Broxtowe Borough Council
Governance, Audit and Standards Committee, Monday 23 November 2026 at 6.00pm

Regulator Update – Service Improvement Plan

Decided Finance 3 papers

AI summaryBroxtowe Borough Council will bring Root Cause Analysis next steps to the Governance, Audit and Standards Committee, compare future progress and increase meeting frequency in 2027/28.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedProgress will be compared, with more meetings in 2027/28.
MoneyNot stated
What happens nextBring analysis steps to committeeUpdates will track analysis steps and the Service Improvement Plan.
Who it affectsHousing and asset managementService delivery and meeting of regulator requirements.

What was decided

The Committee will consider the recommended next steps from the Root Cause Analysis report. Future updates will compare progress against those steps and the Service Improvement Plan.

The meeting frequency of the Governance, Audit and Standards Committee will increase in the proposed 2027/28 programme, reflecting the amount of business expected in future.

The Council continues to implement actions within the refreshed Housing and Asset Management Service Improvement Plan following the Regulator for Social Housing inspection in October 2025. Report P4

Why

Regulator for Social Housing feedback said that a Root Cause Analysis was required to identify why the Council received a C3 judgement. Report P5

The Committee was asked to consider whether actions within the Service Improvement Plan were designed to resolve the key themes identified by the Root Cause Analysis. Report P2

Not following the Regulator's recommendations will have consequences. They should be considered and implemented as soon as practicably possible. Report P11

What happens next

Bring the recommended Root Cause Analysis next steps before the Committee for consideration.

Provide future updates comparing progress against those next steps and the Service Improvement Plan.

Increase the Committee's meeting frequency in the proposed 2027/28 programme.

Options considered

  • Chosen: Bring the recommended Root Cause Analysis next steps before the Committee for consideration. Future updates will compare progress against those steps and the Service Improvement Plan.
  • Chosen: Increase Governance, Audit and Standards Committee meeting frequency in the proposed 2027/28 programme. It will reflect the amount of business to be considered in future.

Implications

  • Legal: Not following the Regulator's recommendations will have consequences. They should be considered and implemented as soon as practicably possible. Report P11
  • Risk: The Council received a C3 judgement. A Root Cause Analysis was required to identify why. Report P5
  • Other: Future scrutiny will track progress against the Root Cause Analysis next steps and the Service Improvement Plan.
  • Legal: The Social Housing (Regulation) Act of 2023 sets out the legislative powers of the Regulator of Social Housing. Section 193 of the Housing and Regeneration Act 2008 introduced the inspection programme. Report P10
  • Equalities: An equality impact assessment is included in the appendix because this is a change to policy or a new policy. Report P21
  • Climate: Climate change implications are contained within the report. Report P17
  • Legal: The report contains no OFFICIAL(SENSITIVE) information and there are no data protection issues. Report P19
  • Staffing: No human resource implications were identified. Report P12, P13

Who and where

  • Governance, Audit and Standards Committee
  • Housing and Asset Management Service Report P4
  • The Council's landlord functions Report P11
  • Broxtowe Borough Council Report P4, P11

Timeline

  • October 2025: The Regulator for Social Housing inspected the Council. Report P4
  • 23 November 2026: The Committee considered the Root Cause Analysis and Service Improvement Plan. Report P8, P2, P5
  • as soon as practicably possible: The Regulator's recommendations should be considered and implemented. Report P11
  • 2027/28: Committee meeting frequency is to increase in the proposed programme of meetings.

Plain English for the jargon

  • Regulator for Social Housing (RSH): The organisation that inspected the Council and provided feedback on the C3 judgement.
  • C3 judgement: The Council's regulatory judgement, for which a Root Cause Analysis was required.
  • Root Cause Analysis: An exercise to identify why the Council received the C3 judgement.
  • Service Improvement Plan: The refreshed Housing and Asset Management plan aligned with the analysis themes.
  • Regulatory judgement: A formal process in assessing the Council's landlord functions.
  • Governance, Audit and Standards Committee: The committee considering analysis next steps and future progress updates.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item36

Resolved

RESOLVED that: 1. The recommended next steps from the Root Cause Analysis report be brought to the Committee for consideration, with future updates comparing progress against those next steps and the Service Improvement Plan; and 2. The frequency of meetings for the Governance, Audit and Standards Committee to be increased in the proposed programme of meetings 2027/28 to reflect the amount of business to be considered by the committee in future.
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Governance, Audit and Standards Committee

Recommendation

The Committee is asked to:

1. NOTE Appendix 1. 2. CONSIDER the information contained within Appendix 2 and RESOLVE accordingly regarding whether the actions within the Service Improvement Plan are designed to resolve the key themes identified in the Root Cause Analysis report.

3. Detail

The Council continues to implement actions within the refreshed Housing and Asset Management Service Improvement Plan following the inspection from the Regulator for Social Housing (RSH) in October 2025. Progress continues to be made to meet the Regulator requirements and improve service delivery.

Feedback from the RSH suggested that a Root Cause Analysis exercise is required to identify why the Council received a C3 judgement. As such, it has been requested that this Committee reviews and scrutinises the Service Improvement Plan aligned to the key themes of the recently completed analysis.

The following are attached to this report:

• Appendix 1: The Service Improvement Plan that has been refreshed following the Root Cause Analysis exercise • Appendix 2: The Root Cause Analysis report

Financial implications

The comments from the Assistant Director Finance Services were as follows: Governance, Audit and Standards Committee 23 November 2026

The comments from the Head of Legal Services were as follows:

The legislative powers of the Regulator of Social Housing are set out in the Social Housing (Regulation) Act of 2023 however Section193 of the Housing and Regeneration Act 2008 introduced the inspection programme which states that the ‘regulator may set Standards for registered providers as to the nature, extent, safety, energy efficiency and quality of accommodation, facilities or services provided by them in connection with social housing’.

The regulatory judgement is a formal process as part of the assessment on the Council’s Landlord functions. The report sets out the details around the judgement and actions required. Failure to adhere to the recommendations of the Regulator will have consequences. It is imperative that the Regulators recommendations are considered and implemented as soon as practicably possible.

6. Human Resources Implications

N/A

7. Union Comments

N/A

8. Climate Change Implications

The climate change implications are contained within the report.

9. Data Protection Compliance Implications

This report does not contain any OFFICIAL(SENSITIVE) information and there are no Data Protection issues in relation to this report.

10. Equality Impact Assessment

As this is a change to policy / a new policy an equality impact assessment is included in the appendix to this report.

Background papers

Nil.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
10.1 RSH Appendix 1 Service Improvement Plan: October 2026 GASAppendix 186 KB Download
PDF
10.2 RSH Appendix 2Appendix 342 KB Download
PDF
Regulator Update: Service Improvement PlanReport 75 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 16 attended
SJ
Councillor Stephen J CarrChair, expected
CC
Councillor Chris CarrVice-Chair, expected
MB
Councillor Michael BrownCommittee Member, expected
RB
Councillor Robert BullockCommittee Member, expected
AC
Councillor Andy CooperCommittee Member, expected
JC
Councillor Judith CouchCommittee Member, expected
SD
Councillor Shaun DannheimerCommittee Member, expected
KA
Councillor Katherine A HarlowCommittee Member, expected
SP
Councillor Stephen P JeremiahCommittee Member, expected
AK
Councillor Andrew KingdonCommittee Member, expected
JM
Councillor Jill M OwenCommittee Member, expected
SW
Councillor Sarah WebbCommittee Member, expected

All 16 on the meeting page

More from Broxtowe Governance, Audit and Standards Committee

All decisions
MeetingDecisionOutcome
23 Nov 2026 Annual Audit Letter – External Auditors Report on the Statement of Account 2025/26RESOLVED that: 1. The updated Statement of Accounts 2025/26 and draft letter of representation as circulated be appro... Approved Open
23 Nov 2026 Review of Strategic Risk RegisterRESOLVED that the amendments to the Strategic Risk Register and the actions to mitigate risks as set out be approved. Approved Open
23 Nov 2026 Work ProgrammeRESOLVED that the Work Programme be approved. Approved Open
21 Sep 2026 Review of Strategic Risk RegisterRESOLVED that the amendments to the Strategic Risk Register and the actions to mitigate risks as set out be approved. Approved Open
21 Sep 2026 Regulator UpdateRESOLVED that: (1) the Committee's understanding and scrutiny of the Service Improvement Plan be strengthened, includ... Decided Open