Resolved
It was agreed: Further update reports in respect of the capital works at Royal Oldham and the North Manchester General Hospital will be provided at future meetings of the Joint Committee.
Pennine Acute NHS Trust agreed this item on Tuesday 3 October 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed: Further update reports in respect of the capital works at Royal Oldham and the North Manchester General Hospital will be provided at future meetings of the Joint Committee.
Pennine Joint Overview and Scrutiny Committee Capital report for the Royal Oldham Hospital and the North Manchester General Hospital 1.0 Overall Purpose and Business Case
1.1The enabling works project has four key objectives as follows: -
1. De-risking future development – at both the North Manchester and Royal Oldham sites to improve resilience, ease of future developments and overall capacity 2. Delivery of savings – financial and carbon emissions – specific energy targets have not yet been agreed, however financial savings are a key objective, particularly to support the Trust in delivering upon its carbon emission obligations of a 34% reduction by 2020/21 (compared to a 2007/08 baseline) 3. Improving resilience – ensuring operational continuity and reducing risk associated with aging infrastructure 4. Addressing backlog – where possible, the address backlog maintenance as part of this project.
1.2Funding of £10m was allotted to the Enabling Works project based on an SOC drafted in Nov 2016. [Extract: The infrastructure enabling work is essential and there are benefits to commencing this work as soon as possible to reduce the overall construction programmes. This work can then run in parallel to the preparation of business cases and reduces the overall programme thus bringing forward the ability to deliver the benefits]. A full business case will be submitted in early 2018 for detailed approval of the full defined scope and installation contract.
2.0Scope
2.1The scope of the project while defined has a degree of flexibility. The scope of possible improvement works at the Trust not surprisingly exceeds the available funding (due to the age of the estate), however, the project team is focussed on maximising the beneficial impact of the capital investment. A summary of the scope is detailed below.
North Manchester General Hospital The Royal Oldham Hospital
Capital Works Steam rationalisation to remove a risk of Provide a new boilerhouse and boiler plant the poor condition service ducts at NMGH Part refurbishment of the boiler plant and De-risk the site based upon the technical preparation of the services for future site risks identified development Rationalise the services in readiness for De-centralisation of services, where future site rationalisation and where feasible as part of this project. feasible in this project The remainder to be included in the future Prepare the site services infrastructure for development projects. future development.
Energy Efficiency measures
26 September 2017 Pennine Joint Overview and Scrutiny Committee Capital report for the Royal Oldham Hospital and the North Manchester General Hospital Improved metering New combined heat and power (CHP) plant Proposal to adopt a new water bore hole Energy efficient lighting Energy efficient lighting Building management system (BMS) BMS optimisation optimisation
Demolition Works Various defined redundant, out-dated buildings and structures
3.0Project Structure and Implementation
3.1A detailed Project Execution Plan has been prepared which defines the project scope, team, structure, programme, stakeholders, budget and controls. Project governance has been put in place with defined roles and a Project Board to provide oversight, leadership, direction and a focus for decision making and escalation. The Project Board meets monthly, the Senior Responsible Owner is Lindsay McCluskie. Change Control, including authorised expenditure of contingency is via the Project Board. Graham Lord, Head of Capital Projects is responsible for stakeholder engagement. Day to day management is via a defined Project Manager who can reach out to immediate colleagues for support in delivering the project.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL REPORT FOR THE ROYAL OLDHAM HOSPITAL AND THE NORTH MANCHESTER GENERAL HOSPITALDecisions | 131 KB | DownloadRead as text |
Follow Pennine Acute NHS Trust at Bury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Sep 2021 | Appointment of chairIt was agreed: That Councillor Linda Robinson be confirmed as Chair to the Joint Health Overview and Scrutiny Committ... | Agreed | Open |
| 6 Sep 2021 | Elective care recovery programmeIt was agreed: That an update presentation would be brought to a future meeting of the Committee. | Agreed | Open |
| 6 Sep 2021 | Future of the joint health overview and scrutiny committeeIt was agreed: 1. That Bury, Rochdale and Oldham Councils would continue to meet as a new Joint Committee. 2. That th... | Agreed | Open |
| 15 Sep 2020 | Pennine acute trust - transaction programme updateIt was agreed: 1. Pat Crowley, Chief Executive Pennine Acute Trust and Gavin Barclay, Director of Transaction be than... | Agreed | Open |
| 15 Sep 2020 | Urgent care updateIt was agreed: 1. Steve Taylor and Zeph Curwen be thanked for the update. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.