Resolved
That the Audit Committee re-affirms its support for the Council’s approach to Risk Management. 2. That the progress made throughout 2015/2016 and the actions planned for 2016/2017 be noted.
Audit Committee noted this item on Tuesday 19 July 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Audit Committee re-affirms its support for the Council’s approach to Risk Management. 2. That the progress made throughout 2015/2016 and the actions planned for 2016/2017 be noted.
REPORT FOR DECISION Agenda Item
MEETINGS: Audit Committee
DATE: 19 July 2016 - Audit Committee
SUBJECT: Risk Management Annual Report 2015/16
REPORT FROM: Councillor Jane Lewis; Deputy Leader of the Council and Cabinet Member for Finance & Human Resources
CONTACT OFFICER: David Hipkiss, Risk & Governance Manager
TYPE OF DECISION: COUNCIL - KEY DECISION
FREEDOM OF This paper is within the public domain INFORMATION/STATUS:
SUMMARY: The Risk Management Annual Report provides Members with details of risk management activity that has taken place over the past 12 months. It outlines risk management policies and practices now in place and the key issues that will be addressed during the coming financial year.
OPTIONS & Members are requested to re-affirm their support for the RECOMMENDED OPTION Council’s approach to Risk Management, and note progress made throughout 2015/16 and actions planned for 2016/17.
IMPLICATIONS:
Corporate Aims/Policy Do the proposals accord with the Policy Framework: Framework? Yes
Financial Implications and Risk See Executive Director of Resources & Considerations: Regulation comment below
Statement by Executive Director There are no direct resource implications of Resources: arising from this report.
1 Risk management is an integral part of the Council’s approach to Corporate Governance and service and financial planning and it is essential that robust risk management practices are put in place to safeguard the Council’s assets and its reputation.
Corporate, departmental and operational risk assessments have been undertaken and key elements of the resultant Management Action Plans are incorporated into Departmental Service Plans.
Equality/Diversity implications: No
Considered by Monitoring Officer: Yes (Governance Panel)
Are there any legal implications? No
There are no direct HR, IT or property Staffing/ICT/Property: implications arising from this report.
Wards Affected: All
Scrutiny Interest: Overview & Scrutiny
TRACKING/PROCESS DIRECTOR:
Chief Executive/ Cabinet Ward Members Partners Strategic Leadership Member/Chair Team 20 June 2016
Overview & Scrutiny Committee Cabinet Council Audit 19 July 2016
2 1.0 BACKGROUND AND RISK PRIORITIES DURING 2015/16
1.1The Council’s Risk Management Policy and Strategy is reviewed annually.
1.2The Council has continued to experience reduced funding, and increased demand for services, and responded to this for 2015/16 through its “Vision, Purpose & Values” which were recognised in the 2015/16 budget.
1.3A number of challenges were presented to the Council during 2015/16 where effective business continuity and emergency response planning played a significant role in preventing disruption to the public and service continuity.
1.4The floods experienced across the Borough on Boxing Day 2016 highlight the need for services to be resilient and responsive. Despite the floods having a devastating impact for residents and businesses, Council services responded to the challenge and the Council played a key role in the wider community response.
2.0IMPLEMENTING RISK MANAGEMENT
2.1Risk management forms an integral part of strategic planning in the Council, ensuring early intervention and management of uncertainty in delivering key strategic priorities.
2.2Early intervention and assessment of risks ensures that departments are able to fully prepare for existing and emerging priorities, and manage their objectives effectively against financial, reputational and performance risks, whilst meeting Team Bury and the Council’s Corporate Priorities.
2.3This approach to risk management ensures a continuous and evolving process that runs throughout the council’s core functional activities at all levels.
“Good risk management supports accountability, performance measurement and reward, thus promoting operational efficiency at all levels”. A Risk Management Standard – Institute of Risk Management.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
RISK MANAGEMENT ANNUAL REPORTDecisions | 219 KB | DownloadRead as text |
Follow Audit Committee at Bury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Oct 2026 | Minutes of the last meetingIt was agreed: That the Minutes of the last meeting held on 22 nd July 2026 be approved as a correct record and signe... | Agreed | Open |
| 19 Oct 2026 | Exclusion of press and publicIt was agreed: 1. That the press and public be excluded from the meeting under Section 100 (A)(4), Schedule 12(A) of ... | Agreed | Open |
| 22 Jul 2026 | Internal audit annual report 2025 -2026It was agreed: That the contents of the report be noted. | Agreed | Open |
| 22 Jul 2026 | Global internal audit standards self-assessment and development plan (qaip) 2026/27It was agreed: 1. That the report be noted. 2. That the Internal Audit Development Plan 2026/2027 be approved. | Agreed | Open |
| 22 Jul 2026 | Internal audit progress reportIt was agreed: That the report be noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.