CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Broxtowe Borough Council
Cabinet, Tuesday 3 November 2026 at 6.00pm

Economic Development and Regeneration Update

Approved Executive 2 papers

AI summaryBroxtowe Cabinet approved a Beeston LED screen, Bramcote Hills Park phase 1 visitor facilities and parking talks. [D] Victoria Street car park will remain public if alternative parking is secured, with a contingent liability of up to 50% of the costs from 2027/28. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedLED screen, visitor facilities, parking agreements and public parking. [D]
Moneyup to 50% [D]2027/28 budget amount set aside if project contingency is exhausted. [D] [P47]
What happens nextProgress parking agreements [D]Lease and licence discussions may proceed in principle. [D]
Who it affectsBeeston, Bramcote and Stapleford [D]Screen users, park visitors, businesses and drivers. [P23] [P42]

What was decided

Cabinet approved the LED screen's position on the roof of the former Argos building in The Square, Beeston, and a framework for its uses. [D] The framework covers public information, council work, events, partner messaging, town centre promotion and occasional commercial use. [P24] [P25] Report P24, P25

Cabinet approved the concept for rapid delivery of phase 1 visitor facilities at Bramcote Hills Park, potentially through Stapleford Town Deal funding. [D] The first phase could provide toilets, covered space for at least four vending units, an undercover picnic area and temporary exhibition space. [P34] Report P34

Cabinet gave in principle permission to progress lease and licence agreements with the Stapleford and Bramcote Conservative Club for alternative parking at the Pencil Works Enterprise Hub. [D] Subject to this or a satisfactory alternative, it retained Victoria Street Car Park for public use rather than privately managed parking, and set a contingent liability of up to 50% of the costs from the 2027/28 budget. [D]

Why

The screen has planning permission and is the final capital project following work on the Nottinghamshire Canal. [P23] Its main uses are public information, council work and existing events, with additional opportunities subject to regulation and licences. [P23] Report P23

The visitor facility was proposed to support families and all Stapleford residents and to create opportunities for existing and new small businesses. [P33] [P34] A phased approach can fit the available Town Deal timeline, while service delivery is the biggest programme risk and the Council aims to stay revenue neutral. [P33] [P34] Report P33, P34

The club parking arrangement is the most promising way to provide alternative parking while retaining public parking availability for the Hub. [P42] The public car park works have costs that are not fully budgeted, and it is not yet possible to judge whether project contingency can meet them. [P44] [P47] Report P42, P44, P47

What happens next

A formal use policy for the screen could be developed through the Policy Overview Working Group, with first use expected over the Christmas period. [P26] Report P26

The next step is to deliver phase 1 visitor facilities within the Town Deal terms and conditions, with service delivery identified as a key risk. [P34] [P35] A second phase could expand the covered area and add a catering kitchen. [P34] Report P34, P35

Progress the lease and licence discussions, ensuring best value, market value supported by an independent valuation and due diligence on title. [P57] [P58] [P59] A suitable development budget is to be included in the capital programme, with the contingent liability used if project contingency is exhausted. [P47] [D] Report P47, P57, P58, P59

The money

  • up to 50% of the costs Contingent liability for bringing back public car parking from the 2027/28 budget.
  • 78,650 Total cost shown for the public parking works. Report P45
  • £36,650 Additional costs shown for the revised public parking package. Report P45
  • £31,650 STD's listed payment under the revised package. Report P45
  • £26,000 Proposed Broxtowe contribution to the public parking package. Report P45
  • £70,000 Possible total package if installation is delayed until post completion. Report P46
  • around £23,000 Amount originally specified for the parking area. Report P47
  • £320,000 Additional EMCCA funding for the Hub's Makers Space element. Report P42

Options considered

  • Chosen: Use the Stapleford and Bramcote Conservative Club for alternative parking. This was the most promising arrangement for staff and tenant parking while retaining public parking availability. Report P42
  • Chosen: Retain Victoria Street Car Park for public use. Public parking can remain available once alternative parking or another satisfactory solution is secured. Report P43
  • Rejected: Make Victoria Street Car Park a privately managed car park for the Pencil Works Enterprise Hub. The Council's objective was to retain public parking availability within the site. Report P42, P43
  • Chosen: Deliver Bramcote Hills Park visitor facilities in phases. Support was given if the project could be delivered within the available time, with phasing creating opportunities for businesses. Report P33, P34

Implications

  • Financial: The 2026/27 revenue budgets and capital programme include provision for the significant Kimberley and Stapleford regeneration projects, but not for additional Victoria Street public car park costs. [P53] [P54] Any uplift in 2026/27, or a new capital development for 2027/28, would be funded from prudential borrowing, with the revenue cost of borrowing offset by public car park income. [P54] Report P53, P54
  • Financial: It is not possible yet to judge whether the general project contingency can meet the revised scope. [P47] Up to 50% of the costs is to be set aside as a contingent liability for 2027/28 and used if project contingency is exhausted. [D] [P47] Report P47
  • Legal: The Council may enter into a lease or licence under s1 of the Localism Act 2011 and s111 of the Local Government Act 1972, but must ensure best value. [P57] Any third party arrangement must have consideration or rent aligned with market value, supported by an independent surveyor's valuation. [P58] Report P57, P58
  • Legal: The works would ensure compliance with applicable health and safety legislation and protect employees and the public. [P56] Legal Services will carry out due diligence on the third party's title, including restrictive covenants and third party rights. [P59] Report P56, P59
  • Equalities: An equality impact assessment is included because this is a policy change or new policy. [P69] Report P69
  • Climate: No climate change implications are anticipated from the activities in the report. [P65] Report P65
  • Risk: Delivery of services is the biggest risk to the Bramcote project programme, and work on it has started. [P34] Report P34
  • Staffing: No human resources implications are identified. [P61] Report P61

Who and where

  • Beeston residents and visitors to The Square Report P23, P24
  • Independent traders Report P25
  • Stapleford residents Report P33
  • Existing and new small businesses Report P34
  • Bramcote Hills Park visitors Report P34
  • Pencil Works Enterprise Hub tenants and staff Report P42
  • Victoria Street public parking users Report P43
  • Stapleford and Bramcote Conservative Club Report P42

Timeline

  • November 2026: Practical completion of the Pencil Works Enterprise Hub is anticipated. Report P42
  • 2027/28: The contingent liability for public car parking is to be set from the budget.
  • 3 November 2026: Cabinet approved the economic development and regeneration decisions. Report P8
  • over the Christmas period: First use of the LED screen is expected. Report P26
  • March 2028 at the latest: The Stapleford Town Deal and Kimberley Means Business schemes must be completed. Report P28
  • from 28 September through to end of October: Public engagement is taking place for Walter Parker VC Memorial Square. Report P36
  • December: Kimberley Hub is due to reach build completion. Report P31
  • July: The Bennerley Viaduct Visitor Centre opened. Report P29

Plain English for the jargon

  • EMCCA: East Midlands Combined Counties Authority, whose Investment Board released funding. [P10]
  • HSRA: High Street Rental Auctions, a process used to address long term vacancies. [P13] [P14]
  • KMB: Kimberley Means Business, one of the two LRF programmes. [P28]
  • UKSPF: The programme that funded projects for businesses, communities, residents and town centres, with more than £708,000 directly invested. [P19]
  • LRF: The programme framework used by the Stapleford Town Deal and Kimberley Means Business. [P28]
  • LED screen: The screen for public information, council work, events and possible commercial use. [P23] [P24] [P25]
  • Makers Space: The Hub element providing specialist facilities for creative industries, start-up businesses and circular economy initiatives. [P42]
  • Contingent liability: An amount set aside for costs if project contingency is exhausted. [D] [P47]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item65.1

Resolved

RESOLVED that: 1. The positioning of an LED screen in The Square, Beeston on the roof of the former Argos building and the framework for conditions of use in be approved. 2. The concept for the rapid delivery of phase 1 of the Bramcote Hills Park visitor facilities, which could be delivered through Stapleford Town Deal funding, be approved. 3. To give in principle permission for the Council, as the accountable body for the Stapleford Town Deal, to progress lease and licence agreements with the Stapleford and Bramcote Conservative Club for the provision of an alternative car park for the Pencil Works Enterprise Hub. 4. Subject to the above point, or a satisfactory alternative solution being achieved, to approve that the Victoria Street, Car Park be retained as a public car park instead of becoming a privately managed car park as part of the Pencil Works Enterprise Hub. 5. A contingent liability for up to 50% of the costs of re-introducing public car parking be set from the 2027/28 budget . Reason The Economic Development and Regeneration service is in a period of transition. This has seen the continued build out of externally funded capital projects, the conclusion of the last elements of UKSPF and the re-introduction of some core ‘business as usual’ work.
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Cabinet

Recommendation

Cabinet is asked to note the update on Economic Development and Regeneration work, including the final six months of the UKSPF programme, and to RESOLVE the following accordingly:

1. The positioning of an LED screen in The Square, Beeston on the roof of the former Argos building and the framework for conditions of use in be approved.

2. The concept for the rapid delivery of phase 1 of the Bramcote Hills Park visitor facilities, which could be delivered through Stapleford Town Deal funding, be approved.

3. To give in principle permission for the Council, as the accountable body for the Stapleford Town Deal, to progress lease and licence agreements with the Stapleford and Bramcote Conservative Club for the provision of an alternative car park for the Pencil Works Enterprise Hub.

4. Subject to the above point, or a satisfactory alternative solution being achieved, to approve that the Victoria Street, Car Park be retained as a public car park instead of becoming a privately managed car park as part of the Pencil Works Enterprise Hub.

5. A contingent liability for up to 50% of the costs of re-introducing public car parking be set from the 2027/28 budget.

3. Detail

The Economic Development and Regeneration service is in a period of transition. This has seen the continued build out of externally funded capital projects, the conclusion of the last elements of UKSPF and the re-introduction of some core ‘business as usual’ work. Cabinet 3 November 2026

Core Work, including UKSPF

Further contributions have been made in response to consultations to release funding via the East Midlands Combined Counties Authority (EMCCA) Investment Board. This includes actions such as business support, the visitor economy and skills interventions.

The objective is to influence countywide funding initiatives and strategies that will support local businesses and residents. Some funding through LGF has been released to both the constituent councils and the East Midlands Chamber of Commerce, the latter as the result of a successful business support tender.

The team works closely monitoring industrial commercial and retail vacancies. In addition to tracking for performance management purposes, this information is used to help support businesses looking to invest or expand in Broxtowe.

Vacancies are also an important feature of the High Street Rental Auctions (HSRA) where Broxtowe has become the first council in the country to complete a refurbishment project and advertise a property at auction. With the two bidders both being out of scope, the auction will be re-run and preparations are being made. The restoration of the Old Rock/Chequers Inn, to a suitable letting standard will be completed during October.

The Council has used the HSRA process to take a proactive approach to understanding and addressing long-term vacancies, engaging with more than 17 property owners in Stapleford and 10 in Eastwood.

The Government has recently released approximately £10 million for this initiative, and the Council has assisted with the national consultation to inform the next steps. At least eight other councils have contacted the team for advice.

Eastwood remains a core area of work. CEDARS continues to steadily grow and from a standing start last summer, regular partner slots operate four days a week with 545 people receiving services by the end of Q2. The Ministry of Justice, the DWP and, most recently, the CAB are in the process of taking further space which should increase outputs further. Additional and occasional one day health screening events also take place from CEDARS.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
and 2Appendix 1 693 KB Download
PDF
Economic Development and Regeneration UpdateReport 120 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 10 attended
MR
Councillor Milan Radulovic MBEChair, expected
GM
Councillor Greg MarshallVice-Chair, expected
GB
Councillor Gabrielle BunnCommittee Member, expected
TA
Councillor Teresa A CullenCommittee Member, expected
RD
Councillor Richard D MacRaeCommittee Member, expected
TJ
Councillor Tyler J MarshCommittee Member, expected
JW
Councillor John W McGrathCommittee Member, expected
SP
Councillor Sue PatersonCommittee Member, expected
VC
Councillor Vanessa C SmithCommittee Member, expected
EW
Councillor Elizabeth WilliamsonCommittee Member, expected

On this subject at Broxtowe

Search all
  1. Economic Development and Regeneration UpdateThis decision
  2. Formation of Broxtowe Local Enterprise Agency to Further the Aims of the Economic Development and Regeneration StrategyApproved
  3. Economic Development & Regeneration StrategyApproved

More from Broxtowe Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Reference - Overview and Scrutiny CommitteeRESOLVED that: 1. The introduction of an end date for the informal service trial currently underway with Lime as 31 D... Approved Open
3 Nov 2026 Communications And Engagement Strategy 2026-28RESOLVED that the Communications and Engagement Strategy be approved. Reason The strategy will support the Council’s ... Approved Open
3 Nov 2026 General Fund - Medium Term Financial Strategy 2026/27 to 2030/31 and Business Strategy 2027/28RESOLVED that the updated Medium Term Financial Strategy and the Business Strategy 2027/28 be approved. Reason To be ... Approved Open
3 Nov 2026 Grant Aid Requests from Parish/Town CouncilsRESOLVED that the grant aid requests from Eastwood Town Council for up to £2,458 for its Remembrance Sunday Event 202... Decided Open
3 Nov 2026 Grants to Voluntary and Community Organisations, Charitable Bodies and Individuals Involved in Sports, the Arts and Disability Matters 2026/27RESOLVED that: The Grant Aid requests be granted as follows: Broxtowe Women’s Project £13,000 Eastwood People’s Initi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies