Audit Progress Report 1. Audit Progress 2. National Publications
24 July 2023 2 Section 01: Audit Progress Audit Progress Purpose of this report This report provides the Audit Committee with an update on progress in delivering our responsibilities as your external auditors.
Audit progress 2020/21 audit Our final remaining responsibility relates to the Authority’s whole of government accounts (WGA) return. We have received the NAO group instructions and are currently waiting final confirmation that no further audits are to be sampled and the 2020/21 WGA has closed. Once we receive this confirmation, we will issue our Audit Certificate to formally close the 2020/21 audit.
2021/22 financial statements audit We presented our Audit Completion Report in March 2023. A number of items were shown as outstanding. We are currently agreeing a timetable for completing this remaining work with the Authority’s finance team as follows: Outstanding areas currently outstanding are: • Agreement of PP&E amendments • National and GMPF pensions accounting issues • Consolidated Accounts queries • Resolution of queries from the technical review of the financial statement • Audit completion including manager, key audit partner and our Engagement Quality review. We will issue a follow up letter to this Committee following the completion of the outstanding work. 2021/22 VFM Our work is in progress. We received much of the information and supporting evidence from the Council during April. However, further supporting evidence has been received in the last few weeks and we are currently reviewing this.
24 July 2023 4 Audit Progress Members are reminded that, as we reported previously, we have identified two risks of significant weakness in respect of the: • Council’s arrangements for financial reporting; and • Outcome of the Ofsted inspection of children’s services. We plan to complete and report our Value for Money arrangements work alongside the remaining aspects of work on the financial statements.
2022/23 audit. The Council published its draft Accounts and annual governance statement on 31st May 2023, in line with the statutory timetable. Our planning for the audit of these financial statements is now underway. We will agree a detailed timetable for our work following resolution of the outstanding areas of work on 2021/22. We highlight for the Audit Committee a change to an auditing standard (known as ISA 315) which applies from 2022/23. We have included, at section 3 of this report, a summary of the changes and the expected impact on our audit work.
24 July 2023 5 Section 02: National Publications National publications Publication/update Key points
Chartered Institute of Public Finance and Accountability (CIPFA)
CiPFA Bulletin 14 Supplement – The Triennial Valuation and 1 Covers the impact of the triennial valuation statements on IAS 19 Employee benefits reporting IAS 19 Reporting CIPFA Bulletin 14: Closure of the 2022/23 Financial 2 Provides advice on emerging or urgent accounting issues. Statements Insourcing in the Public Sector: A Practical Guide (2022 3 Guidance for practitioners edition) CIPFA Bulletin 12 Accounting for Infrastructure Assets Covers the issues to be considered regarding the temporary solution for the accounting and reporting issues relating to infrastructure 4 Temporary Solution assets
Department for Levelling up Housing and communities
5 Local Government Finance settlement Final local government finance settlement 2023-24
Cross Sectoral
House of Commons Committee of Public Accounts report: The Public Accounts Committee (PAC) has published its report on Timeliness of local auditor reporting, following a hearing in March. 6 Timeliness of local auditor reporting The report sets out the committee’s conclusions and recommendations.
Public Sector Audit Appointments Ltd
7 Directory of Auditor Appointments from 2023/24 Auditor appointments for PSAA opted-in bodies
8 Publication of the 2022/23 fee scale External audit fees for 2022/23
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
External Audit UpdateDecisions | 412 KB | DownloadRead as text |
Follow Audit Committee at Bury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Oct 2026 | Minutes of the last meetingIt was agreed: That the Minutes of the last meeting held on 22 nd July 2026 be approved as a correct record and signe... | Agreed | Open |
| 19 Oct 2026 | Exclusion of press and publicIt was agreed: 1. That the press and public be excluded from the meeting under Section 100 (A)(4), Schedule 12(A) of ... | Agreed | Open |
| 22 Jul 2026 | Internal audit annual report 2025 -2026It was agreed: That the contents of the report be noted. | Agreed | Open |
| 22 Jul 2026 | Global internal audit standards self-assessment and development plan (qaip) 2026/27It was agreed: 1. That the report be noted. 2. That the Internal Audit Development Plan 2026/2027 be approved. | Agreed | Open |
| 22 Jul 2026 | Internal audit progress reportIt was agreed: That the report be noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.