cost of the most popular replacement choice from the consultation is estimated at £220,000. Any capital investment would have to be funded from prudential borrowing unless alternative capital grant funding and/or other third party contributions could be sourced. It has been identified that up to £145,000 of capital contributions may become available. In addition to the cost of borrowing (principal and interest), there would be ongoing revenue budget implications in terms of maintenance and repairs. Further details are provided in the appendix.

The comments from the Monitoring Officer / Head of Legal Services were as follows:

There are no direct legal implications that arise from this report.

8. Human Resources Implications

Not applicable.

7. Union Comments

Not applicable.

8. Climate Change Implications

When considering the climate change implications of replacing the Headstocks, it is important to evaluate the environmental impact of various materials. Opting for a wooden replacement could offer potential ecological benefits due to the woods renewable nature and lower carbon footprint. Responsible sourcing of the wood would be crucial. It should be noted that whilst a wooden replacement would be an environmentally sustainable option, it would require an enhanced and extensive programme of maintenance Cabinet 16 July 2024

9. Data Protection Compliance Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20240628140901_000656_0001372_AppendixBrinsleyHeadstocksJuly2024Appendix 358 KB Download
PDF
Brinsley HeadstocksReport 15 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
MR
Councillor Milan Radulovic MBEChair, present
GM
Councillor Greg MarshallVice-Chair, present
PJ
Councillor Peter J BalesCommittee Member, present
GB
Councillor Gabrielle BunnCommittee Member, present
CC
Councillor Chris CarrCommittee Member, present
TA
Councillor Teresa A CullenCommittee Member, present
HJ
Councillor Helen J FaccioCommittee Member, present
JW
Councillor John W McGrathCommittee Member, present
HE
Councillor Helen E SkinnerCommittee Member, present
VC
Councillor Vanessa C SmithCommittee Member, present

On this subject at Broxtowe

Search all
  1. Brinsley HeadstocksThis decision
  2. Replacement options for brinsley headstocksApproved

More from Broxtowe Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Reference - Overview and Scrutiny CommitteeRESOLVED that: 1. The introduction of an end date for the informal service trial currently underway with Lime as 31 D... Approved Open
3 Nov 2026 Communications And Engagement Strategy 2026-28RESOLVED that the Communications and Engagement Strategy be approved. Reason The strategy will support the Council’s ... Approved Open
3 Nov 2026 General Fund - Medium Term Financial Strategy 2026/27 to 2030/31 and Business Strategy 2027/28RESOLVED that the updated Medium Term Financial Strategy and the Business Strategy 2027/28 be approved. Reason To be ... Approved Open
3 Nov 2026 Grant Aid Requests from Parish/Town CouncilsRESOLVED that the grant aid requests from Eastwood Town Council for up to £2,458 for its Remembrance Sunday Event 202... Decided Open
3 Nov 2026 Grants to Voluntary and Community Organisations, Charitable Bodies and Individuals Involved in Sports, the Arts and Disability Matters 2026/27RESOLVED that: The Grant Aid requests be granted as follows: Broxtowe Women’s Project £13,000 Eastwood People’s Initi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies